214-216 E 101ST ST 90003

Certificate Information: 214-216 E 101ST ST 90003

Application / Permit
19010-10000-04738
Plan Check / Job No.
B19LA22542
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE (TRANSITIONAL HOUSING) SEPARATE PERMIT REQUIRED FOR DEMOITION
Permit Issued
Issued on 6/19/2020
Issuing Office
Current Status
CofO Issued on 12/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 JESSE ARELLANO
Corrections Issued 11/20/2019 JESSE ARELLANO
Quality Review Completed 12/2/2019 BILL STUTSMAN
Building Plans Picked Up 12/6/2019 APPLICANT
Green Plans Picked Up 5/11/2020 APPLICANT
Plan Check Approved 6/18/2020 JESSE ARELLANO
Issued 6/19/2020 APPLICANT
CofO in Progress 12/14/2020 JOSEPH MCGARRY
Permit Finaled 12/17/2020 DEROLD HAUFF
CofO Issued 12/17/2020 DEROLD HAUFF
Permit Finaled 12/17/2020 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/13/2019 JOHN CONNEALLY
Address approval Cleared 12/16/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/16/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/16/2019 EMIL KYUPELYAN
Green Code Cleared 5/11/2020 VIVIAN LAO
Low Impact Development Cleared 6/2/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 6/4/2020 RENZ SORIANO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/6/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 7/8/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 7/15/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 7/15/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Partial Approval EUGENE CASSIDY
Insulation 7/16/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/11/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/24/2020 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 8/24/2020 Approved JOSEPH MCGARRY
Green Building Rough 8/24/2020 Approved JOSEPH MCGARRY
HVAC-Rough 8/24/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 8/24/2020 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 8/24/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 8/24/2020 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 9/2/2020 Conditional Approval EUGENE CASSIDY
Insulation 9/2/2020 Approved EUGENE CASSIDY
Sewer 9/2/2020 Approved EUGENE CASSIDY
Drywall Nailing 9/14/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/14/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/11/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 12/11/2020 Approved JOSEPH MCGARRY
Final 12/11/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/11/2020 Approved JOSEPH MCGARRY
HVAC-Final 12/11/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 12/11/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/11/2020 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 12/11/2020 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 12/11/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/11/2020 Approved JOSEPH MCGARRY
Final 12/14/2020 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 12/14/2020 Approved JOSEPH MCGARRY