1124 S NORMANDIE AVE 90006

Certificate Information: 1124 S NORMANDIE AVE 90006

Application / Permit
19010-10000-04611
Plan Check / Job No.
B19LA22009
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY 84 UNIT APT. BUILDING WITH PARTIAL SUB PARKING GARAGE.
Permit Issued
Issued on 9/1/2021
Issuing Office
Metro
Current Status
Issued on 9/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 JOE VO
Corrections Issued 11/4/2019 JOE VO
Quality Review Completed 11/13/2019 KEN GILL
Building Plans Picked Up 11/18/2019 APPLICANT
Disabled Access Plans Picked Up 11/18/2019 APPLICANT
Applicant returned to address corrections 5/18/2020 JOE VO
Applicant returned to address corrections 6/8/2020 JOE VO
Applicant returned to address corrections 6/23/2020 JOE VO
Applicant returned to address corrections 12/8/2020 JOE VO
Green Plans Picked Up 4/20/2021 APPLICANT
Applicant returned to address corrections 8/11/2021 JOE VO
Plan Check Approved 8/16/2021 JOE VO
Issued 9/1/2021 APPLICANT
TCO Issued (Expire Date: 01-05-2026) 7/9/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 06-28-2026) 12/30/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/19/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/19/2020 THOMAS LANG
DAS Clearance Cleared 5/22/2020 SHINE LIN
Low Impact Development Cleared 8/23/2020 MARTIN FRAGOSO
Driveway location Cleared 9/1/2020 PETE EYRE
Green Code Cleared 9/1/2020 JOE VO
Sewer availability Cleared 9/24/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 9/29/2020 CELINA MORENO
Density Bonus 12.22.A.31 Cleared 10/9/2020 NICHOLAS KAWAZOE
Building over 3-story or 36-ft Cleared 10/12/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/12/2020 CALOSHA APPROVED
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL
Highway dedication Cleared 11/16/2020 CELINA MORENO
Fire Marshall Fire Life Safety Cleared 1/20/2021 ANDREW KO
Frnt yard landscape/Water mgmt Cleared 3/5/2021 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 3/5/2021 JOE LUCKEY
Site Plan review Cleared 3/5/2021 JOE LUCKEY
ZA Case Cleared 3/5/2021 JOE LUCKEY
Permit Cleared 7/9/2021 CECILIO NAVARRO

Contact Information

Architect Bittoni,, Mark Christopher; Lic. No.: C34136 434 N GREENCRAIG ROAD      LOS ANGELES, CA 90049
Contractor Goodson Real Estate Co; Lic. No.: 977440-B 6230 WILSHIRE BLVD #1154      LOS ANGELES, CA 90048
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 6007 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2021 Partial Inspection LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 9/24/2021 Partial Inspection DANIEL MC AULIFFE
Piling/Pier/Caisson 9/30/2021 Partial Inspection EDWIN GREGORYONA
Piling/Pier/Caisson 10/7/2021 Partial Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 10/14/2021 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 12/13/2021 Approved RAFAEL ESPINOZA
Special/Order Compliance 12/29/2021 No Access for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/20/2022 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 1/21/2022 Conditional Approval TED RIES
Deputy Shotcrete 1/25/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 1/28/2022 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/10/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/17/2022 Partial Approval NICK DANERI
Piling/Pier/Caisson 2/17/2022 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 3/10/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/14/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/24/2022 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/29/2022 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 3/31/2022 Partial Approval NICK DANERI
Deputy Shotcrete 4/5/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/9/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/11/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/24/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 10/28/2022 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/31/2022 Partial Approval NICK DANERI
Green Building Rough 10/31/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 10/31/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 10/31/2022 Not Ready for Inspection NICK DANERI
Deputy Drilled-In Anchors 11/18/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/6/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/9/2022 Conditional Approval GREGORY POMISH
Special/Order Compliance 12/9/2022 Partial Inspection NICK DANERI
Deputy Wood Construction 1/4/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Special/Order Compliance 2/28/2023 Partial Inspection NICK DANERI
