5510 E EATON ST 90042

Certificate Information: 5510 E EATON ST 90042

Application / Permit
19010-10000-04470
Plan Check / Job No.
B19LA21254
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-story Accessory Dwelling Unit with attached covered patio per AB 494 and SB 229.
Permit Issued
Issued on 6/15/2020
Issuing Office
Current Status
Issued on 6/15/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/7/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 HELEN NGUYEN
Corrections Issued 10/15/2019 HELEN NGUYEN
Quality Review Completed 10/27/2019 YOUNG KIM
Building Plans Picked Up 11/13/2019 APPLICANT
Applicant returned to address corrections 1/31/2020 HELEN NGUYEN
Green Plans Picked Up 5/11/2020 APPLICANT
Applicant returned to address corrections 5/19/2020 HELEN NGUYEN
Plan Check Approved 5/21/2020 HELEN NGUYEN
Issued 6/15/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/22/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/22/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 1/22/2020 JEREMY CARTER
Sewer availability Cleared 1/22/2020 EMIL KYUPELYAN
Green Code Cleared 2/26/2020 HELEN NGUYEN
Low Impact Development Cleared 3/9/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/10/2020 CELINA MORENO
GPI Written Notices Cleared 3/11/2020 HELEN NGUYEN
Grading Pre-Inspection Cleared 3/11/2020 HELEN NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/17/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 6/24/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 6/29/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/9/2020 Approved CRAIG VAUGHAN
Piling/Pier/Caisson 7/9/2020 Approved CRAIG VAUGHAN
Sewer 7/28/2020 Approved COREY HUPP
Underground Mechanical 7/28/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 9/2/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/2/2020 Approved CRAIG VAUGHAN
Green Building Rough 9/2/2020 Approved CRAIG VAUGHAN
HVAC-Rough 9/2/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 9/2/2020 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 9/2/2020 Approved CRAIG VAUGHAN
Wood Frame 9/2/2020 Partial Approval CRAIG VAUGHAN
HVAC-Rough 9/8/2020 Approved ENRIQUE MIRELES
Insulation 9/14/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 9/14/2020 Partial Approval RUBEN SALAS
Drywall Nailing 9/21/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/21/2020 Corrections Issued CRAIG VAUGHAN
Underground Mechanical 9/21/2020 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 10/2/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/25/2020 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 1/8/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/8/2021 Corrections Issued CRAIG VAUGHAN
Final 1/8/2021 Corrections Issued CRAIG VAUGHAN
Gas Test 1/8/2021 Approved CRAIG VAUGHAN
Green Building Final 1/8/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/8/2021 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 1/8/2021 Approved CRAIG VAUGHAN
Smoke Detectors 1/8/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/20/2021 Corrections Issued CRAIG VAUGHAN
Final 1/20/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 1/20/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/28/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 1/28/2021 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 3/15/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Final 8/3/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 8/6/2021 Approved CRAIG VAUGHAN
Final 8/6/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 8/6/2021 Approved CRAIG VAUGHAN