847-849 E 83RD ST 90001

Certificate Information: 847-849 E 83RD ST 90001

Application / Permit
19010-10000-04737
Plan Check / Job No.
B19LA22541
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 FERNANDO FLORES
Green Plans Picked Up 10/31/2019 APPLICANT
Corrections Issued 11/7/2019 FERNANDO FLORES
Quality Review Completed 11/12/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 11/18/2019 APPLICANT
Plan Check Approved 1/6/2020 FERNANDO FLORES
Issued 1/23/2020 LADBS
CofO in Progress 9/17/2020 DAVID FEILER
Permit Finaled 11/3/2020 DEROLD HAUFF
CofO Issued 11/3/2020 DEROLD HAUFF
Permit Finaled 11/3/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/25/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/25/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 11/25/2019 JEREMY CARTER
Permit Cleared 11/25/2019 ERIK BEASLEY
Sewer availability Cleared 11/25/2019 ERIK BEASLEY
Green Code Cleared 12/13/2019 COLIN LOREDO
Low Impact Development Cleared 12/13/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/13/2019 JEANIE LAM

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/4/2020 Approved EUGENE CASSIDY
Underground Mechanical 3/24/2020 Approved EUGENE CASSIDY
Wood Frame 3/24/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Approved EUGENE CASSIDY
Insulation 3/26/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/4/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 6/4/2020 Approved EUGENE CASSIDY
Green Building Rough 6/4/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 6/4/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 6/4/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 6/4/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/9/2020 Approved EUGENE CASSIDY
Green Building Rough 6/9/2020 Approved EUGENE CASSIDY
Insulation 6/11/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 6/15/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 6/15/2020 Corrections Issued BRIAN CHRISTIAN
Interior/Exterior Lathing 6/17/2020 Approved BRIAN CHRISTIAN
Sewer 6/29/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 9/15/2020 Approved DAVID FEILER
Final 9/15/2020 Corrections Issued DAVID FEILER
Gas Test 9/15/2020 Approved DAVID FEILER
Green Building Final 9/15/2020 Approved DAVID FEILER
HVAC-Final 9/15/2020 Approved DAVID FEILER
PLUMBING-Final 9/15/2020 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/15/2020 SGSOV Approved DAVID FEILER
Service/Power Release 9/15/2020 Not Ready for Inspection DAVID FEILER
Smoke Detectors 9/15/2020 Approved DAVID FEILER
Final 9/17/2020 OK to Issue CofO DAVID FEILER
Service/Power Release 9/17/2020 Approved DAVID FEILER