558 N BRISTOL AVE 90049

Certificate Information: 558 N BRISTOL AVE 90049

Application / Permit
19010-10000-04601
Plan Check / Job No.
B19LA21958
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELING WITH BASEMENT AND ATTACHED GARAGE.
Permit Issued
Issued on 4/20/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 SINA KHOSRAVI
Green Plans Picked Up 10/25/2019 APPLICANT
Corrections Issued 11/4/2019 ZAW HAN
Quality Review Completed 11/22/2019 HERNAN ARREOLA
Building Plans Picked Up 11/25/2019 APPLICANT
Applicant returned to address corrections 2/25/2020 ZAW HAN
Plan Check Approved 4/2/2020 ZAW HAN
Issued 4/20/2020 LADBS
CofO in Progress 9/5/2025 KEVIN SARGSYAN
Permit Finaled 9/6/2025 RICHARD STEINBACH
CofO Issued 9/6/2025 RICHARD STEINBACH
Permit Finaled 9/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/12/2019 JEREMY CARTER
Green Code Cleared 1/22/2020 VIVIAN LAO
Address approval Cleared 1/23/2020 CELINA MORENO
CPC Cleared 1/23/2020 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 1/23/2020 CELINA MORENO
Permit Cleared 1/23/2020 CELINA MORENO
Sewer availability Cleared 1/23/2020 CELINA MORENO
ZA Case Cleared 1/23/2020 RICHARD REASER
Work Adjacent to Public Way Cleared 1/24/2020 DANNY MORALES
Low Impact Development Cleared 1/27/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/27/2020 JUAN ASHTON
Trees in Parkway Cleared 1/28/2020 ADRIAN SANCHEZ
Disturb/Remove Protected Trees Cleared 1/29/2020 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 2/25/2020 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/25/2020 BRIAN OLSON
Construction near power lines Cleared 3/21/2020 RIDWAN HARDY
Construction within easement Cleared 3/21/2020 RIDWAN HARDY
GPI Written Notices Cleared 4/2/2020 BRIAN OLSON

Contact Information

Architect Rubio,, Edgardo A; Lic. No.: C26444 970 JUNIPERO DRIVE      COSTA MESA, CA 92626
Contractor Hanover Builders Inc; Lic. No.: 709353-B 141 DUESENBERG DRIVE STE 6      WESTLAKE VILLAGE, CA 91362
Engineer Danz,, Joshua Franklin; Lic. No.: C84764 932 WITHERSPOON DRIVE      THOUSAND OAKS, CA 91360
Engineer Padilla,, Juan C; Lic. No.: C79760 647 ERBES ROAD      THOUSAND OAKS, CA 91362
Engineer Richmond,, Bryce Dean; Lic. No.: C49628 4425 CANOGA AVENUE      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/25/2020 Approved ROBERT SHELLY
Footing/Foundation/Slab 6/26/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 7/27/2020 Corrections Issued MATT KELLERMAN
Masonry Wall/Backfill 7/27/2020 Not Ready for Inspection MATT KELLERMAN
Reinforced Masonry Frame 7/28/2020 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Masonry 7/30/2020 Conditional Approval TIM CHRISTENSEN
Underground Mechanical 8/17/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 9/3/2020 Conditional Approval TIM CHRISTENSEN
Underground Mechanical 9/29/2020 Corrections Issued TIM CHRISTENSEN
Underground Mechanical 9/30/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 10/1/2020 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 10/5/2020 Conditional Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval JUAN VALENZUELA
Sewer 4/12/2021 Not Ready for Inspection JUAN VALENZUELA
Sewer 4/14/2021 Approved PIERRE VEGA
Underground Mechanical 4/14/2021 Partial Approval PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 3/7/2022 Corrections Issued BRENDAN LOONEY
HVAC-Rough 3/9/2022 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 3/11/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 3/11/2022 Approved JOHN KIDWELL
HVAC-Rough 3/14/2022 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 3/14/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 3/17/2022 Partial Approval JUAN VALENZUELA
HVAC-Rough 3/23/2022 Approved JUAN VALENZUELA
ELECTRICAL-Rough 3/24/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 4/6/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Not Ready for Inspection JUAN VALENZUELA
Shower Pan 4/7/2022 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 4/18/2022 Approved JUAN VALENZUELA
Green Building Rough 4/18/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 4/18/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Corrections Issued MICHAEL PELHAM
Insulation 6/24/2022 Approved JUAN VALENZUELA
Drywall Nailing 7/1/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/19/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Not Ready KEVIN SARGSYAN
Underground Mechanical 5/15/2024 Approved KEVIN SARGSYAN
Service/Power Release 10/16/2024 Approved KENNETH NAGLE
HVAC-Final 2/26/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/4/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/4/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 3/4/2025 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 5/30/2025 Corrections Issued KEVIN SARGSYAN
Gas Test 6/20/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 8/12/2025 Approved KEVIN SARGSYAN
Final 8/19/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 8/19/2025 Approved STEPHANIE SWANSON
Green Building Final 8/19/2025 Approved STEPHANIE SWANSON
Reinforced Concrete Frame 8/19/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 8/19/2025 Corrections Issued STEPHANIE SWANSON
Final 8/21/2025 OK to Issue CofO KEVIN SARGSYAN
Smoke Detectors 8/21/2025 Approved KEVIN SARGSYAN