11619 W COLLINS ST 91601

Certificate Information: 11619 W COLLINS ST 91601

Application / Permit
19010-10000-04832
Plan Check / Job No.
B19LA23039
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING (ADU) PER AB 494 AND SB 229
Permit Issued
Issued on 3/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 SERGIO GUTIERREZ
Corrections Issued 12/2/2019 SERGIO GUTIERREZ
Green Plans Picked Up 12/10/2019 APPLICANT
Quality Review Completed 12/24/2019 KESETE HAREGOT
Building Plans Picked Up 12/30/2019 APPLICANT
Applicant returned to address corrections 2/4/2020 SERGIO GUTIERREZ
Plan Check Approved 2/28/2020 SERGIO GUTIERREZ
Issued 3/2/2020 LADBS
CofO in Progress 6/2/2021 THOMAS FINNILA
Permit Finaled 9/14/2021 MICHAEL SMITH
CofO Issued 9/14/2021 MICHAEL SMITH
Permit Finaled 9/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 1/16/2020 VIVIAN LAO
Address approval Cleared 1/22/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 1/22/2020 JEREMY CARTER
Eng Process Fee Ord 176,300 Cleared 1/28/2020 THOMAS LANG
Sewer availability Cleared 1/28/2020 THOMAS LANG
Low Impact Development Cleared 1/30/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/30/2020 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Beck,, Charles Joseph; Lic. No.: C19289 129 WEST PONDERA STREET      LANCASTER, CA 93534

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/31/2020 Approved JEFFREY PARD
PLUMBING-Rough 4/6/2020 Not Ready for Inspection JEFFREY PARD
Special/Order Compliance 4/6/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 4/8/2020 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval JEFFREY PARD
Gas Test 4/16/2020 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 5/29/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 5/29/2020 Corrections Issued JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Approved JEFFREY PARD
Green Building Rough 5/29/2020 Approved JEFFREY PARD
HVAC-Rough 5/29/2020 Approved JEFFREY PARD
PLUMBING-Rough 5/29/2020 Approved JEFFREY PARD
Verify Sprinkler Sign Off 5/29/2020 Approved JEFFREY PARD
Wood Frame 5/29/2020 Approved JEFFREY PARD
Insulation 6/4/2020 Corrections Issued JEFFREY PARD
Interior/Exterior Lathing 6/4/2020 Approved JEFFREY PARD
Insulation 6/9/2020 Not Ready for Inspection JEFFREY PARD
Deputy Wood Construction 6/10/2020 Approved JEFFREY PARD
Insulation 6/10/2020 Approved JEFFREY PARD
Drywall Nailing 6/17/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/17/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 7/14/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 12/1/2020 Approved THOMAS FINNILA
Final 12/1/2020 Corrections Issued THOMAS FINNILA
Green Building Final 12/1/2020 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/1/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 12/1/2020 Corrections Issued THOMAS FINNILA
Final 1/7/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Final 1/7/2021 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/7/2021 SGSOV Approved THOMAS FINNILA
Service/Power Release 1/7/2021 Corrections Issued THOMAS FINNILA
Smoke Detectors 1/7/2021 Not Ready for Inspection THOMAS FINNILA
Final 3/16/2021 Corrections Issued THOMAS FINNILA
Green Building Final 3/16/2021 Approved THOMAS FINNILA
Service/Power Release 3/16/2021 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 3/16/2021 Approved THOMAS FINNILA
Final 4/30/2021 Partial Inspection RICHARD DOCKUS
Final 5/10/2021 Partial Inspection THOMAS FINNILA
Service/Power Release 5/10/2021 Not Ready for Inspection THOMAS FINNILA
Final 5/17/2021 Partial Inspection THOMAS FINNILA
Service/Power Release 5/17/2021 Not Ready for Inspection THOMAS FINNILA
Final 5/24/2021 Partial Inspection THOMAS FINNILA
Service/Power Release 5/24/2021 Not Ready for Inspection THOMAS FINNILA
Final 6/2/2021 OK to Issue CofO THOMAS FINNILA
Service/Power Release 6/2/2021 Approved THOMAS FINNILA
Special/Order Compliance 8/21/2021 Corrections Issued MICHAEL PELHAM