10759 W WESTMINSTER AVE 90034

Certificate Information: 10759 W WESTMINSTER AVE 90034

Application / Permit
19010-10000-04267
Plan Check / Job No.
B19LA20294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO-STORY, TYPE V, 25'-7" X 31', 1022 SF ADU AT REAR OF R1-1 PROPERTY.
Permit Issued
Issued on 5/2/2020
Issuing Office
Current Status
Issued on 5/2/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 CHUNG-WEN CHUANG
Corrections Issued 10/31/2019 CHUNG-WEN CHUANG
Green Plans Picked Up 11/5/2019 APPLICANT
Quality Review Completed 11/18/2019 KESETE HAREGOT
Building Plans Picked Up 11/19/2019 APPLICANT
Applicant returned to address corrections 3/3/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 4/7/2020 CHUNG-WEN CHUANG
Plan Check Approved 4/8/2020 CHUNG-WEN CHUANG
Issued 5/2/2020 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2020 PAMELA TENEZA
Hydrant and Access approval Cleared 1/24/2020 ROBERT DUFF
Sewer availability Cleared 1/24/2020 PAMELA TENEZA
Specific Plan Cleared 1/28/2020 FREDDY GARCIA
Address approval Cleared 1/31/2020 JEANETTE VONG
Green Code Cleared 3/4/2020 CHUNG-WEN CHUANG
Low Impact Development Cleared 3/4/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/4/2020 JEANIE LAM
Miscellaneous Cleared 3/25/2020 DINAH GARIN
GPI Written Notices Cleared 4/8/2020 CHUNG-WEN CHUANG
Grading Pre-Inspection Cleared 4/8/2020 CHUNG-WEN CHUANG

Contact Information

Contractor Forte Build & Design Inc; Lic. No.: 1026084-B 127 S BRAND BLVD #104      GLENDALE, CA 91204
Engineer Polon,, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/2/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 6/2/2020 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/19/2020 Approved JUSTIN CURTIS
Underground Mechanical 6/23/2020 Approved JUSTIN CURTIS
BUILDING-Rough-Frame 7/7/2020 Not Ready for Inspection JUSTIN CURTIS
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval JUSTIN CURTIS
Green Building Rough 7/7/2020 Not Ready for Inspection JUSTIN CURTIS
Verify Sprinkler Sign Off 7/7/2020 Not Ready for Inspection JUSTIN CURTIS
Wood Frame 7/7/2020 Not Ready for Inspection JUSTIN CURTIS
Deputy Wood Construction 7/13/2020 Conditional Approval JUSTIN CURTIS
PLUMBING-Rough 8/19/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 9/1/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/2/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/3/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Approved OGANES TARAKHCHYAN
Gas Test 9/14/2020 Partial Approval OGANES TARAKHCHYAN
Wood Frame 9/14/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 9/24/2020 Not Ready for Inspection KEVIN SARGSYAN
Sewer 9/24/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/28/2020 Partial Approval KEVIN SARGSYAN
Sewer 9/28/2020 Approved KEVIN SARGSYAN
Shower Pan 9/28/2020 Approved KEVIN SARGSYAN
Underground Mechanical 9/28/2020 Partial Approval KEVIN SARGSYAN
Gas Test 9/30/2020 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 10/2/2020 Partial Approval EVAN COOPER
Insulation 10/7/2020 Approved KEVIN SARGSYAN
Drywall Nailing 10/16/2020 Approved OGANES TARAKHCHYAN
Green Building Rough 10/16/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/16/2020 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/19/2021 Approved EVAN COOPER
ELECTRICAL-Final 3/19/2021 Not Ready for Inspection EVAN COOPER
Final 3/19/2021 Corrections Issued EVAN COOPER
Green Building Final 3/19/2021 Not Ready for Inspection EVAN COOPER
HVAC-Final 3/19/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 3/19/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved EVAN COOPER
Service/Power Release 3/19/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 3/19/2021 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 3/19/2021 Approved EVAN COOPER
ELECTRICAL-Final 4/7/2021 Not Ready for Inspection EVAN COOPER
Gas Test 4/7/2021 Approved EVAN COOPER
PLUMBING-Final 4/7/2021 Approved EVAN COOPER
ELECTRICAL-Final 4/15/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 4/15/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 5/11/2021 Approved EVAN COOPER
Final 6/4/2021 Corrections Issued KENNETH NAGLE
Green Building Final 6/4/2021 Not Ready for Inspection KENNETH NAGLE
Service/Power Release 6/4/2021 Not Ready for Inspection KENNETH NAGLE
Smoke Detectors 6/4/2021 Approved KENNETH NAGLE
Special/Order Compliance 3/1/2024 Corrections Issued KENNETH NAGLE
Final 8/18/2025 No Access for Inspection KIRK SANDERS
Green Building Final 8/18/2025 No Access for Inspection KIRK SANDERS
Service/Power Release 8/18/2025 No Access for Inspection KIRK SANDERS