565 N MARIPOSA AVE 90004

Certificate Information: 565 N MARIPOSA AVE 90004

Application / Permit
19010-10000-04296
Plan Check / Job No.
B19LA20528
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
5- UNIT APARTMENT BUILDING, 3-STORY IN HEIGHT, 2- STORY OF LIVING SPACES OVER ONE LEVEL PARKING GARAGE
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
Issued on 8/10/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 VU NGUYEN
Corrections Issued 10/22/2019 VU NGUYEN
Quality Review Completed 11/15/2019 QUAN NGHIEM
Disabled Access Plans Picked Up 12/5/2019 APPLICANT
Applicant returned to address corrections 2/21/2020 VU NGUYEN
Applicant returned to address corrections 2/28/2020 VU NGUYEN
Green Plans Picked Up 5/19/2020 APPLICANT
Applicant returned to address corrections 6/26/2020 VU NGUYEN
Applicant returned to address corrections 7/2/2020 VU NGUYEN
Applicant returned to address corrections 8/26/2020 VU NGUYEN
Applicant returned to address corrections 11/24/2020 VU NGUYEN
Plan Check Approved 7/13/2021 VU NGUYEN
Issued 8/10/2021 APPLICANT
Building Plans Picked Up 8/12/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/21/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 11/21/2019 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 1/31/2020 THOMAS LANG
Highway dedication Cleared 1/31/2020 THOMAS LANG
Sewer availability Cleared 1/31/2020 THOMAS LANG
Green Code Cleared 2/18/2020 COLIN LOREDO
"Q" conditions Cleared 2/28/2020 ANACANY HURTADO
DAS Clearance Cleared 4/6/2020 WAI LAU
Low Impact Development Cleared 5/6/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 5/13/2020 WALLIE JONG

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Zamora Juan Jr; Lic. No.: 854854-B 14318 POLK ST      SYLMAR, CA 91342
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 10/21/2021 Partial Inspection DANIEL MC AULIFFE
Wall Anchors 10/21/2021 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/5/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/5/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 2/22/2022 Corrections Issued SORIN CIRSTOIU
Deputy Reinf. Concrete 2/23/2022 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 3/1/2022 Not Ready for Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 3/11/2022 Conditional Approval JONATHAN QUACH
Green Building Rough 4/22/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 4/22/2022 Corrections Issued SORIN CIRSTOIU
Verify Sprinkler Sign Off 4/22/2022 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 5/5/2022 Conditional Approval JONATHAN QUACH
Green Building Rough 6/28/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 6/28/2022 Corrections Issued GREGORY POMISH
Verify Sprinkler Sign Off 6/28/2022 Not Ready for Inspection GREGORY POMISH
Structural Steel Frame 11/7/2022 No Access for Inspection JONATHAN QUACH
Green Building Rough 11/8/2022 Not Ready for Inspection MARK FERRARI
Reinforced Concrete Frame 11/8/2022 Corrections Issued MARK FERRARI
Verify Sprinkler Sign Off 11/8/2022 Not Ready for Inspection MARK FERRARI
Green Building Rough 11/16/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 11/16/2022 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 11/16/2022 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 12/29/2022 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 5/12/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 5/12/2023 Partial Inspection TIMOTHY POWELL
Verify Sprinkler Sign Off 5/12/2023 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 5/15/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 5/15/2023 Partial Approval TIMOTHY POWELL
Verify Sprinkler Sign Off 5/15/2023 Not Ready for Inspection TIMOTHY POWELL
Deputy Reinf. Concrete 5/16/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Not Ready for Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Approval VAHE KELEDJIAN
Deputy Reinf. Concrete 9/14/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 12/21/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 12/21/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 12/21/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 1/11/2024 Approved GREGORY POMISH
Green Building Rough 3/29/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/29/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 4/2/2024 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Approved DAVID BURKHEAD
Footing/Foundation/Slab 4/2/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/2/2024 Partial Inspection DAVID BURKHEAD
Green Building Rough 4/3/2024 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/3/2024 Partial Approval DAVID BURKHEAD
Wood Frame 4/3/2024 Corrections Issued DAVID BURKHEAD
Green Building Rough 4/10/2024 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 4/10/2024 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 4/10/2024 Partial Inspection DAVID BURKHEAD
Wood Frame 4/10/2024 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/18/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/18/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 6/18/2024 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/24/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 6/24/2024 Partial Approval DAVID BURKHEAD
Wood Frame 6/24/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/15/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/15/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/15/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/31/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/31/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/31/2024 Corrections Issued DAVID BURKHEAD
Green Building Rough 8/8/2024 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/8/2024 Partial Approval DAVID BURKHEAD
Wood Frame 8/8/2024 Partial Approval DAVID BURKHEAD
Insulation 8/26/2024 Partial Approval DAVID BURKHEAD
Insulation 2/18/2025 Partial Approval DAVID BURKHEAD
Final 1/14/2026 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 1/14/2026 Conditional Approval DAVID BURKHEAD
Green Building Final 1/14/2026 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 1/14/2026 Approved DAVID BURKHEAD
Reinforced Concrete Frame 1/14/2026 Conditional Approval DAVID BURKHEAD
Reinforced Masonry Frame 1/14/2026 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 1/14/2026 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 1/14/2026 Approved DAVID BURKHEAD
Wood Frame 1/14/2026 Conditional Approval DAVID BURKHEAD
Special/Order Compliance 5/29/2026 Approved RONALD JIMENEZ
Special/Order Compliance 6/5/2026 Approved DAVID BURKHEAD