5849 N CORBIN AVE 91356
Certificate Information: 5849 N CORBIN AVE 91356
- Application / Permit
- 19010-10000-04512
- Plan Check / Job No.
- B19LA21453
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | FERNANDO FLORES |
| Corrections Issued | 10/31/2019 | FERNANDO FLORES |
| Quality Review Completed | 11/12/2019 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 10/22/2020 | APPLICANT |
| Applicant returned to address corrections | 12/7/2020 | FERNANDO FLORES |
| Plan Check Approved | 2/25/2021 | FERNANDO FLORES |
| Issued | 9/13/2021 | APPLICANT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| CofO in Progress | 12/9/2025 | JON MCHUGH |
| No Progress | 1/5/2026 | JON MCHUGH |
| CofO in Progress | 1/5/2026 | JON MCHUGH |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
| CofO Issued | 4/18/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 10/26/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2020 | JOHN TRIANTAFYLLOS |
| Miscellaneous | Cleared | 11/10/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/10/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 12/7/2020 | COLIN LOREDO |
| Zoning Information File | Cleared | 12/7/2020 | FERNANDO FLORES |
| Low Impact Development | Cleared | 2/18/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/19/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/22/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 11/5/2021 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 12/7/2021 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 12/10/2021 | Approved | SEAN HAUPT |
| Wood Frame | 1/18/2022 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/18/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 2/18/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 2/18/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 2/18/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 2/18/2022 | Corrections Issued | SEAN HAUPT |
| Verify Sprinkler Sign Off | 2/18/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/2/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/16/2022 | Approved | SEAN HAUPT |
| Insulation | 3/24/2022 | Approved | SEAN HAUPT |
| Shower Pan | 3/24/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/20/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 4/20/2022 | Approved | SEAN HAUPT |
| Gas Test | 8/17/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | SEAN HAUPT |
| Final | 1/31/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 1/31/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Not Ready | SEAN HAUPT |
| Service/Power Release | 1/31/2023 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 1/31/2023 | Not Ready for Inspection | SEAN HAUPT |
| Final | 4/25/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/25/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 4/25/2024 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 4/25/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 5/24/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 5/24/2024 | Not Ready for Inspection | JON MCHUGH |
| Special/Order Compliance | 2/26/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 3/4/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 3/4/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 3/4/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 3/4/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 3/4/2025 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 3/4/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Not Ready | JON MCHUGH |
| Final | 10/31/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 10/31/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 10/31/2025 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 10/31/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 12/8/2025 | Approved | JON MCHUGH |
| Final | 12/8/2025 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 12/8/2025 | Approved | JON MCHUGH |
| Service/Power Release | 12/8/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 12/8/2025 | Approved | JON MCHUGH |
| Special/Order Compliance | 1/5/2026 | Corrections Issued | JON MCHUGH |