6453-6455 N CALHOUN AVE 91401
Certificate Information: 6453-6455 N CALHOUN AVE 91401
- Application / Permit
- 19010-10000-04579
- Plan Check / Job No.
- B19LA21845
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX AT FRONT
- Permit Issued
- Issued on 9/1/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | SINA KHOSRAVI |
| Corrections Issued | 10/29/2019 | ZAW HAN |
| Quality Review Completed | 11/12/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 11/12/2019 | APPLICANT |
| Green Plans Picked Up | 5/1/2020 | APPLICANT |
| Applicant returned to address corrections | 8/21/2020 | ZAW HAN |
| Plan Check Approved | 8/26/2020 | ZAW HAN |
| Issued | 9/1/2020 | APPLICANT |
| CofO in Progress | 6/18/2021 | MICHAEL TEMPLE |
| Permit Finaled | 7/3/2021 | MICHAEL SMITH |
| CofO Issued | 7/3/2021 | MICHAEL SMITH |
| Permit Finaled | 7/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/12/2019 | ANNA VAN |
| CPC | Cleared | 11/12/2019 | ANNA VAN |
| Address approval | Cleared | 12/9/2019 | ELAINE LEI |
| Address approval | Cleared | 12/9/2019 | ELAINE LEI |
| Green Code | Cleared | 12/23/2019 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 3/10/2020 | ROBERT DUFF |
| Frnt yard landscape/Water mgmt | Cleared | 3/12/2020 | TERRI OSBORNE |
| Public Housing | Cleared | 4/9/2020 | GUS VINDELL |
| Permit | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/22/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 8/4/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/12/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/3/2020 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Approved | WILLIAM KUEHN |
| Pre-Inspection | 9/14/2020 | Corrections Issued | WILLIAM KUEHN |
| Pre-Inspection | 9/17/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Not Ready for Inspection | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | No Access for Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/23/2020 | Approved | MATTHEW NELSON |
| Insulation | 11/23/2020 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 11/23/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/1/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/15/2020 | Not Ready for Inspection | BEAU COLLINS |
| Interior/Exterior Lathing | 12/22/2020 | Approved | DAVID MATSON |
| Final | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Special/Order Compliance | 2/11/2021 | Approved | DAVID MATSON |
| Wood Frame | 2/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 6/7/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 6/7/2021 | Approved | MICHAEL TEMPLE |
| Green Building Final | 6/7/2021 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 6/7/2021 | Approved | MICHAEL TEMPLE |
| Wood Frame | 6/7/2021 | Approved | MICHAEL TEMPLE |
| Final | 6/14/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 6/14/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Final | 6/17/2021 | OK to Issue CofO | MICHAEL TEMPLE |