300 W 60TH ST 1-60 90003

Certificate Information: 300 W 60TH ST 1-60 90003

Application / Permit
19010-10000-04673
Plan Check / Job No.
B19LA22305
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY TYPE V-A RESIDINTIAL BUILDING. 60 UNITS, 100% ON-SITE RESTRICTED AFFORDABLE HOUSING. PRIVATELY FUNDED. NO PARKING PROVIDED.
Permit Issued
Issued on 10/2/2023
Issuing Office
Valley
Current Status
CofO Corrected on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 HERNAN ARREOLA
Corrections Issued 11/12/2019 HERNAN ARREOLA
Quality Review Completed 11/18/2019 BILL STUTSMAN
Building Plans Picked Up 1/7/2020 APPLICANT
Applicant returned to address corrections 4/1/2020 HERNAN ARREOLA
Applicant returned to address corrections 4/14/2020 HERNAN ARREOLA
Applicant returned to address corrections 2/25/2022 HERNAN ARREOLA
Plan Check Approved 5/11/2022 HERNAN ARREOLA
Issued 10/2/2023 APPLICANT
CofO in Progress 6/23/2025 RAFAEL ESPINOZA
CofO Issued-Status Void 6/23/2025 ERNESTO CORRAL
Permit Finaled-Status Void 6/23/2025 ERNESTO CORRAL
Re-Activate Permit 6/27/2025 RAFAEL ESPINOZA
CofO Corrected 7/7/2025 RAFAEL ESPINOZA
Permit Finaled 7/7/2025 RAFAEL ESPINOZA

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 5/22/2020 SAM NAVID
Frnt yard landscape/Water mgmt Cleared 9/29/2020 RICHARD REASER
Miscellaneous Cleared 9/29/2020 RICHARD REASER
Opn space landscape/Water mgmt Cleared 9/29/2020 RICHARD REASER
ZI Cleared 9/29/2020 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 10/6/2020 CELINA MORENO
Community Plan Implem. Overlay Cleared 10/13/2020 KEVIN ARUCAN
Highway dedication Cleared 11/5/2020 CELINA MORENO
Building over 3-story or 36-ft Cleared 11/10/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/10/2020 CALOSHA APPROVED
Address approval Cleared 12/2/2020 THOMAS LANG
Hydrant and Access approval Cleared 12/8/2020 MATTHEW CRAIG
Green Code Cleared 1/27/2021 KHEDER ALRAZAA
DAS Clearance Cleared 2/11/2021 CHOI YAN
Redevelopment Project Area Cleared 2/26/2021 GRACIELA ACOSTA
Sewer availability Cleared 5/4/2021 THOMAS LANG
Fire Marshall Fire Life Safety Cleared 6/3/2021 VIDAL GARCIA
Low Impact Development Cleared 6/9/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/15/2021 THOMAS LANG
Community Plan Implem. Overlay Cleared 9/7/2021 RIDWAN HARDY
Construction near power lines Cleared 9/7/2021 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 1/24/2022 HELEN JADALI
Density Bonus 12.22.A.31 Cleared 1/26/2022 RICHARD TRUONG

Contact Information

Contractor Owner-Builder       ,
Engineer Afshar,, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST 9038      NEWPORT BEACH, CA 92658
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/16/2024 Not Ready for Inspection JAMES POWERS
Pre-Inspection 2/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/14/2024 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/14/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/15/2024 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/15/2024 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 4/1/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 4/2/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 4/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 4/12/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/15/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/18/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/22/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/26/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 5/8/2024 Conditional Approval RAFAEL ESPINOZA
Pre-Inspection 5/9/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 5/14/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Corrections Issued JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/6/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/13/2024 Partial Inspection RAFAEL ESPINOZA
Insulation 6/21/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/28/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/28/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 7/1/2024 Corrections Issued RAFAEL ESPINOZA
Wood Frame 7/2/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/3/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/8/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/8/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/10/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/10/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/10/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/11/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/15/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/15/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/22/2024 Partial Approval RAFAEL ESPINOZA
Insulation 7/26/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 7/29/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/31/2024 Approved DARRYL ARNOLD
Deputy Wood Construction 8/6/2024 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 8/6/2024 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 8/6/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/6/2024 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Approval DANIEL VARNUM
Green Building Rough 8/8/2024 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 8/8/2024 Not Ready for Inspection DANIEL VARNUM
Wood Frame 8/8/2024 Not Ready for Inspection DANIEL VARNUM
Wood Frame 8/13/2024 Partial Approval RAFAEL ESPINOZA
T-Bar Ceiling 8/21/2024 Not Ready for Inspection RAFAEL ESPINOZA
T-Bar Ceiling 8/28/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 8/29/2024 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/29/2024 Partial Approval LARRY ARNICK
Drywall Nailing 9/11/2024 Partial Approval RONALD JIMENEZ
T-Bar Ceiling 9/11/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 9/18/2024 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 9/27/2024 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 10/1/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 10/11/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 10/15/2024 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 1/14/2025 Approved RAFAEL CORTES
Final 4/3/2025 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/3/2025 Approved RAFAEL ESPINOZA
Green Building Final 4/3/2025 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 4/3/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 4/3/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/3/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/3/2025 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/4/2025 Corrections Issued RAFAEL ESPINOZA
Pre-Inspection 4/4/2025 Partial Inspection RAFAEL ESPINOZA
Final 4/17/2025 Partial Inspection RAFAEL ESPINOZA
Green Building Final 4/17/2025 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 4/17/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/17/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/17/2025 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/28/2025 Corrections Issued RAFAEL ESPINOZA
Green Building Final 4/28/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 4/28/2025 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/28/2025 Approved RAFAEL ESPINOZA
Wood Frame 4/28/2025 Approved RAFAEL ESPINOZA
Final 6/10/2025 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved RAFAEL ESPINOZA
Final 6/23/2025 OK to Issue CofO RAFAEL ESPINOZA