Special/Order Compliance 3/8/2023 Corrections Issued NICK DANERI
Special/Order Compliance 3/13/2023 Corrections Issued NICK DANERI
Special/Order Compliance 3/15/2023 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Inspection GREGORY POMISH
Special/Order Compliance 4/5/2023 Corrections Issued NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval GREGORY POMISH
Special/Order Compliance 5/4/2023 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 6/5/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 6/6/2023 Partial Inspection EDWIN GREGORYONA
Wood Frame 6/6/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 6/21/2023 Partial Approval GREGORY POMISH
Green Building Rough 6/21/2023 Not Ready for Inspection GREGORY POMISH
Insulation 7/3/2023 Partial Inspection EDWIN GREGORYONA
Special/Order Compliance 7/3/2023 Partial Inspection EDWIN GREGORYONA
Insulation 7/11/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval NICK DANERI
Insulation 7/14/2023 Partial Approval NICK DANERI
Drywall Nailing 7/17/2023 Partial Approval GREGORY POMISH
Green Building Rough 7/17/2023 Partial Inspection GREGORY POMISH
Wood Frame 7/17/2023 Partial Approval GREGORY POMISH
Drywall Nailing 7/20/2023 Partial Approval GREGORY POMISH
Green Building Rough 7/20/2023 Partial Inspection GREGORY POMISH
Special/Order Compliance 7/20/2023 Partial Inspection GREGORY POMISH
Special/Order Compliance 7/25/2023 Partial Approval GREGORY POMISH
Insulation 7/27/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 7/27/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval NICK DANERI
Insulation 7/31/2023 Partial Approval NICK DANERI
Insulation 8/2/2023 Partial Approval NICK DANERI
Deputy Wood Construction 8/7/2023 Conditional Approval GREGORY POMISH
Deputy Wood Construction 8/9/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval NICK DANERI
Drywall Nailing 8/14/2023 Partial Approval GREGORY POMISH
Green Building Rough 8/14/2023 Partial Approval GREGORY POMISH
Drywall Nailing 8/21/2023 Partial Approval LARRY ARNICK
Green Building Rough 8/21/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 8/24/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 8/24/2023 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 8/30/2023 Partial Inspection NICK DANERI
Drywall Nailing 9/7/2023 Partial Approval NICK DANERI
Green Building Rough 9/7/2023 Not Ready for Inspection NICK DANERI
Insulation 9/7/2023 Partial Approval NICK DANERI
Insulation 9/11/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 9/21/2023 Partial Approval LARRY ARNICK
Drywall Nailing 9/29/2023 Partial Approval GREGORY POMISH
Green Building Rough 9/29/2023 Partial Approval GREGORY POMISH
Insulation 9/29/2023 Partial Approval GREGORY POMISH
Insulation 10/4/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/11/2023 Partial Approval NICK DANERI
Green Building Rough 10/11/2023 Not Ready for Inspection NICK DANERI
Drywall Nailing 10/17/2023 Partial Approval GREGORY POMISH
Green Building Rough 10/17/2023 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval GREGORY POMISH
Insulation 10/26/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/5/2023 Partial Inspection GREGORY POMISH
Insulation 12/5/2023 Partial Approval GREGORY POMISH
Drywall Nailing 12/15/2023 Partial Approval NICK DANERI
Green Building Rough 12/15/2023 Partial Inspection NICK DANERI
Insulation 12/15/2023 Partial Inspection NICK DANERI
Drywall Nailing 12/20/2023 Partial Approval NICK DANERI
Green Building Rough 12/20/2023 Not Ready for Inspection NICK DANERI
T-Bar Ceiling 12/20/2023 Partial Approval NICK DANERI
Drywall Nailing 12/26/2023 Partial Approval NICK DANERI
Green Building Rough 12/26/2023 Approved NICK DANERI
Insulation 1/4/2024 Not Ready for Inspection NICK DANERI
Insulation 1/5/2024 Partial Approval GREGORY POMISH
Drywall Nailing 1/12/2024 Partial Approval GREGORY POMISH
Insulation 1/24/2024 Partial Approval GREGORY POMISH
Insulation 2/16/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/28/2024 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 2/29/2024 Conditional Approval NICK DANERI
Drywall Nailing 2/29/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 2/29/2024 Partial Inspection JEFFREY FULTON
Insulation 3/4/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 3/7/2024 Partial Inspection JEFFREY FULTON
Insulation 3/8/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/13/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/14/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/27/2024 Not Ready for Inspection NICK DANERI
Insulation 3/27/2024 Partial Approval NICK DANERI
