5110 W ORANGE PL 90008

Certificate Information: 5110 W ORANGE PL 90008

Application / Permit
19010-10000-04884
Plan Check / Job No.
B19LA23397
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
NEW CARPORT PER CITY STANDARD
Permit Issued
Issued on 4/24/2020
Issuing Office
Current Status
CofO Issued on 12/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2019 APPLICANT
Assigned to Plan Check Engineer 11/8/2019 EMMANUEL MARTINEZ
Corrections Issued 11/18/2019 EMMANUEL MARTINEZ
Green Plans Picked Up 11/22/2019 APPLICANT
Quality Review Completed 11/27/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 12/11/2019 APPLICANT
Plan Check Approved 2/25/2020 EMMANUEL MARTINEZ
Issued 4/24/2020 APPLICANT
CofO in Progress 11/21/2025 LUIS CASTRO
No Progress 11/21/2025 MICHAEL LEWIS
CofO in Progress 11/21/2025 MICHAEL LEWIS
Permit Finaled 12/17/2025 DEROLD HAUFF
CofO Issued 12/17/2025 DEROLD HAUFF
Permit Finaled 12/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2019 JAMES KHO
Low Impact Development Cleared 2/5/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/5/2020 JEANETTE VONG
Hydrant and Access approval Cleared 2/19/2020 GEORGE SUCHAND
GPI Written Notices Cleared 2/25/2020 EMMANUEL MARTINEZ
Grading Pre-Inspection Cleared 2/25/2020 EMMANUEL MARTINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2023 Not Ready for Inspection ANTHONY EGSON
Insulation 4/15/2025 Not Ready for Inspection LUIS CASTRO
Drywall Nailing 4/22/2025 Not Ready for Inspection ALEX COLIN
Drywall Nailing 4/25/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 11/18/2025 Approved LUIS CASTRO
Final 11/18/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 11/18/2025 Approved LUIS CASTRO
Green Building Final 11/18/2025 Approved LUIS CASTRO
Green Building Rough 11/18/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Approved LUIS CASTRO
Service/Power Release 11/18/2025 Approved LUIS CASTRO
Smoke Detectors 11/18/2025 Approved LUIS CASTRO
ELECTRICAL-Final 11/20/2025 Approved LUIS CASTRO
Final 11/20/2025 OK to Issue CofO LUIS CASTRO