3034 S 5TH AVE 90018

Certificate Information: 3034 S 5TH AVE 90018

Application / Permit
19010-10000-04867
Plan Check / Job No.
B19LA23330
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 1-story Accesorry Dwelling Unit per AB 494 and SB 229.
Permit Issued
Issued on 3/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 HELEN NGUYEN
Green Plans Picked Up 11/15/2019 APPLICANT
Corrections Issued 11/18/2019 HELEN NGUYEN
Quality Review Completed 11/23/2019 YOUNG KIM
Building Plans Picked Up 12/4/2019 APPLICANT
Applicant returned to address corrections 1/8/2020 HELEN NGUYEN
Plan Check Approved 2/19/2020 HELEN NGUYEN
Issued 3/17/2020 LADBS
CofO in Progress 11/6/2020 STUART CHAPMAN
Permit Finaled 2/2/2021 DEROLD HAUFF
CofO Issued 2/2/2021 DEROLD HAUFF
Permit Finaled 2/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 11/25/2019 COLIN LOREDO
Address approval Cleared 1/8/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 1/8/2020 ELAINE LEI
Hydrant and Access approval Cleared 1/8/2020 JEREMY CARTER
Roof/Waste drainage to street Cleared 1/8/2020 ELAINE LEI
Sewer availability Cleared 1/8/2020 ELAINE LEI
HPOZ Cleared 1/17/2020 LYDIA CHAPMAN
Miscellaneous Cleared 1/17/2020 LYDIA CHAPMAN
Miscellaneous Cleared 1/17/2020 LYDIA CHAPMAN
ZI Cleared 1/17/2020 LYDIA CHAPMAN

Contact Information

Contractor Ammex Construction; Lic. No.: 1011784-B 12869 MONTFORD STREET      PACOIMA, CA 91331
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/31/2020 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/19/2020 Approved STUART CHAPMAN
Insulation 8/19/2020 Partial Approval STUART CHAPMAN
PLUMBING-Rough 8/19/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 9/9/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 9/9/2020 Corrections Issued STUART CHAPMAN
Rough-Elec/Plmb/HVAC 9/9/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 9/9/2020 Approved STUART CHAPMAN
Insulation 9/22/2020 Conditional Approval STUART CHAPMAN
Drywall Nailing 9/24/2020 Approved STUART CHAPMAN
Green Building Rough 9/24/2020 Approved STUART CHAPMAN
Shower Pan 10/7/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/2/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 11/2/2020 Approved STUART CHAPMAN
Final 11/2/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Final 11/2/2020 Approved STUART CHAPMAN
HVAC-Final 11/2/2020 Approved STUART CHAPMAN
PLUMBING-Final 11/2/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved STUART CHAPMAN
Service/Power Release 11/2/2020 Approved STUART CHAPMAN
Smoke Detectors 11/2/2020 Approved STUART CHAPMAN
Final 11/5/2020 OK to Issue CofO STUART CHAPMAN