214-216 E 101ST ST 90003
Certificate Information: 214-216 E 101ST ST 90003
- Application / Permit
- 19010-10000-04738
- Plan Check / Job No.
- B19LA22542
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE (TRANSITIONAL HOUSING) SEPARATE PERMIT REQUIRED FOR DEMOITION
- Permit Issued
- Issued on 6/19/2020
- Issuing Office
- Current Status
- CofO Issued on 12/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | JESSE ARELLANO |
| Corrections Issued | 11/20/2019 | JESSE ARELLANO |
| Quality Review Completed | 12/2/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 12/6/2019 | APPLICANT |
| Green Plans Picked Up | 5/11/2020 | APPLICANT |
| Plan Check Approved | 6/18/2020 | JESSE ARELLANO |
| Issued | 6/19/2020 | APPLICANT |
| CofO in Progress | 12/14/2020 | JOSEPH MCGARRY |
| Permit Finaled | 12/17/2020 | DEROLD HAUFF |
| CofO Issued | 12/17/2020 | DEROLD HAUFF |
| Permit Finaled | 12/17/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/13/2019 | JOHN CONNEALLY |
| Address approval | Cleared | 12/16/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/16/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 5/11/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 6/2/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 6/4/2020 | RENZ SORIANO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/6/2020 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 7/8/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/15/2020 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 7/15/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 7/16/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/24/2020 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/24/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 8/24/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 8/24/2020 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 8/24/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/2/2020 | Conditional Approval | EUGENE CASSIDY |
| Insulation | 9/2/2020 | Approved | EUGENE CASSIDY |
| Sewer | 9/2/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/14/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/14/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/11/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/11/2020 | Approved | JOSEPH MCGARRY |
| Final | 12/11/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 12/11/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 12/11/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 12/11/2020 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/11/2020 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 12/11/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 12/11/2020 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/11/2020 | Approved | JOSEPH MCGARRY |
| Final | 12/14/2020 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 12/14/2020 | Approved | JOSEPH MCGARRY |