Drywall Nailing 4/3/2024 Partial Approval NICK DANERI
Insulation 4/3/2024 Partial Approval NICK DANERI
Drywall Nailing 4/8/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/10/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 5/2/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 5/7/2024 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 5/10/2024 Partial Approval JEROME BLACKWOOD
Special/Order Compliance 5/13/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 5/15/2024 Partial Approval JEROME BLACKWOOD
T-Bar Ceiling 5/15/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 5/22/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 5/28/2024 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 5/30/2024 Not Ready for Inspection NICK DANERI
Drywall Nailing 6/21/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 7/5/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 7/8/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 7/8/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 7/10/2024 Partial Approval LARRY ARNICK
Light Gage Steel Frame 7/16/2024 Partial Approval EDWIN GREGORYONA
Insulation 8/7/2024 Partial Approval NICK DANERI
Drywall Nailing 8/14/2024 Partial Approval NICK DANERI
Drywall Nailing 8/23/2024 Partial Approval NICK DANERI
Drywall Nailing 8/29/2024 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 9/16/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/16/2024 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 9/17/2024 Approved JEROME BLACKWOOD
Drywall Nailing 9/17/2024 Not Ready for Inspection JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 9/17/2024 Corrections Issued JEROME BLACKWOOD
Drywall Nailing 9/20/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 9/24/2024 Partial Approval NICK DANERI
Special/Order Compliance 9/24/2024 Partial Inspection NICK DANERI
Drywall Nailing 9/26/2024 Partial Approval NICK DANERI
Special/Order Compliance 9/26/2024 Partial Inspection NICK DANERI
Drywall Nailing 9/30/2024 Partial Approval NICK DANERI
Drywall Nailing 10/30/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 10/31/2024 Partial Approval LARRY ARNICK
Special/Order Compliance 11/1/2024 Partial Approval LARRY ARNICK
Pre-Inspection 12/12/2024 Partial Inspection NICK DANERI
Special/Order Compliance 12/12/2024 Partial Approval NICK DANERI
Drywall Nailing 12/23/2024 Partial Approval NICK DANERI
Green Building Final 1/17/2025 Not Ready for Inspection RONALD JIMENEZ
Smoke Detectors 1/17/2025 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 1/23/2025 Partial Inspection NICK DANERI
Smoke Detectors 1/23/2025 Not Ready for Inspection NICK DANERI
Verify Rec and Parks Fee Memo 1/23/2025 Partial Inspection NICK DANERI
Special/Order Compliance 2/6/2025 Partial Inspection NICK DANERI
Special/Order Compliance 3/12/2025 Partial Inspection NICK DANERI
Drywall Nailing 5/1/2025 Not Ready for Inspection NICK DANERI
Final 5/1/2025 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 5/1/2025 Not Ready for Inspection NICK DANERI
Green Building Final 5/1/2025 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/1/2025 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 5/1/2025 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Not Ready NICK DANERI
Smoke Detectors 5/1/2025 Not Ready for Inspection NICK DANERI
Structural Steel Frame 5/1/2025 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/1/2025 Not Ready for Inspection NICK DANERI
Wood Frame 5/1/2025 Not Ready for Inspection NICK DANERI
Special/Order Compliance 5/14/2025 Partial Inspection NICK DANERI
Green Building Final 5/15/2025 Not Ready for Inspection NICK DANERI
Pre-Inspection 5/15/2025 Partial Inspection NICK DANERI
Smoke Detectors 5/15/2025 Approved NICK DANERI
Verify Rec and Parks Fee Memo 5/15/2025 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/15/2025 Approved NICK DANERI
Special/Order Compliance 5/22/2025 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 7/8/2025 Approved EDWIN GREGORYONA
Final 7/8/2025 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 7/8/2025 Approved EDWIN GREGORYONA
Green Building Final 7/8/2025 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 7/8/2025 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 7/8/2025 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 7/8/2025 SGSOV Approved EDWIN GREGORYONA
Structural Steel Frame 7/8/2025 Approved EDWIN GREGORYONA
Wood Frame 7/8/2025 Approved EDWIN GREGORYONA
Special/Order Compliance 12/9/2025 Approved JOEY BUCHANAN
Special/Order Compliance 6/2/2026 Approved JOEY BUCHANAN