14629 W ERWIN ST 1-21 91411

Certificate Information: 14629 W ERWIN ST 1-21 91411

Application / Permit
19010-10000-04672
Plan Check / Job No.
B19LA22304
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 5- STORY APARTMENT BUILDING 21 UNITS WITH GROUND LEVEL PARKING GARAGE. (TOC TIER3) 2 EXTREMELY LOW INCOME AND 1 VERY LOW INCOME UNIT PER DIR-2019-1323-TOC-PHP.
Permit Issued
Issued on 8/11/2021
Issuing Office
Current Status
Issued on 8/11/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ARMEN JIVALAGIAN
Corrections Issued 11/25/2019 ARMEN JIVALAGIAN
Quality Review Completed 12/3/2019 TIEN JEN WANG
Disabled Access Plans Picked Up 2/24/2020 APPLICANT
Applicant returned to address corrections 6/30/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/2/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/6/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/8/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/18/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/21/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/5/2021 ARMEN JIVALAGIAN
Green Plans Picked Up 3/5/2021 APPLICANT
Applicant returned to address corrections 5/21/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/13/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/23/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/26/2021 ARMEN JIVALAGIAN
Plan Check Approved 7/27/2021 ARMEN JIVALAGIAN
Issued 8/11/2021 APPLICANT
Building Plans Picked Up 8/20/2021 APPLICANT
TCO Issued (Expire Date: 04-26-2026) 10/28/2025 RICKEY JACKSON
TCO Issued (Expire Date: 10-25-2026) 4/28/2026 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 6/18/2020 LEE GUILBEAUX
Bicycle Parking Cleared 6/18/2020 LEE GUILBEAUX
Encroachment in public way Cleared 6/18/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/18/2020 LEE GUILBEAUX
Highway dedication Cleared 6/18/2020 LEE GUILBEAUX
Permit Cleared 6/18/2020 LEE GUILBEAUX
Sewer availability Cleared 6/18/2020 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 6/18/2020 LEE GUILBEAUX
Green Code Cleared 6/25/2020 ARMEN JIVALAGIAN
Hydrant and Access approval Cleared 6/30/2020 KURT CORRAL
Trees in Parkway Cleared 7/16/2020 JOHN KIM
Fire Marshall Fire Life Safety Cleared 7/27/2020 ARMEN JIVALAGIAN
"Q" conditions Cleared 7/28/2020 ANACANY HURTADO
Frnt yard landscape/Water mgmt Cleared 9/4/2020 ANACANY HURTADO
Opn space landscape/Water mgmt Cleared 9/4/2020 ANACANY HURTADO
Construction near power lines Cleared 9/21/2020 RIDWAN HARDY
Construction within easement Cleared 9/21/2020 RIDWAN HARDY
DAS Clearance Cleared 9/24/2020 ELIZABETH TOMS
DCP conditions approval Cleared 10/26/2020 LOUIE MILLER
Density Bonus 12.22.A.31 Cleared 10/26/2020 LOUIE MILLER
Low Impact Development Cleared 11/8/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 11/10/2020 LEE GUILBEAUX
Miscellaneous Cleared 1/27/2021 ANACANY HURTADO
Building over 3-story or 36-ft Cleared 5/21/2021 CALOSHA APPROVED
Hold Cleared 8/24/2021 JASON SHEETS

Contact Information

Architect Crockett,, Cameron; Lic. No.: C31503 1327 LOMA AVENUE      LONG BEACH, CA 90804
Contractor Design Construction; Lic. No.: 840542-B 14506 FRIAR ST      VAN NUYS, CA 914112308
Engineer Burton,, John Clifford; Lic. No.: C31503 162 PROSPECT AVE      SAUSALITO, CA 94965
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Wu,, Michael; Lic. No.: C75964 2502 GRAND SUMMIT ROAD      TORRANCE, CA 90505

