6453-6455 N CALHOUN AVE 91401

Certificate Information: 6453-6455 N CALHOUN AVE 91401

Application / Permit
19010-10000-04579
Plan Check / Job No.
B19LA21845
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX AT FRONT
Permit Issued
Issued on 9/1/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 SINA KHOSRAVI
Corrections Issued 10/29/2019 ZAW HAN
Quality Review Completed 11/12/2019 HERNAN ARREOLA
Building Plans Picked Up 11/12/2019 APPLICANT
Green Plans Picked Up 5/1/2020 APPLICANT
Applicant returned to address corrections 8/21/2020 ZAW HAN
Plan Check Approved 8/26/2020 ZAW HAN
Issued 9/1/2020 APPLICANT
CofO in Progress 6/18/2021 MICHAEL TEMPLE
Permit Finaled 7/3/2021 MICHAEL SMITH
CofO Issued 7/3/2021 MICHAEL SMITH
Permit Finaled 7/3/2021 MICHAEL SMITH

Permit Application Clearance Information

"Q" conditions Cleared 11/12/2019 ANNA VAN
CPC Cleared 11/12/2019 ANNA VAN
Address approval Cleared 12/9/2019 ELAINE LEI
Address approval Cleared 12/9/2019 ELAINE LEI
Green Code Cleared 12/23/2019 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 12/30/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 3/10/2020 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 3/12/2020 TERRI OSBORNE
Public Housing Cleared 4/9/2020 GUS VINDELL
Permit Cleared 7/22/2020 GUILLERMO PETRA
Sewer availability Cleared 7/22/2020 GUILLERMO PETRA
Low Impact Development Cleared 8/4/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/12/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/3/2020 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/14/2020 Approved WILLIAM KUEHN
Pre-Inspection 9/14/2020 Corrections Issued WILLIAM KUEHN
Pre-Inspection 9/17/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Not Ready for Inspection BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 No Access for Inspection WILLIAM KUEHN
Green Building Rough 11/23/2020 Approved MATTHEW NELSON
Insulation 11/23/2020 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 11/23/2020 Approved MATTHEW NELSON
Drywall Nailing 12/1/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/15/2020 Not Ready for Inspection BEAU COLLINS
Interior/Exterior Lathing 12/22/2020 Approved DAVID MATSON
Final 2/11/2021 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 2/11/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Final 2/11/2021 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 2/11/2021 Not Ready for Inspection MATTHEW NELSON
Special/Order Compliance 2/11/2021 Approved DAVID MATSON
Wood Frame 2/11/2021 Not Ready for Inspection MATTHEW NELSON
Final 6/7/2021 Not Ready for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 6/7/2021 Approved MICHAEL TEMPLE
Green Building Final 6/7/2021 Corrections Issued MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 6/7/2021 SGSOV Not Ready MICHAEL TEMPLE
Smoke Detectors 6/7/2021 Approved MICHAEL TEMPLE
Wood Frame 6/7/2021 Approved MICHAEL TEMPLE
Final 6/14/2021 Not Ready for Inspection MICHAEL TEMPLE
Green Building Final 6/14/2021 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 6/14/2021 SGSOV Approved MICHAEL TEMPLE
Final 6/17/2021 OK to Issue CofO MICHAEL TEMPLE