1237 S NEW HAMPSHIRE AVE 90006

Certificate Information: 1237 S NEW HAMPSHIRE AVE 90006

Application / Permit
19010-10000-04609
Plan Check / Job No.
B19LA21998
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AT REAR OF LOT. INCLUDES OPEN PARKING.
Permit Issued
Issued on 2/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Green Plans Picked Up 10/22/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 LAWRENCE QUIRANTE
Corrections Issued 10/28/2019 LAWRENCE QUIRANTE
Quality Review Completed 10/30/2019 KEN GILL
Building Plans Picked Up 11/6/2019 APPLICANT
Applicant returned to address corrections 12/10/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/7/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/13/2020 LAWRENCE QUIRANTE
Plan Check Approved 1/30/2020 LAWRENCE QUIRANTE
Issued 2/3/2020 LADBS
CofO in Progress 11/10/2020 KATHRYN BUTTERWORTH
Permit Finaled 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/15/2019 CELINA MORENO
Highway dedication Cleared 11/15/2019 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 12/3/2019 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 12/10/2019 THOMAS LANG
Hydrant and Access approval Cleared 12/10/2019 JEREMY CARTER
Sewer availability Cleared 12/10/2019 THOMAS LANG
Low Impact Development Cleared 12/26/2019 MITESH PATEL
Green Code Cleared 1/2/2020 VIVIAN LAO
Roof/Waste drainage to street Cleared 1/7/2020 ERIK BEASLEY

Contact Information

Contractor California Green Home Solutions; Lic. No.: 1043877-B 7020 HAYVENHURST AVE STE B      VAN NUYS, CA 91406
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2020 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 3/4/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 3/5/2020 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 3/11/2020 Conditional Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 3/20/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 4/2/2020 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/2/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/28/2020 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 4/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 4/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/17/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/17/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 6/17/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 6/17/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 6/17/2020 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 6/17/2020 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 6/19/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/22/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/22/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 6/22/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 6/22/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/22/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 6/22/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/25/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 6/25/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/25/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 7/6/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 7/6/2020 Partial Approval THOMAS LOGRASSO
Drywall Nailing 7/14/2020 Approved CHRISTOPHER DELLEFIELD
Sewer 9/1/2020 Approved KATHRYN BUTTERWORTH
Underground Mechanical 9/1/2020 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 10/9/2020 SGSOV Not Ready KATHRYN BUTTERWORTH
Final 10/14/2020 Corrections Issued KATHRYN BUTTERWORTH
Final 10/20/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Final 10/20/2020 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 10/20/2020 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 10/20/2020 Approved KATHRYN BUTTERWORTH
Smoke Detectors 10/20/2020 Approved KATHRYN BUTTERWORTH
Final 11/6/2020 Partial Approval KATHRYN BUTTERWORTH