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 12/22/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 12/22/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 12/22/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 3/4/2022 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/7/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 3/21/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 3/22/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/1/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/1/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/4/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/4/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/5/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/5/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/6/2022 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 4/6/2022 Partial Approval CAMERON CHABAN
Piling/Pier/Caisson 4/7/2022 Partial Approval CAMERON CHABAN
Deputy Other (see comments) 4/8/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/8/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/11/2022 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 4/11/2022 Conditional Approval DANIEL VARNUM
Deputy Other (see comments) 4/12/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/12/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/13/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/13/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/15/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/15/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/18/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/18/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/20/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/20/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/21/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/21/2022 Conditional Approval CAMERON CHABAN
Deputy Other (see comments) 4/22/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/22/2022 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/22/2022 Partial Inspection JEFFREY FULTON
Deputy Other (see comments) 4/25/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/25/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/19/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/6/2022 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 6/8/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 6/8/2022 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 6/8/2022 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 6/8/2022 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Concrete 6/10/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 6/22/2022 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved DANIEL VARNUM
Insulation 11/21/2022 Partial Approval CAMERON CHABAN
Insulation 1/25/2023 Partial Approval CAMERON CHABAN
Pre-Inspection 2/9/2023 Partial Approval CAMERON CHABAN
Wood Frame 4/10/2023 Corrections Issued JEFFREY FULTON
Deputy Steel/Welding 4/26/2023 Conditional Approval CAMERON CHABAN
Insulation 5/16/2023 Partial Inspection CAMERON CHABAN
Special/Order Compliance 5/16/2023 Partial Inspection STEVEN LEVITT
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval CAMERON CHABAN
Green Building Rough 6/21/2023 Not Ready for Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 6/21/2023 Not Ready for Inspection CAMERON CHABAN
Insulation 6/22/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 7/26/2023 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval CAMERON CHABAN
Green Building Rough 10/18/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 10/18/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/18/2023 Corrections Issued JOHN KITCKO
Deputy Drilled-In Anchors 10/23/2023 Conditional Approval JEFFREY DURAN
Green Building Rough 10/23/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 10/23/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/23/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/24/2023 Partial Approval CAMERON CHABAN
Green Building Rough 10/26/2023 Approved CAMERON CHABAN
Insulation 10/26/2023 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 10/26/2023 Conditional Approval CAMERON CHABAN
Wood Frame 10/26/2023 Partial Approval CAMERON CHABAN
Insulation 10/27/2023 Partial Approval CAMERON CHABAN
Insulation 11/14/2023 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 11/14/2023 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 11/30/2023 Approved CAMERON CHABAN
Drywall Nailing 12/8/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 12/12/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 12/20/2023 Partial Approval CAMERON CHABAN
Wall Anchors 3/5/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 3/6/2024 Partial Inspection ROBERT DAVIS
Footing/Foundation/Slab 4/29/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 4/29/2024 No Access for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 4/29/2024 Not Ready for Inspection ROBERT DAVIS
Masonry Wall/Backfill 4/30/2024 Not Ready for Inspection KENNETH ROBERTS
Special/Order Compliance 4/30/2024 Partial Inspection DEANDRE HOFFMAN
Masonry Wall/Backfill 5/7/2024 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 5/8/2024 Approved ROBERT DAVIS
Masonry Wall/Backfill 5/16/2024 Approved ROBERT DAVIS
Final 6/12/2024 Corrections Issued ROBERT DAVIS
Green Building Final 6/12/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 6/12/2024 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 6/12/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 6/12/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 6/12/2024 Partial Inspection ROBERT DAVIS
Drywall Nailing 7/3/2024 Partial Inspection ROBERT DAVIS
Wall Anchors 7/3/2024 Partial Inspection ROBERT DAVIS
Special/Order Compliance 7/8/2024 Partial Inspection ROBERT DAVIS
Drywall Nailing 8/7/2024 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 8/7/2024 Partial Approval ROBERT DAVIS
Reinforced Concrete Frame 8/7/2024 Partial Approval ROBERT DAVIS
Reinforced Concrete Frame 8/19/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 8/20/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 8/27/2024 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 8/27/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 9/4/2024 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 9/4/2024 Approved ROBERT DAVIS
Final 3/12/2025 Corrections Issued ROBERT DAVIS
Reinforced Concrete Frame 3/12/2025 Partial Approval ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 3/12/2025 Not Ready for Inspection ROBERT DAVIS
Wood Frame 3/12/2025 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 4/10/2025 Partial Approval ROBERT DAVIS
Final 8/13/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 8/13/2025 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 8/13/2025 Not Ready for Inspection ROBERT DAVIS
Final 9/15/2025 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 9/15/2025 Not Ready for Inspection ROBERT DAVIS
Final 10/10/2025 OK for TCO ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Approved ROBERT DAVIS
Smoke Detectors 10/10/2025 Approved ROBERT DAVIS
Final 10/24/2025 Partial Inspection BRIAN KELLY
Posting Pre-Inspection 10/28/2025 Partial Inspection GREGORY POMISH
Special/Order Compliance 4/1/2026 Partial Inspection ROBERT DAVIS