847-849 E 83RD ST 90001
Certificate Information: 847-849 E 83RD ST 90001
- Application / Permit
- 19010-10000-04737
- Plan Check / Job No.
- B19LA22541
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | FERNANDO FLORES |
| Green Plans Picked Up | 10/31/2019 | APPLICANT |
| Corrections Issued | 11/7/2019 | FERNANDO FLORES |
| Quality Review Completed | 11/12/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 11/18/2019 | APPLICANT |
| Plan Check Approved | 1/6/2020 | FERNANDO FLORES |
| Issued | 1/23/2020 | LADBS |
| CofO in Progress | 9/17/2020 | DAVID FEILER |
| Permit Finaled | 11/3/2020 | DEROLD HAUFF |
| CofO Issued | 11/3/2020 | DEROLD HAUFF |
| Permit Finaled | 11/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 11/25/2019 | JEREMY CARTER |
| Permit | Cleared | 11/25/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/25/2019 | ERIK BEASLEY |
| Green Code | Cleared | 12/13/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 12/13/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | JEANIE LAM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2020 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 3/24/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 3/24/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Approved | EUGENE CASSIDY |
| Insulation | 3/26/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 6/4/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/4/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/4/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 6/4/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/4/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/4/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/9/2020 | Approved | EUGENE CASSIDY |
| Insulation | 6/11/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 6/15/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/15/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/17/2020 | Approved | BRIAN CHRISTIAN |
| Sewer | 6/29/2020 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 9/15/2020 | Approved | DAVID FEILER |
| Final | 9/15/2020 | Corrections Issued | DAVID FEILER |
| Gas Test | 9/15/2020 | Approved | DAVID FEILER |
| Green Building Final | 9/15/2020 | Approved | DAVID FEILER |
| HVAC-Final | 9/15/2020 | Approved | DAVID FEILER |
| PLUMBING-Final | 9/15/2020 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 9/15/2020 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 9/15/2020 | Approved | DAVID FEILER |
| Final | 9/17/2020 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 9/17/2020 | Approved | DAVID FEILER |