214 S RAMPART BLVD 90057

Certificate Information: 214 S RAMPART BLVD 90057

Application / Permit
19010-10000-04286
Plan Check / Job No.
B19LA20461
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5 STORY 24 UNIT APARTMENT HOUSE TYPE IIIA OVER 1-LEVEL TYPE 1-A BASEMENT PARKING. 2 UNITS SET ASIDE FOR EXTREMELY LOW INCOME. TOC TIER 1
Permit Issued
Issued on 10/13/2022
Issuing Office
Metro
Current Status
Issued on 10/13/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 HERNAN ARREOLA
Corrections Issued 10/28/2019 HERNAN ARREOLA
Disabled Access Plans Picked Up 11/7/2019 APPLICANT
Quality Review Completed 11/13/2019 BILL STUTSMAN
Building Plans Picked Up 11/15/2019 APPLICANT
Applicant returned to address corrections 2/13/2020 HERNAN ARREOLA
Applicant returned to address corrections 7/13/2020 HERNAN ARREOLA
Green Plans Picked Up 7/15/2020 APPLICANT
Plan Check Approved 4/26/2022 HERNAN ARREOLA
Issued 10/13/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/26/2020 ELAINE LEI
Work Adjacent to Public Way Cleared 3/9/2020 BOK GOH
Construction near power lines Cleared 5/30/2020 RIDWAN HARDY
Low Impact Development Cleared 6/2/2020 ANDRES COVARRUBIAS
Green Code Cleared 7/16/2020 DONALD CRICHLOW
Green Code Cleared 7/16/2020 DONALD CRICHLOW
Trees in Parkway Cleared 8/20/2020 JOHN KIM
Hydrant and Access approval Cleared 3/1/2021 KURT CORRAL
Density Bonus 12.22.A.31 Cleared 5/25/2021 MARITESS GO
Roof/Waste drainage to street Cleared 8/6/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/9/2021 RENZ SORIANO
Sewer availability Cleared 8/9/2021 RENZ SORIANO
Fire Marshall Fire Life Safety Cleared 9/9/2021 MENOA AGHAJANI
DAS Clearance Cleared 9/14/2021 HERNAN ARREOLA
DAS Clearance Cleared 9/14/2021 HERNAN ARREOLA
DAS Clearance Cleared 9/14/2021 WAI LAU
Highway dedication Cleared 10/19/2021 RENZ SORIANO
Frnt yard landscape/Water mgmt Cleared 12/3/2021 ANACANY HURTADO
Miscellaneous Cleared 12/3/2021 ANACANY HURTADO
Opn space landscape/Water mgmt Cleared 12/3/2021 ANACANY HURTADO
Building over 3-story or 36-ft Cleared 1/5/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/5/2022 CALOSHA APPROVED
GPI Written Notices Cleared 1/5/2022 HERNAN ARREOLA
Grading Pre-Inspection Cleared 1/5/2022 HERNAN ARREOLA

Contact Information

Architect Afari,, Frank; Lic. No.: C19872 1453 CLUBVIEW DRIVE      LOS ANGELES, CA 90024
Contractor Owner-Builder       ,
Engineer Lota,, Dante S; Lic. No.: S2314 19325 TRENTHAM AVE      CERRITOS, CA 90701

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/24/2023 Corrections Issued NICK DANERI
Footing/Foundation/Slab 4/3/2023 Corrections Issued NICK DANERI
METHANE-Barrier 4/3/2023 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 4/3/2023 Not Ready for Inspection NICK DANERI
Special/Order Compliance 4/14/2023 Corrections Issued NICK DANERI
Piling/Pier/Caisson 4/19/2023 Partial Approval LARRY ARNICK
Pre-Inspection 4/19/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 4/20/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 5/11/2023 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 5/11/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 5/11/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 5/11/2023 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/11/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 5/15/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 6/21/2023 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/7/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 7/7/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 7/7/2023 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/10/2023 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 8/15/2023 Not Ready for Inspection LARRY ARNICK
T-Bar Ceiling 8/28/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Partial Approval LARRY ARNICK
Deputy Drilled-In Anchors 1/10/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Wood Construction 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval LARRY ARNICK
Green Building Rough 1/16/2024 Partial Approval LARRY ARNICK
METHANE-Rough 1/16/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/16/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 1/16/2024 Partial Approval LARRY ARNICK
Drywall Nailing 3/21/2024 Partial Approval LARRY ARNICK
Green Building Rough 9/13/2024 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/13/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/13/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 9/13/2024 Partial Approval LARRY ARNICK
Green Building Rough 9/24/2024 Not Ready for Inspection RAMAZANALI ALMASI
Interior/Exterior Lathing 9/24/2024 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Rough 9/24/2024 Not Ready for Inspection RAMAZANALI ALMASI
Verify Sprinkler Sign Off 9/24/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 9/24/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 11/27/2024 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 11/27/2024 Partial Approval LARRY ARNICK
METHANE-Rough 11/27/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 11/27/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 11/27/2024 Not Ready for Inspection LARRY ARNICK
Insulation 12/6/2024 Approved LARRY ARNICK
Interior/Exterior Lathing 1/21/2025 Approved PAUL BAZERKANIAN
Interior/Exterior Lathing 2/4/2025 Approved LARRY ARNICK
Special/Order Compliance 3/18/2025 Partial Inspection LARRY ARNICK
Pre-Inspection 10/7/2025 Conditional Approval LARRY ARNICK