4629-4629 1/2 W 18TH ST 90019
Certificate Information: 4629-4629 1/2 W 18TH ST 90019
- Application / Permit
- 19010-10000-04436
- Plan Check / Job No.
- B19LA21138
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW DUPLEX WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 2/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | EVERARDO SANTOS |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Corrections Issued | 10/29/2019 | EVERARDO SANTOS |
| Quality Review Completed | 11/7/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Applicant returned to address corrections | 12/12/2019 | EVERARDO SANTOS |
| Applicant returned to address corrections | 1/24/2020 | VU NGUYEN |
| Plan Check Approved | 1/24/2020 | VU NGUYEN |
| Issued | 2/10/2020 | LADBS |
| CofO in Progress | 9/20/2021 | STUART CHAPMAN |
| Permit Finaled | 10/5/2021 | DEROLD HAUFF |
| CofO Issued | 10/5/2021 | DEROLD HAUFF |
| Permit Finaled | 10/5/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2019 | THAN WIN |
| Hydrant and Access approval | Cleared | 11/22/2019 | JOHN CONNEALLY |
| Green Code | Cleared | 12/2/2019 | EVERARDO SANTOS |
| Green Code | Cleared | 12/2/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 12/6/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/12/2019 | CELINA MORENO |
| Sewer availability | Cleared | 12/12/2019 | CELINA MORENO |
Contact Information
| Contractor | True Vision Development Inc; Lic. No.: 1047713-B | 1332 W PARADE STREET LONG BEACH, CA 90810 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/30/2020 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/5/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/5/2020 | Partial Approval | STUART CHAPMAN |
| METHANE-Barrier | 5/5/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 5/5/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/26/2020 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/22/2020 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 6/22/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 6/22/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/22/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Drywall Nailing | 6/29/2020 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 6/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/17/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/17/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/17/2020 | Approved | STUART CHAPMAN |
| Shower Pan | 8/6/2020 | Corrections Issued | THOMAS LOGRASSO |
| Shower Pan | 8/11/2020 | Approved | STUART CHAPMAN |
| Underground Mechanical | 8/11/2020 | Corrections Issued | STUART CHAPMAN |
| Underground Mechanical | 8/28/2020 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/27/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/27/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/27/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 10/27/2020 | Approved | STUART CHAPMAN |
| METHANE-Rough | 10/27/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/27/2020 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/27/2020 | Approved | STUART CHAPMAN |
| Insulation | 11/4/2020 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/4/2020 | Partial Approval | STUART CHAPMAN |
| Insulation | 11/6/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 11/16/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/16/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 6/4/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 6/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 6/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 7/16/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 7/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 7/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 7/16/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 7/16/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 7/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 7/16/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 7/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 7/30/2021 | Approved | SABAS ALONSO |
| Green Building Final | 7/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 7/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| Deck | 8/17/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 8/17/2021 | Approved | STUART CHAPMAN |
| Gas Test | 8/17/2021 | Approved | STUART CHAPMAN |
| HVAC-Final | 8/17/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/17/2021 | Approved | STUART CHAPMAN |
| Final | 9/7/2021 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Final | 9/7/2021 | Approved | RUBEN SALAS |
| Service/Power Release | 9/7/2021 | Not Ready for Inspection | RUBEN SALAS |
| Final | 9/13/2021 | Partial Approval | STUART CHAPMAN |
| Service/Power Release | 9/13/2021 | Approved | STUART CHAPMAN |
| Final | 9/20/2021 | OK to Issue CofO | STUART CHAPMAN |