1415 W BLAKE AVE 90031

Certificate Information: 1415 W BLAKE AVE 90031

Application / Permit
19010-10000-04462
Plan Check / Job No.
B19LA21204
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT AT REAR PER AB494 AND SB229.
Permit Issued
Issued on 3/11/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 KEVIN MORALES
Corrections Issued 10/15/2019 KEVIN MORALES
Quality Review Completed 10/26/2019 YOUNG KIM
Building Plans Picked Up 11/5/2019 APPLICANT
Green Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 1/2/2020 KEVIN MORALES
Plan Check Approved 3/10/2020 KEVIN MORALES
Issued 3/11/2020 LADBS
Refund in Progress-Status Void 6/22/2020 SELENIA GARCIA
Re-Activate Permit 7/9/2020 SELENIA GARCIA
CofO in Progress 7/24/2021 RUBEN SALAS
CofO in Progress 7/24/2021 RUBEN SALAS
Permit Finaled 7/27/2021 DEROLD HAUFF
CofO Issued 7/27/2021 DEROLD HAUFF
Permit Finaled 7/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/18/2019 ERIK BEASLEY
ZI Cleared 11/18/2019 TERRI OSBORNE
Green Code Cleared 12/13/2019 DONALD CRICHLOW
Low Impact Development Cleared 12/27/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/27/2019 JAMES MORALEZ
Sewer availability Cleared 12/30/2019 EMIL KYUPELYAN
Construction near power lines Cleared 3/8/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/10/2020 JUAN ASHTON

Contact Information

Contractor Owner-Builder       ,
Engineer Jung,, Jason Stanley; Lic. No.: C80569 1032 S PALM AVE      SAN GABRIEL, CA 91776

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/10/2020 Partial Inspection ROBERT VORHIS
Underground Mechanical 6/16/2020 Partial Approval RUBEN SALAS
Underground Mechanical 6/18/2020 Partial Approval OSVALDO PARAMO
Underground Mechanical 6/23/2020 Approved ARTHUR SARGSYAN
Pre-Inspection 7/13/2020 Approved ENRIQUE MIRELES
Underground Mechanical 7/16/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 8/6/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Partial Approval DONALD CRICHLOW
Deputy Wood Construction 10/23/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 10/29/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 10/29/2020 Not Ready for Inspection COREY HUPP
MERV13>=Rough 10/29/2020 Not Ready for Inspection COREY HUPP
Rough-Elec/Plmb/HVAC 10/29/2020 Approved COREY HUPP
Verify Sprinkler Sign Off 10/29/2020 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Partial Approval ROBERT VORHIS
Green Building Rough 12/29/2020 Not Ready for Inspection ROBERT VORHIS
MERV13>=Rough 12/29/2020 Not Ready for Inspection ROBERT VORHIS
Interior/Exterior Lathing 1/14/2021 Partial Approval RICHARD STEINBACH
Shower Pan 1/14/2021 Approved RICHARD STEINBACH
Insulation 1/19/2021 Approved COREY HUPP
Insulation 1/22/2021 No Access for Inspection RUBEN SALAS
Drywall Nailing 1/26/2021 Conditional Approval SCOTT FINNILA
Green Building Rough 1/26/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 5/28/2021 Approved RUBEN SALAS
Drywall Nailing 5/28/2021 Approved RUBEN SALAS
Final 5/28/2021 Not Ready for Inspection RUBEN SALAS
Green Building Final 5/28/2021 Approved RUBEN SALAS
MERV13>=Final 5/28/2021 Approved RUBEN SALAS
MERV13>=Rough 5/28/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Approved RUBEN SALAS
Service/Power Release 5/28/2021 Not Ready for Inspection RUBEN SALAS
Smoke Detectors 5/28/2021 Approved RUBEN SALAS
Final 6/4/2021 Corrections Issued ROBERT VORHIS
Rough-Elec/Plmb/HVAC 6/4/2021 Approved ROBERT VORHIS
Service/Power Release 6/4/2021 Not Ready for Inspection ROBERT VORHIS
Final 7/22/2021 OK to Issue CofO RUBEN SALAS
Service/Power Release 7/22/2021 Approved RUBEN SALAS