1132 N ORANGE DR 90038

Certificate Information: 1132 N ORANGE DR 90038

Application / Permit
19010-10000-04877
Plan Check / Job No.
B19LA23367
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5-STORY, TYPE IIIA, 24-UNIT APARTMENT BUILDING OVER 1 LEVEL, TYPE IA, BASEMENT PARKING GARAGE. AFFORDABLE DENSITY BONUS HOUSING PROJECT RESTRICTING 3 VLI UNITS.
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 KESETE HAREGOT
Corrections Issued 11/25/2019 KESETE HAREGOT
Quality Review Completed 12/13/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 12/24/2019 APPLICANT
Applicant returned to address corrections 5/15/2020 KESETE HAREGOT
Applicant returned to address corrections 1/13/2021 KESETE HAREGOT
Plan Check Approved 3/15/2021 KESETE HAREGOT
Issued 3/15/2021 APPLICANT
TCO Issued (Expire Date: 06-15-2025) 12/17/2024 ADAM BURGESS
TCO Issued (Expire Date: 12-01-2025) 6/4/2025 ERNESTO CORRAL
CofO in Progress 1/28/2026 MARTIN TAVITIAN
Permit Finaled 1/28/2026 ERNESTO CORRAL
CofO Issued 1/28/2026 ERNESTO CORRAL
Permit Finaled 1/28/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 12/27/2019 JEANIE LAM
Trees in Parkway Cleared 2/6/2020 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 2/10/2020 ERIK BEASLEY
Highway dedication Cleared 2/10/2020 ERIK BEASLEY
Permit Cleared 2/10/2020 ERIK BEASLEY
Sewer availability Cleared 2/10/2020 ERIK BEASLEY
Work Adjacent to Public Way Cleared 3/6/2020 ARMEN SARKISIAN
Hydrant and Access approval Cleared 4/14/2020 ROBERT DUFF
DCP conditions approval Cleared 4/23/2020 MICHAEL ZIRBES
Density Bonus 12.22.A.25 Cleared 4/23/2020 MICHAEL ZIRBES
CPC Cleared 9/10/2020 NOAH MCCOY
Frnt yard landscape/Water mgmt Cleared 9/10/2020 NOAH MCCOY
Opn space landscape/Water mgmt Cleared 9/10/2020 NOAH MCCOY
Low Impact Development Cleared 9/15/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/23/2020 WALLIE JONG
DAS Clearance Cleared 11/16/2020 KESETE HAREGOT
Fire Marshall Fire Life Safety Cleared 11/18/2020 WILLIAM JOHNS
Green Code Cleared 1/7/2021 KESETE HAREGOT
CPC Cleared 2/2/2021 NOAH MCCOY
Miscellaneous Cleared 2/2/2021 NOAH MCCOY
Building over 3-story or 36-ft Cleared 3/15/2021 CALOSHA APPROVED

Contact Information

Architect Robert,, Christian J M; Lic. No.: C34175 4200 SEPULVEDA BLVD SUITE 104   C/O OFFICEUNTITLED INC.    CULVER CITY, CA 90230
Contractor Ketter Construction Inc; Lic. No.: 958623-B 12650 RIVERSIDE DRIVE #100      STUDIO CITY, CA 91607
Engineer Chen,, Wei-Chih; Lic. No.: S5150 1732 DATE AVE      TORRANCE, CA 90503
Engineer Kempton,, Justin John; Lic. No.: GE2385 5736 CORPORATE AVE      CYPRESS, CA 90630
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Nelson,, William Mc Kee; Lic. No.: S3417 5 DELLWOOD      DOVE CANYON, CA 92679
Landscape Architect Margulies,, Esther; Lic. No.: LA3752 1131 SUPERBA AVENUE      VENICE, CA 90291

