1402 1/2 N KENTER AVE 90049
Certificate Information: 1402 1/2 N KENTER AVE 90049
- Application / Permit
- 19010-10000-04489
- Plan Check / Job No.
- B19LA21333
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW FACTORY-BUILT HOUSING STRUCTURE FOR ACCESORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 4/27/2020
- Issuing Office
- Current Status
- CofO Issued on 2/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | EVERARDO SANTOS |
| Green Plans Picked Up | 10/22/2019 | APPLICANT |
| Corrections Issued | 10/31/2019 | EVERARDO SANTOS |
| Quality Review Completed | 11/7/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 3/27/2020 | JOHNNY WU |
| Applicant returned to address corrections | 4/13/2020 | JOHNNY WU |
| Plan Check Approved | 4/15/2020 | JOHNNY WU |
| Issued | 4/27/2020 | APPLICANT |
| CofO in Progress | 2/5/2021 | JOHN KIDWELL |
| CofO Issued | 2/18/2021 | VINCENT COTTON |
| Permit Finaled | 2/18/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 11/18/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 11/18/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/20/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 11/20/2019 | ANTHONY MAINEZ |
| Private street | Cleared | 11/27/2019 | DANALYNN DOMINGUEZ |
| Address approval | Cleared | 12/6/2019 | THAN WIN |
| Green Code | Cleared | 12/19/2019 | KHEDER ALRAZAA |
| BHO/Hillside ordinance | Cleared | 3/13/2020 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 3/16/2020 | RAYMOND MUGAMBWA |
| Grading Pre-Inspection | Cleared | 4/8/2020 | EVERARDO SANTOS |
Contact Information
| Contractor | Cover Technologies Inc; Lic. No.: 1039029-B | 1219 W 135TH STREET GARDENA, CA 90247 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Shane, Sveiven; Lic. No.: C89133 | 5900 CANTERBURY DR APT A206 CULVER CITY, CA 90230 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2020 | Partial Inspection | TIM CHRISTENSEN |
| Piling/Pier/Caisson | 6/9/2020 | Partial Approval | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 8/18/2020 | Corrections Issued | TIM CHRISTENSEN |
| PLUMBING-Rough | 8/18/2020 | Corrections Issued | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 8/19/2020 | Partial Approval | TIM CHRISTENSEN |
| Gas Test | 8/19/2020 | Approved | TIM CHRISTENSEN |
| PLUMBING-Rough | 8/19/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 10/16/2020 | Approved | TIM CHRISTENSEN |
| Grounding or Bonding | 10/16/2020 | Approved | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 10/22/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 10/26/2020 | Approved | ROBERT SHELLY |
| Deputy Reinf. Concrete | 10/28/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Drilled-In Anchors | 11/5/2020 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 11/6/2020 | Approved | ROBERT SHELLY |
| ELECTRICAL-Final | 1/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Test | 1/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 1/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Service/Power Release | 1/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sewer | 1/12/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 1/15/2021 | Partial Inspection | KENNETH NAGLE |
| Sewer | 1/15/2021 | Partial Inspection | KENNETH NAGLE |
| PLUMBING-Final | 1/20/2021 | Partial Approval | KENNETH NAGLE |
| Sewer | 1/20/2021 | Approved | KENNETH NAGLE |
| Drywall Nailing | 1/22/2021 | Approved | JUAN VALENZUELA |
| Final | 1/22/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/22/2021 | Approved | JUAN VALENZUELA |
| Green Building Final | 1/22/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 1/22/2021 | Approved | JUAN VALENZUELA |
| Reinforced Concrete Frame | 1/22/2021 | Corrections Issued | JUAN VALENZUELA |
| Reinforced Masonry Frame | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2021 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 1/22/2021 | Approved | JUAN VALENZUELA |
| Final | 1/29/2021 | OK to Issue CofO | JOHN KIDWELL |
| Reinforced Concrete Frame | 1/29/2021 | Approved | JOHN KIDWELL |
| Reinforced Masonry Frame | 1/29/2021 | Approved | JOHN KIDWELL |
| Service/Power Release | 1/29/2021 | Approved | JOHN KIDWELL |