4629-4629 1/2 W 18TH ST 90019

Certificate Information: 4629-4629 1/2 W 18TH ST 90019

Application / Permit
19010-10000-04436
Plan Check / Job No.
B19LA21138
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH ATTACHED GARAGE.
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 EVERARDO SANTOS
Green Plans Picked Up 10/17/2019 APPLICANT
Corrections Issued 10/29/2019 EVERARDO SANTOS
Quality Review Completed 11/7/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/7/2019 APPLICANT
Applicant returned to address corrections 12/12/2019 EVERARDO SANTOS
Applicant returned to address corrections 1/24/2020 VU NGUYEN
Plan Check Approved 1/24/2020 VU NGUYEN
Issued 2/10/2020 LADBS
CofO in Progress 9/20/2021 STUART CHAPMAN
Permit Finaled 10/5/2021 DEROLD HAUFF
CofO Issued 10/5/2021 DEROLD HAUFF
Permit Finaled 10/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/21/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/22/2019 THAN WIN
Hydrant and Access approval Cleared 11/22/2019 JOHN CONNEALLY
Green Code Cleared 12/2/2019 EVERARDO SANTOS
Green Code Cleared 12/2/2019 VIVIAN LAO
Low Impact Development Cleared 12/6/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/12/2019 CELINA MORENO
Sewer availability Cleared 12/12/2019 CELINA MORENO

Contact Information

Contractor True Vision Development Inc; Lic. No.: 1047713-B 1332 W PARADE STREET      LONG BEACH, CA 90810
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/30/2020 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/5/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/5/2020 Partial Approval STUART CHAPMAN
METHANE-Barrier 5/5/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Subgrade 5/5/2020 Not Ready for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/26/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 6/22/2020 Partial Approval STUART CHAPMAN
Green Building Rough 6/22/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 6/22/2020 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 6/22/2020 Not Ready for Inspection STUART CHAPMAN
Drywall Nailing 6/29/2020 Partial Approval STUART CHAPMAN
Green Building Rough 6/29/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 7/17/2020 Approved STUART CHAPMAN
HVAC-Rough 7/17/2020 Approved STUART CHAPMAN
PLUMBING-Rough 7/17/2020 Approved STUART CHAPMAN
Shower Pan 8/6/2020 Corrections Issued THOMAS LOGRASSO
Shower Pan 8/11/2020 Approved STUART CHAPMAN
Underground Mechanical 8/11/2020 Corrections Issued STUART CHAPMAN
Underground Mechanical 8/28/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 10/27/2020 Approved STUART CHAPMAN
ELECTRICAL-Rough 10/27/2020 Approved STUART CHAPMAN
Green Building Rough 10/27/2020 Approved STUART CHAPMAN
HVAC-Rough 10/27/2020 Approved STUART CHAPMAN
METHANE-Rough 10/27/2020 Approved STUART CHAPMAN
PLUMBING-Rough 10/27/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/27/2020 Approved STUART CHAPMAN
Insulation 11/4/2020 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 11/4/2020 Partial Approval STUART CHAPMAN
Insulation 11/6/2020 Approved STUART CHAPMAN
Drywall Nailing 11/16/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/16/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 6/4/2021 Not Ready for Inspection STUART CHAPMAN
Final 6/4/2021 Corrections Issued STUART CHAPMAN
HVAC-Final 6/4/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 6/4/2021 Not Ready for Inspection STUART CHAPMAN
Final 7/16/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 7/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 7/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 7/16/2021 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 7/16/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 7/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 7/16/2021 Approved KATHRYN BUTTERWORTH
Final 7/30/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 7/30/2021 Approved SABAS ALONSO
Green Building Final 7/30/2021 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 7/30/2021 Not Ready for Inspection SABAS ALONSO
Deck 8/17/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 8/17/2021 Approved STUART CHAPMAN
Gas Test 8/17/2021 Approved STUART CHAPMAN
HVAC-Final 8/17/2021 Approved STUART CHAPMAN
PLUMBING-Final 8/17/2021 Approved STUART CHAPMAN
Final 9/7/2021 Not Ready for Inspection RUBEN SALAS
Green Building Final 9/7/2021 Approved RUBEN SALAS
Service/Power Release 9/7/2021 Not Ready for Inspection RUBEN SALAS
Final 9/13/2021 Partial Approval STUART CHAPMAN
Service/Power Release 9/13/2021 Approved STUART CHAPMAN
Final 9/20/2021 OK to Issue CofO STUART CHAPMAN