552-552 1/2 W 47TH ST 90037

Certificate Information: 552-552 1/2 W 47TH ST 90037

Application / Permit
19010-10000-04784
Plan Check / Job No.
B19LA22859
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
FOR NEW 3-STORY DUPLEX W/ATTCAHED GARAGE AT REAR OF LOT 2 OF 2
Permit Issued
Issued on 4/6/2020
Issuing Office
Current Status
CofO Issued on 10/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 VU NGUYEN
Green Plans Picked Up 11/8/2019 APPLICANT
Corrections Issued 11/13/2019 VU NGUYEN
Quality Review Completed 11/26/2019 JOSE RODRIGUEZ
Plan Check Approved 1/10/2020 VU NGUYEN
Issued 4/6/2020 APPLICANT
Building Plans Picked Up 4/7/2020 APPLICANT
CofO in Progress 10/5/2021 HORACE FULTZ
Permit Finaled 10/5/2021 DEROLD HAUFF
CofO Issued 10/5/2021 DEROLD HAUFF
Permit Finaled 10/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/18/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 11/18/2019 EMIL KYUPELYAN
Green Code Cleared 11/18/2019 KHEDER ALRAZAA
Green Code Cleared 11/18/2019 VU NGUYEN
Permit Cleared 11/18/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/18/2019 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 11/19/2019 SOPHIE GABEL-SCHEINBAU
Hydrant and Access approval Cleared 11/19/2019 JEREMY CARTER
Low Impact Development Cleared 11/21/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 11/22/2019 ERIK BEASLEY
Trees in Parkway Cleared 11/27/2019 ADRIAN SANCHEZ

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 57 W PALM STREET      ALTADENA, CA 910014368
Engineer Chao,, Chun-Ching; Lic. No.: C57893 PO BOX 8422      ROWLAND HEIGHTS, CA 91748
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/9/2020 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/21/2020 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 4/22/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/29/2020 Partial Approval FREDDIE RIVERA
Deputy Wood Construction 9/9/2020 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 9/16/2020 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 9/16/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 12/9/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/17/2020 Approved ROBERT MCDOWELL
Green Building Rough 12/17/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 12/17/2020 Approved ROBERT MCDOWELL
MERV13>=Rough 12/17/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 12/17/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 12/17/2020 Approved ROBERT MCDOWELL
Insulation 12/23/2020 Approved ROBERT MCDOWELL
Drywall Nailing 1/19/2021 Approved ROBERT MCDOWELL
Service/Power Release 6/4/2021 Approved ROBERT MCDOWELL
Sewer 6/4/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 8/9/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 8/9/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Final 8/11/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 8/11/2021 Approved JOAQUIN GREENOUGH
MERV13>=Final 8/11/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 8/11/2021 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 8/11/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 9/7/2021 Approved JOAQUIN GREENOUGH
Final 9/7/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Final 9/7/2021 Approved JOAQUIN GREENOUGH
MERV13>=Final 9/7/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Final 9/7/2021 Approved JOAQUIN GREENOUGH
Service/Power Release 9/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Service/Power Release 9/9/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Final 9/15/2021 Corrections Issued JOAQUIN GREENOUGH
Final 10/5/2021 OK to Issue CofO HORACE FULTZ