333-335 W 80TH ST 90003

Certificate Information: 333-335 W 80TH ST 90003

Application / Permit
19010-10000-04377
Plan Check / Job No.
B19LA20929
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY 25'x94' DUPLEX WITH ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 1/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 GEORGE ALVAREZ
Green Plans Picked Up 10/16/2019 APPLICANT
Corrections Issued 10/17/2019 GEORGE ALVAREZ
Quality Review Completed 10/19/2019 STANLEY RAAP
Building Plans Picked Up 10/28/2019 APPLICANT
Plan Check Approved 12/18/2019 GEORGE ALVAREZ
Issued 1/2/2020 LADBS
CofO in Progress 7/25/2020 ALEJANDRO DE ARTOLA
Permit Finaled 7/30/2020 DEROLD HAUFF
CofO Issued 7/30/2020 DEROLD HAUFF
Permit Finaled 7/30/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/12/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 11/12/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 11/12/2019 ROBERT DUFF
Sewer availability Cleared 11/12/2019 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 11/13/2019 TERRI OSBORNE
Low Impact Development Cleared 11/13/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/13/2019 CELINA MORENO
Green Code Cleared 11/18/2019 VIVIAN LAO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/17/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 1/21/2020 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Approved EUGENE CASSIDY
Underground Mechanical 2/11/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Approved EUGENE CASSIDY
Insulation 2/13/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 3/27/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval JUSTIN CURTIS
BUILDING-Rough-Frame 4/28/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/28/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/28/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 4/28/2020 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 4/28/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/28/2020 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 4/28/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/28/2020 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/30/2020 Conditional Approval ALEJANDRO DE ARTOLA
HVAC-Rough 4/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 4/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/30/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 5/1/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 5/1/2020 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 5/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 5/1/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/1/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/4/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 5/4/2020 Approved ALEJANDRO DE ARTOLA
Insulation 5/4/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/7/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/7/2020 Approved EUGENE CASSIDY
Sewer 5/7/2020 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 5/12/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/12/2020 Approved BRIAN CHRISTIAN
Pre-Inspection 5/12/2020 Not Ready for Inspection BRIAN CHRISTIAN
Sewer 5/28/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 7/22/2020 Corrections Issued JOSEPH MCGARRY
Final 7/22/2020 Corrections Issued JOSEPH MCGARRY
Gas Test 7/22/2020 Approved JOSEPH MCGARRY
Green Building Final 7/22/2020 Approved JOSEPH MCGARRY
HVAC-Final 7/22/2020 Approved JOSEPH MCGARRY
MERV13>=Final 7/22/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Final 7/22/2020 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 7/22/2020 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 7/22/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 7/24/2020 Approved ALEJANDRO DE ARTOLA
Final 7/24/2020 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 7/24/2020 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 7/24/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/24/2020 Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/24/2020 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/24/2020 Approved ALEJANDRO DE ARTOLA