1036-1038 N WATSON AVE 90744

Certificate Information: 1036-1038 N WATSON AVE 90744

Application / Permit
19010-10000-04276
Plan Check / Job No.
B19LA20378
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 2-STORY DUPLEX WITH AN ATTACHED 2-CAR CARPORT.
Permit Issued
Issued on 1/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 MICHAEL LOPEZ
Corrections Issued 10/8/2019 MICHAEL LOPEZ
Green Plans Picked Up 10/8/2019 APPLICANT
Quality Review Completed 10/12/2019 STANLEY RAAP
Building Plans Picked Up 10/18/2019 APPLICANT
Plan Check Approved 11/14/2019 MICHAEL LOPEZ
No Progress 12/10/2019 MICHAEL LOPEZ
Plan Check Approved 12/18/2019 MICHAEL LOPEZ
Issued 1/17/2020 LADBS
CofO in Progress 2/9/2021 JOHN KLARIN
Permit Finaled 4/21/2021 DEROLD HAUFF
CofO Issued 4/21/2021 DEROLD HAUFF
Permit Finaled 4/21/2021 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 10/18/2019 ADRIAN SANCHEZ
"Q" conditions Cleared 11/12/2019 SARAHI ORTEGA
Address approval Cleared 11/12/2019 ELENA LOPEZ
CPC Cleared 11/12/2019 SARAHI ORTEGA
CPC Cleared 11/12/2019 SARAHI ORTEGA
Clean Up Green Up Cleared 11/12/2019 SARAHI ORTEGA
Eng Process Fee Ord 176,300 Cleared 11/12/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 11/12/2019 JEREMY CARTER
Low Impact Development Cleared 11/12/2019 JORGE MEJIA LEMUS
Permit Cleared 11/12/2019 ELENA LOPEZ
Sewer availability Cleared 11/12/2019 ELENA LOPEZ
Green Code Cleared 11/13/2019 VIVIAN LAO
Roof/Waste drainage to street Cleared 11/13/2019 CELINA MORENO

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2020 Approved ANSON MAGLASANG
METHANE-Barrier 2/3/2020 Approved ANSON MAGLASANG
METHANE-Subgrade 2/3/2020 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 3/6/2020 Partial Approval ANSON MAGLASANG
Green Building Rough 3/6/2020 Not Ready for Inspection ANSON MAGLASANG
Insulation 3/6/2020 Not Ready for Inspection ANSON MAGLASANG
METHANE-Rough 3/6/2020 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 3/6/2020 Partial Approval ANSON MAGLASANG
Verify Sprinkler Sign Off 3/6/2020 Not Ready for Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 3/11/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/20/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 5/20/2020 Approved JOHN KLARIN
Green Building Rough 5/20/2020 Approved JOHN KLARIN
HVAC-Rough 5/20/2020 Approved JOHN KLARIN
METHANE-Rough 5/20/2020 Approved JOHN KLARIN
PLUMBING-Rough 5/20/2020 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 5/20/2020 Approved JOHN KLARIN
Verify Sprinkler Sign Off 5/20/2020 Approved JOHN KLARIN
Insulation 5/22/2020 Not Ready for Inspection SABAS ALONSO
Insulation 5/26/2020 Approved JOHN KLARIN
Drywall Nailing 5/29/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 5/29/2020 Approved JOHN KLARIN
ELECTRICAL-Final 9/28/2020 Approved JOHN KLARIN
Final 9/28/2020 Corrections Issued JOHN KLARIN
Green Building Final 9/28/2020 Corrections Issued JOHN KLARIN
HVAC-Final 9/28/2020 Approved JOHN KLARIN
PLUMBING-Final 9/28/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Approved JOHN KLARIN
Service/Power Release 9/28/2020 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 9/28/2020 Approved JOHN KLARIN
ELECTRICAL-Final 11/19/2020 Approved JOHN KLARIN
Final 11/19/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 11/19/2020 Conditional Approval JOHN KLARIN
HVAC-Final 11/19/2020 Approved JOHN KLARIN
PLUMBING-Final 11/19/2020 Approved JOHN KLARIN
Service/Power Release 11/19/2020 Not Ready for Inspection JOHN KLARIN
Final 12/17/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 12/17/2020 Conditional Approval JOHN KLARIN
Service/Power Release 12/17/2020 Not Ready for Inspection JOHN KLARIN
Final 1/19/2021 Not Ready for Inspection JOHN KLARIN
Green Building Final 1/19/2021 Partial Approval JOHN KLARIN
Service/Power Release 1/19/2021 Not Ready for Inspection JOHN KLARIN
Final 2/8/2021 OK to Issue CofO JOHN KLARIN
Green Building Final 2/8/2021 Approved JOHN KLARIN
Service/Power Release 2/8/2021 Approved JOHN KLARIN