1421 W ADAMS BLVD 1-45 90007

Certificate Information: 1421 W ADAMS BLVD 1-45 90007

Application / Permit
19010-10000-04671
Plan Check / Job No.
B19LA22301
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5-STORY MIXED-USE 45 UNIT APARTMENT AND RETAIL.
Permit Issued
Issued on 11/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 HERNAN ARREOLA
Disabled Access Plans Picked Up 11/6/2019 APPLICANT
Corrections Issued 11/12/2019 HERNAN ARREOLA
Quality Review Completed 11/18/2019 BILL STUTSMAN
Building Plans Picked Up 11/19/2019 APPLICANT
Applicant returned to address corrections 3/26/2020 HERNAN ARREOLA
Green Plans Picked Up 8/10/2020 APPLICANT
Plan Check Approved 11/13/2020 HERNAN ARREOLA
Issued 11/16/2020 APPLICANT
TCO Issued (Expire Date: 01-24-2023) 7/28/2022 TED RIES
TCO Issued (Expire Date: 09-24-2023) 3/28/2023 ERNESTO CORRAL
CofO in Progress 3/31/2023 JAMES POWERS
CofO Issued 3/31/2023 ERNESTO CORRAL
Permit Finaled 3/31/2023 ERNESTO CORRAL

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 2/8/2020 RIDWAN HARDY
Construction near power lines Cleared 2/8/2020 RIDWAN HARDY
Green Code Cleared 2/25/2020 VIVIAN LAO
Community Plan Implem. Overlay Cleared 6/16/2020 SAM NAVID
Hydrant and Access approval Cleared 6/25/2020 KURT CORRAL
Address approval Cleared 7/2/2020 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 7/2/2020 JAMES KHO
Community Plan Implem. Overlay Cleared 7/7/2020 MOHAMMAD HASAN
Sewer availability Cleared 7/10/2020 JAMES KHO
Density Bonus 12.22.A.31 Cleared 7/29/2020 NICHOLAS KAWAZOE
Low Impact Development Cleared 8/4/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/7/2020 JAMES KHO
DAS Clearance Cleared 8/20/2020 SHINE LIN
Fire Marshall Fire Life Safety Cleared 9/8/2020 OSCAR SALGADO JR
Highway dedication Cleared 9/10/2020 THAN WIN
City Hist. Cultural Monument Cleared 9/28/2020 MICAELA TORRES-GIL
HPOZ Cleared 9/28/2020 MICAELA TORRES-GIL
Hist. Property Cntrct Mgr Appr Cleared 9/28/2020 MICAELA TORRES-GIL
Miscellaneous Cleared 9/28/2020 MICAELA TORRES-GIL
ZI Cleared 9/28/2020 MICAELA TORRES-GIL
Community Plan Implem. Overlay Cleared 9/29/2020 HELEN JADALI
ZI Cleared 9/29/2020 HELEN JADALI
Frnt yard landscape/Water mgmt Cleared 10/16/2020 ANACANY HURTADO
Miscellaneous Cleared 10/16/2020 ANACANY HURTADO
Opn space landscape/Water mgmt Cleared 10/16/2020 ANACANY HURTADO
Building over 3-story or 36-ft Cleared 11/13/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/13/2020 CALOSHA APPROVED

