2500 N LILLYVALE AVE 90032

Certificate Information: 2500 N LILLYVALE AVE 90032

Application / Permit
19010-10000-04950
Plan Check / Job No.
B19LA23676
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
SINGLE NEW BUILDING-CONSTRUCTION ADDED ONTO TRACT 34415, PARCEL LOT #3, OF THE "FRIFOLS" MULTI-BUILDING SITE. OCCUPANCY: DATA CENTER FOR COMPUTER EQUIPMENT AND POWER WITH REDUNDANT BACKUP. CONSTRUCTION: CONCRETE MACONRY BEARING, CONC. ROOF SLABS ON STEEL DECK. 1 OF 2
Permit Issued
Issued on 10/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 SERGIO GUTIERREZ
Corrections Issued 11/18/2019 SERGIO GUTIERREZ
Quality Review Completed 12/2/2019 KESETE HAREGOT
Disabled Access Plans Picked Up 12/26/2019 APPLICANT
Applicant returned to address corrections 4/16/2020 SERGIO GUTIERREZ
Plan Check Approved 5/5/2020 SERGIO GUTIERREZ
Issued 10/16/2020 APPLICANT
Building Plans Picked Up 10/22/2020 APPLICANT
CofO in Progress 1/28/2022 TED RIES
CofO Issued 1/28/2022 TED RIES
Permit Finaled 1/28/2022 TED RIES

Permit Application Clearance Information

DAS Clearance Cleared 1/31/2020 SERGIO GUTIERREZ
Green Code Cleared 2/7/2020 DONALD CRICHLOW
Address approval Cleared 2/13/2020 JEANETTE VONG
BHO/Hillside ordinance Cleared 2/13/2020 JEANETTE VONG
BHO/Hillside ordinance Cleared 2/13/2020 JEANETTE VONG
BHO/Hillside ordinance Cleared 2/13/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/13/2020 JEANETTE VONG
Highway dedication Cleared 2/13/2020 JEANETTE VONG
Historic Resource Verification Cleared 2/13/2020 MICAELA TORRES-GIL
Sewer availability Cleared 2/13/2020 JEANETTE VONG
Redevelopment Project Area Cleared 2/18/2020 GISELLE CORELLA
Low Impact Development Cleared 3/3/2020 ORVAL HERNANDEZ-MARCI
Hydrant and Access approval Cleared 3/11/2020 GILBERT URREA
Roof/Waste drainage to street Cleared 4/15/2020 NGOC KIEM
GPI Written Notices Cleared 4/24/2020 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 4/24/2020 SERGIO GUTIERREZ

Contact Information

Architect Mc, Cann, Richard Frank; Lic. No.: C7671 40 EAST MONTECITO AVENUE      SIERRA MADRE, CA 91024
Contractor Grifols Biologicals Llc; Lic. No.: 1040892-B 2410 LILLYVALE AVE      LOS ANGELES, CA 90032
Engineer Garza,, Jaime; Lic. No.: S5456 4022 BERENICE PLACE      LOS ANGELES, CA 90031

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/25/2020 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 12/4/2020 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 12/8/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 12/9/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 12/17/2020 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 1/22/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/10/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/11/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 2/18/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Masonry 2/23/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 2/24/2021 Conditional Approval RONALD PACHECO
Deputy Reinf. Masonry 2/25/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Masonry 2/26/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/2/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/3/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/4/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/5/2021 Conditional Approval RONALD PACHECO
Masonry Wall/Backfill 3/5/2021 Partial Approval RONALD PACHECO
Deputy Reinf. Masonry 3/8/2021 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 3/9/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/9/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/10/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/11/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/12/2021 Approved RONALD PACHECO
Excavation/Setback/Form/Re-Bar 3/12/2021 Partial Approval RONALD PACHECO
Deputy Reinf. Masonry 3/15/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Masonry 3/16/2021 Conditional Approval RONALD PACHECO
Deputy Reinf. Masonry 3/17/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/18/2021 Conditional Approval DANIEL COLLINS
Masonry Wall/Backfill 3/18/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/19/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/22/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/23/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/24/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/25/2021 Conditional Approval RONALD PACHECO
Deputy Reinf. Masonry 3/26/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 3/26/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/30/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 3/31/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 3/31/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 4/1/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/5/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/6/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/7/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 4/8/2021 Conditional Approval RONALD PACHECO
Deputy Steel/Welding 4/12/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/12/2021 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 4/13/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/15/2021 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 4/22/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/27/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/29/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 5/10/2021 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 5/11/2021 Conditional Approval LANNY MERRICK
Drywall Nailing 5/18/2021 Approved DANIEL COLLINS
Green Building Rough 5/18/2021 Approved DANIEL COLLINS
Wall Anchors 5/18/2021 Approved DANIEL COLLINS
Deputy Drilled-In Anchors 5/24/2021 Conditional Approval DANIEL COLLINS
Deputy Grading 5/24/2021 Conditional Approval DANIEL COLLINS
Pre-Inspection 6/15/2021 Partial Inspection DANIEL COLLINS
Final 9/10/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 9/10/2021 Approved DANIEL COLLINS
Green Building Final 9/10/2021 Approved DANIEL COLLINS
Reinforced Masonry Frame 9/10/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV No Gas DANIEL COLLINS
Smoke Detectors 9/10/2021 Approved DANIEL COLLINS
Structural Steel Frame 9/10/2021 Approved DANIEL COLLINS
Verify Sprinkler Sign Off 9/10/2021 Approved DANIEL COLLINS