5116 E CORINGA DR 90042

Certificate Information: 5116 E CORINGA DR 90042

Application / Permit
19010-10000-04336
Plan Check / Job No.
B19LA20740
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW GARAGE AND TWO-STORY ADU
Permit Issued
Issued on 12/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 MIGUEL JIMENEZ
Green Plans Picked Up 10/16/2019 APPLICANT
Corrections Issued 10/18/2019 MIGUEL JIMENEZ
Quality Review Completed 10/24/2019 BILL STUTSMAN
Building Plans Picked Up 11/6/2019 APPLICANT
Applicant returned to address corrections 12/16/2019 MIGUEL JIMENEZ
Plan Check Approved 12/23/2019 MIGUEL JIMENEZ
Issued 12/27/2019 LADBS
CofO in Progress 7/30/2021 CRAIG VAUGHAN
Permit Finaled 8/13/2021 DEROLD HAUFF
CofO Issued 8/13/2021 DEROLD HAUFF
Permit Finaled 8/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/19/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 11/19/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/19/2019 EMIL KYUPELYAN
Green Code Cleared 12/4/2019 COLIN LOREDO
Hydrant and Access approval Cleared 12/4/2019 JOHN CONNEALLY
Low Impact Development Cleared 12/10/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/16/2019 ERIK BEASLEY
GPI Written Notices Cleared 12/23/2019 MIGUEL JIMENEZ
Grading Pre-Inspection Cleared 12/23/2019 MIGUEL JIMENEZ

Contact Information

Contractor B & C Construction Inc; Lic. No.: 1017702-B 4523 EAST 56TH STREET      MAYWOOD, CA 90270
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/4/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 2/10/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 2/18/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/19/2020 Approved CRAIG VAUGHAN
Underground Mechanical 2/19/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/9/2020 Corrections Issued RUBEN SALAS
Green Building Rough 3/9/2020 Not Ready for Inspection RUBEN SALAS
Verify Sprinkler Sign Off 3/9/2020 Not Ready for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/11/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/13/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 5/13/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/13/2020 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/13/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/14/2020 Partial Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/20/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/20/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/20/2020 Approved CRAIG VAUGHAN
HVAC-Rough 5/27/2020 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 5/27/2020 Partial Approval CRAIG VAUGHAN
Underground Mechanical 5/27/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/3/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/3/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/3/2020 Partial Approval CRAIG VAUGHAN
Insulation 6/5/2020 Approved COREY HUPP
Drywall Nailing 6/11/2020 Approved CHRISTOPHER DELLEFIELD
Final 8/18/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/18/2020 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/18/2020 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 8/18/2020 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 8/18/2020 Not Ready for Inspection CRAIG VAUGHAN
Final 11/24/2020 Corrections Issued CRAIG VAUGHAN
Gas Test 11/24/2020 Approved CRAIG VAUGHAN
Green Building Final 11/24/2020 Approved CRAIG VAUGHAN
Service/Power Release 11/24/2020 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 11/24/2020 Approved CRAIG VAUGHAN
Final 11/30/2020 Corrections Issued CRAIG VAUGHAN
Final 12/7/2020 Corrections Issued HAMIK HARTOUNIAN
Service/Power Release 12/7/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 12/10/2020 Conditional Approval CRAIG VAUGHAN
Final 7/26/2021 Corrections Issued CRAIG VAUGHAN
Service/Power Release 7/26/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 7/29/2021 Approved CRAIG VAUGHAN
Final 7/29/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 7/29/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 7/29/2021 Approved CRAIG VAUGHAN
Service/Power Release 7/29/2021 Approved CRAIG VAUGHAN