719-719 1/2 W 41ST PL 90037
Certificate Information: 719-719 1/2 W 41ST PL 90037
- Application / Permit
- 19010-10000-04704
- Plan Check / Job No.
- B19LA22450
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX W/ ATTACHED GARAGE (FRONT Building)
- Permit Issued
- Issued on 7/19/2020
- Issuing Office
- Current Status
- CofO Issued on 7/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | RACHEL BEYENE |
| Green Plans Picked Up | 11/27/2019 | APPLICANT |
| Corrections Issued | 12/2/2019 | RACHEL BEYENE |
| Quality Review Completed | 12/14/2019 | STANLEY RAAP |
| Applicant returned to address corrections | 1/9/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 5/13/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/7/2020 | RACHEL BEYENE |
| Plan Check Approved | 7/8/2020 | RAHEL BEYENE |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Issued | 7/19/2020 | APPLICANT |
| CofO in Progress | 6/24/2022 | SABAS ALONSO |
| Permit Finaled | 7/7/2022 | DEROLD HAUFF |
| CofO Issued | 7/7/2022 | DEROLD HAUFF |
| Permit Finaled | 7/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2019 | CELINA MORENO |
| Sewer availability | Cleared | 11/18/2019 | CELINA MORENO |
| ZI | Cleared | 11/20/2019 | ANNA VAN |
| Roof/Waste drainage to street | Cleared | 11/25/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 11/26/2019 | JEREMY CARTER |
| Address approval | Cleared | 11/27/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 12/10/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 12/16/2019 | ORVAL HERNANDEZ-MARCIAL |
Contact Information
| Engineer | Chao,, Chun-Ching; Lic. No.: C57893 | PO BOX 8422 ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 7/22/2020 | Approved | ROBERT MCDOWELL |
| Deputy Reinf. Concrete | 7/28/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2020 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 8/25/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 8/25/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 5/28/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/3/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 6/3/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 9/14/2021 | Approved | SABAS ALONSO |
| Insulation | 9/14/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/12/2021 | Approved | SABAS ALONSO |
| Sewer | 1/26/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/29/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/29/2022 | Approved | SABAS ALONSO |
| Final | 5/19/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 5/19/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 5/19/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 5/19/2022 | Not Required | SABAS ALONSO |
| Smoke Detectors | 5/19/2022 | Approved | SABAS ALONSO |
| Final | 6/13/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/24/2022 | OK to Issue CofO | SABAS ALONSO |