Contact Information

Architect Chang,, Winston L; Lic. No.: C25009 1476 VIA CORONEL      PALOS VERDES ESTATES, CA 90274
Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/25/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/25/2020 Partial Approval JAMES POWERS
METHANE-Barrier 11/25/2020 Partial Approval JAMES POWERS
METHANE-Subgrade 11/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/7/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/7/2020 Partial Approval JAMES POWERS
METHANE-Barrier 12/7/2020 Partial Approval JAMES POWERS
METHANE-Subgrade 12/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2020 Partial Approval JAMES POWERS
METHANE-Barrier 12/11/2020 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 12/11/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/11/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/15/2020 Partial Approval JAMES POWERS
Green Building Rough 12/15/2020 Not Ready for Inspection JAMES POWERS
METHANE-Rough 12/15/2020 Approved JAMES POWERS
Reinforced Concrete Frame 12/15/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/15/2020 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 12/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/17/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/17/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/17/2020 Partial Approval JAMES POWERS
METHANE-Barrier 12/17/2020 Partial Approval JAMES POWERS
METHANE-Subgrade 12/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/18/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/22/2020 Partial Approval JAMES POWERS
METHANE-Barrier 12/22/2020 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 12/22/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/28/2020 Partial Approval JAMES POWERS
Green Building Rough 12/28/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/28/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/28/2020 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 12/29/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/8/2021 Partial Approval JAMES POWERS
METHANE-Barrier 1/8/2021 Approved JAMES POWERS
METHANE-Subgrade 1/8/2021 Approved JAMES POWERS
Deputy Reinf. Concrete 1/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/14/2021 Partial Approval JAMES POWERS
Green Building Rough 1/14/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 1/14/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/15/2021 Partial Approval JAMES POWERS
Green Building Rough 1/20/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 1/20/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/20/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 1/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/25/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/25/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 1/25/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/25/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/25/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 1/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/27/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/2/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/4/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/4/2021 Partial Approval JAMES POWERS
Green Building Rough 2/4/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/4/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/4/2021 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 2/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/16/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/17/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/23/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/23/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/3/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/3/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 3/4/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/4/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/4/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/11/2021 Order to Comply Issued JAMES POWERS
Deputy Reinf. Masonry 3/11/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/16/2021 Partial Approval JAMES POWERS
Green Building Rough 3/16/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 3/16/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/16/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/17/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/17/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 3/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/18/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/18/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 3/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/23/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/23/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/23/2021 Not Ready for Inspection JAMES POWERS
Green Building Rough 3/23/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 3/23/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/23/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 3/24/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/24/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/26/2021 Partial Approval JAMES POWERS
Green Building Rough 3/26/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 3/26/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/26/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 3/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/20/2021 Partial Approval JAMES POWERS
Green Building Rough 4/20/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/20/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 4/20/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/20/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/1/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 6/21/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/19/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/4/2021 Partial Approval JAMES POWERS
Wood Frame 8/20/2021 Not Ready for Inspection JAMES POWERS
Insulation 8/24/2021 Partial Approval JAMES POWERS
Wood Frame 8/24/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Partial Approval JAMES POWERS
Insulation 9/20/2021 Partial Approval JAMES POWERS
Drywall Nailing 9/27/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval JAMES POWERS
Insulation 10/8/2021 Partial Approval JAMES POWERS
Insulation 10/25/2021 Partial Approval JAMES POWERS
Insulation 11/4/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/5/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/6/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/13/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/12/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 1/12/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/14/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/19/2022 Approved JAMES POWERS
Drywall Nailing 1/31/2022 Partial Approval JAMES POWERS
Insulation 1/31/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/15/2022 Partial Approval JAMES POWERS
Pre-Inspection 4/29/2022 Not Ready for Inspection JAMES POWERS
Verify Rec and Parks Fee Memo 4/29/2022 Partial Approval JAMES POWERS
Final 6/17/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 6/24/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/29/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/22/2022 Approved JAMES POWERS
Green Building Final 7/22/2022 Approved JAMES POWERS
Green Building Rough 7/22/2022 Approved JAMES POWERS
Reinforced Concrete Frame 7/22/2022 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/22/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved JAMES POWERS
Smoke Detectors 7/22/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/22/2022 Not Ready for Inspection JAMES POWERS
Final 7/25/2022 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 12/28/2022 Approved JAMES POWERS
Final 3/31/2023 OK to Issue CofO JAMES POWERS
Reinforced Concrete Frame 3/31/2023 Approved JAMES POWERS
Reinforced Masonry Frame 3/31/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/31/2023 Approved JAMES POWERS