8582 N TELFAIR AVE 91352

Certificate Information: 8582 N TELFAIR AVE 91352

Application / Permit
19010-10000-04856
Plan Check / Job No.
B19LA23219
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
(N) 1 STORY WAREHOUSE
Permit Issued
Issued on 5/27/2022
Issuing Office
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 HERNAN ARREOLA
Green Plans Picked Up 12/3/2019 APPLICANT
Disabled Access Plans Picked Up 12/6/2019 APPLICANT
Corrections Issued 12/9/2019 HERNAN ARREOLA
Quality Review Completed 12/10/2019 BILL STUTSMAN
Building Plans Picked Up 12/11/2019 APPLICANT
Applicant returned to address corrections 12/27/2019 HERNAN ARREOLA
Plan Check Approved 5/19/2022 HERNAN ARREOLA
Issued 5/27/2022 APPLICANT
CofO in Progress 6/26/2025 GREGORY POMISH
CofO in Progress 6/26/2025 JEFFREY DURAN
Permit Finaled 12/2/2025 RICKEY JACKSON
CofO Issued 12/2/2025 RICKEY JACKSON
Permit Finaled 12/2/2025 RICKEY JACKSON

Permit Application Clearance Information

DAS Clearance Cleared 1/2/2020 SHINE LIN
Hydrant and Access approval Cleared 1/3/2020 JEREMY CARTER
Green Code Cleared 1/6/2020 VIVIAN LAO
Trees in Parkway Cleared 1/17/2020 ADRIAN SANCHEZ
Certificate of Compliance Cleared 1/24/2022 MARC WOERSCHING
"Q" conditions Cleared 1/28/2022 DALIA MOKAYED
ZI Cleared 1/28/2022 DALIA MOKAYED
ZI Cleared 1/28/2022 DALIA MOKAYED
Low Impact Development Cleared 3/1/2022 JORGE MEJIA LEMUS
Highway dedication Cleared 3/2/2022 LEE GUILBEAUX
Sewer availability Cleared 3/2/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/7/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/8/2022 LEE GUILBEAUX

Contact Information

Contractor Savs Enterprises; Lic. No.: 814956-B 4500 SUNNYCREST DRIVE      LOS ANGELES, CA 90065
Engineer Keshishian,, Nejdeh; Lic. No.: C38341 2654 RISA DR      GLENDALE, CA 91208

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2022 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 7/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/29/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 8/15/2022 Corrections Issued ROBERT DAVIS
Deputy Drilled-In Anchors 8/16/2022 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 8/17/2022 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 9/16/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/28/2022 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 9/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 9/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/3/2022 No Access for Inspection DANNY RODRIGUEZ
Green Building Rough 10/3/2022 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/4/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 11/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/29/2022 Conditional Approval JEFFREY DURAN
Green Building Rough 11/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 11/30/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/8/2022 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 12/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/9/2022 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 12/12/2022 No Access for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/14/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/28/2022 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 12/29/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 12/30/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Masonry 2/3/2023 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 2/3/2023 Corrections Issued DANNY RODRIGUEZ
Special/Order Compliance 2/3/2023 Not Ready for Inspection STEVEN LEVITT
Reinforced Masonry Frame 2/9/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 2/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/3/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/3/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/3/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Approved ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Corrections Issued DANNY RODRIGUEZ
Pre-Inspection 12/27/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 12/28/2023 Corrections Issued DANNY RODRIGUEZ
Special/Order Compliance 2/1/2024 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/19/2024 Partial Approval DANNY RODRIGUEZ
Wood Frame 3/27/2024 No Access for Inspection DANNY RODRIGUEZ
Wood Frame 4/8/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/17/2024 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 4/18/2024 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Final 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Green Building Final 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Green Building Rough 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 9/26/2024 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Structural Steel Frame 9/26/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/26/2024 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 12/12/2024 No Access for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/1/2025 Not Ready for Inspection DANNY RODRIGUEZ
Final 5/1/2025 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/1/2025 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 5/1/2025 Approved DANNY RODRIGUEZ
Green Building Rough 5/1/2025 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 5/1/2025 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 5/1/2025 Approved DANNY RODRIGUEZ
Structural Steel Frame 5/1/2025 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/1/2025 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 6/2/2025 Approved GREGORY POMISH
Final 6/2/2025 OK to Issue CofO GREGORY POMISH
Footing/Foundation/Slab 6/2/2025 Approved GREGORY POMISH
Reinforced Masonry Frame 6/2/2025 Approved GREGORY POMISH
Structural Steel Frame 6/2/2025 Approved GREGORY POMISH
Verify Sprinkler Sign Off 6/2/2025 Approved GREGORY POMISH