316 W 93RD ST 90003

Certificate Information: 316 W 93RD ST 90003

Application / Permit
19010-10000-04305
Plan Check / Job No.
B19LA20581
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNIT PER AB494 AND SB229.
Permit Issued
Issued on 4/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 JOHNNY WU
Corrections Issued 10/24/2019 JOHNNY WU
Green Plans Picked Up 10/31/2019 APPLICANT
Quality Review Completed 11/5/2019 JOSE RODRIGUEZ
Building Plans Picked Up 11/14/2019 APPLICANT
Applicant returned to address corrections 1/30/2020 JOHNNY WU
Plan Check Approved 2/27/2020 JOHNNY WU
Issued 4/23/2020 LADBS
CofO in Progress 3/17/2021 EUGENE CASSIDY
Permit Finaled 4/10/2021 DEROLD HAUFF
CofO Issued 4/10/2021 DEROLD HAUFF
Permit Finaled 4/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/27/2019 JAMES MORALEZ
Hydrant and Access approval Cleared 12/6/2019 ROBERT DUFF
Green Code Cleared 12/18/2019 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/14/2020 ERIK BEASLEY
Low Impact Development Cleared 1/14/2020 ORVAL HERNANDEZ-MARCIAL
Sewer availability Cleared 1/14/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 1/30/2020 EMIL KYUPELYAN

Contact Information

Architect Wang,, Sean; Lic. No.: C31230 1000 ABAJO DR. #208      MONTEREY PARK, CA 91754
Contractor Diversfied Construction & Engineering Group Inc; Lic. No.: 768516-B 621 WEST COVINA BOULEVARD      SAN DIMAS, CA 91773
Engineer Chao,, Chun-Ching; Lic. No.: C57893 PO BOX 8422      ROWLAND HEIGHTS, CA 91748

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/23/2020 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/29/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/18/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 8/18/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 8/18/2020 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 8/18/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/24/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/24/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 8/24/2020 Not Ready for Inspection JOSEPH MCGARRY
MERV13>=Rough 8/24/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/5/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 10/5/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 10/5/2020 Corrections Issued EUGENE CASSIDY
HVAC-Rough 10/5/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/5/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/13/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/13/2020 Approved EUGENE CASSIDY
Green Building Rough 10/13/2020 Approved EUGENE CASSIDY
HVAC-Rough 10/13/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 10/13/2020 Approved EUGENE CASSIDY
Insulation 10/20/2020 Approved DAVID FEILER
Drywall Nailing 10/27/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/27/2020 Approved EUGENE CASSIDY
Service/Power Release 12/22/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 12/22/2020 Corrections Issued EUGENE CASSIDY
Final 12/28/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 12/28/2020 Approved EUGENE CASSIDY
Green Building Final 12/28/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 12/28/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/28/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 12/28/2020 Not Ready for Inspection EUGENE CASSIDY
Final 1/6/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 1/6/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Not Required EUGENE CASSIDY
Service/Power Release 1/6/2021 Not Ready for Inspection EUGENE CASSIDY
Sewer 1/6/2021 Approved EUGENE CASSIDY
Smoke Detectors 1/6/2021 Approved EUGENE CASSIDY
Final 2/23/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 2/23/2021 Not Ready for Inspection EUGENE CASSIDY
Final 3/9/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 3/9/2021 Not Ready for Inspection EUGENE CASSIDY
Final 3/15/2021 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 3/15/2021 Not Ready for Inspection EUGENE CASSIDY