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2021 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 5/12/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/13/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/17/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/17/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/19/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/19/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/19/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 5/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/26/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/26/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/26/2021 Partial Inspection EDWIN GREGORYONA
Deputy Shotcrete 5/27/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/27/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 5/27/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/27/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 5/28/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/28/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/1/2021 Conditional Approval RUSSELL BONVOULOIR
Green Building Rough 7/8/2021 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 7/8/2021 Partial Approval JONATHAN QUACH
Verify Sprinkler Sign Off 7/8/2021 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 9/13/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/20/2021 Partial Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/6/2021 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 10/7/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/7/2021 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/7/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/8/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/3/2021 Conditional Approval TED RIES
Green Building Rough 11/4/2021 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 11/4/2021 Partial Approval TED RIES
Verify Sprinkler Sign Off 11/4/2021 Not Ready for Inspection TED RIES
Deputy Reinf. Masonry 11/5/2021 Conditional Approval TED RIES
Deputy Reinf. Masonry 11/8/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/9/2021 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 11/9/2021 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/9/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 11/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/17/2021 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/29/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/30/2021 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 11/30/2021 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 11/30/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 11/30/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 12/1/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 12/3/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 12/6/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/7/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/16/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/5/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 1/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/10/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/3/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 2/3/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/22/2022 Conditional Approval ERNESTO CORRAL
Wood Frame 2/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 3/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 3/10/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 3/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/22/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 3/24/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/1/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Inspection EDWIN GREGORYONA
Deputy Drilled-In Anchors 4/6/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/29/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 5/13/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/20/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 6/8/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 6/17/2022 Conditional Approval WINSTON DUNNING
Wood Frame 6/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 6/27/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 6/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/1/2022 Conditional Approval ERNESTO CORRAL
Wood Frame 7/11/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/13/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 7/13/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 7/14/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 7/19/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 7/22/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/26/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/1/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 8/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/15/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 8/15/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 8/18/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 8/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 9/1/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/12/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 9/14/2022 Partial Approval EDWIN GREGORYONA
Wall Anchors 9/26/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 9/26/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 9/28/2022 Approved EDWIN GREGORYONA
Structural Steel Frame 9/28/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 9/28/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 10/4/2022 Partial Inspection GREGORY POMISH
Wood Frame 10/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 10/12/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 10/17/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 12/5/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 2/3/2023 Partial Approval EDWIN GREGORYONA
Insulation 2/9/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/10/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/14/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/21/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 2/21/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/27/2023 Conditional Approval MICHAEL ROSENBERG
Wood Frame 2/28/2023 Partial Approval GREGORY POMISH
Wood Frame 3/3/2023 Partial Inspection EDWIN GREGORYONA
Wood Frame 3/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 5/1/2023 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 5/1/2023 Partial Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 5/4/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 5/15/2023 Partial Inspection EDWIN GREGORYONA
Wood Frame 5/24/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 6/21/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 6/23/2023 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 8/1/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/7/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/14/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/17/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/6/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 9/14/2023 Not Ready for Inspection GREGORY POMISH
Insulation 9/18/2023 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 9/21/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/6/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/11/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/28/2023 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 12/21/2023 Partial Inspection EDWIN GREGORYONA
Wood Frame 12/26/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 12/29/2023 Partial Inspection EDWIN GREGORYONA
Wood Frame 2/15/2024 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 2/26/2024 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 2/27/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 3/6/2024 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/2/2024 Approved EDWIN GREGORYONA
Green Building Rough 5/7/2024 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/7/2024 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/7/2024 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 5/14/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 6/3/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 9/13/2024 Partial Inspection DAVID BURKHEAD
Final 9/23/2024 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 9/23/2024 Approved EDWIN GREGORYONA
Green Building Final 9/23/2024 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 9/23/2024 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 9/23/2024 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 9/23/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 9/23/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 10/25/2024 Corrections Issued EDWIN GREGORYONA
Final 11/13/2024 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 11/13/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved EDWIN GREGORYONA
Special/Order Compliance 12/9/2024 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 5/16/2025 Approved EDWIN GREGORYONA
Special/Order Compliance 6/2/2025 Approved EDWIN GREGORYONA
Special/Order Compliance 11/4/2025 Approved EDWIN GREGORYONA
Special/Order Compliance 11/4/2025 Partial Approval SCOTT SOBEL
Final 1/28/2026 OK to Issue CofO MARTIN TAVITIAN