463-469 W 88TH PL 90003
Certificate Information: 463-469 W 88TH PL 90003
- Application / Permit
- 19010-10000-04261
- Plan Check / Job No.
- B19LA20274
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH AN ATTACHED 2 CAR GARAGE' See Comments
- Permit Issued
- Issued on 8/28/2020
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 6/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | ALBERT SERVIN |
| Corrections Issued | 10/8/2019 | ALBERT SERVIN |
| Quality Review Completed | 10/10/2019 | KEN GILL |
| Building Plans Picked Up | 10/16/2019 | APPLICANT |
| Applicant returned to address corrections | 4/8/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 5/29/2020 | ALBERT SERVIN |
| Green Plans Picked Up | 8/7/2020 | APPLICANT |
| Plan Check Approved | 8/17/2020 | ALBERT SERVIN |
| Issued | 8/28/2020 | APPLICANT |
| CofO in Progress | 11/6/2021 | JOAQUIN GREENOUGH |
| CofO Issued-Status Void | 11/19/2021 | DEROLD HAUFF |
| Permit Finaled-Status Void | 11/19/2021 | DEROLD HAUFF |
| Re-Activate Permit | 2/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/4/2022 | DEROLD HAUFF |
| CofO Corrected | 6/4/2022 | DEROLD HAUFF |
| Permit Finaled | 6/4/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2019 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 12/6/2019 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 12/6/2019 | JOHN KIM |
| Highway dedication | Cleared | 12/6/2019 | JEANIE LAM |
| Green Code | Cleared | 12/18/2019 | ALBERT SERVIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | ERIK BEASLEY |
| Frnt yard landscape/Water mgmt | Cleared | 1/16/2020 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 2/24/2020 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 2/25/2020 | GEORGE SUCHAND |
| Miscellaneous | Cleared | 2/25/2020 | MARC WOERSCHING |
| Permit | Cleared | 2/25/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/25/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/25/2020 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 3/12/2020 | KEVIN ARUCAN |
| Community Plan Implem. Overlay | Cleared | 3/12/2020 | TORI CHEN |
| Community Plan Implem. Overlay | Cleared | 4/20/2020 | HELEN JADALI |
| Miscellaneous | Cleared | 4/23/2020 | ANACANY HURTADO |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/2/2020 | Partial Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 9/2/2020 | Partial Approval | ARTHUR SARGSYAN |
| Underground Mechanical | 9/8/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/18/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/23/2020 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 9/28/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 10/1/2020 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 10/1/2020 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 10/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Conditional Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 2/3/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 2/11/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 2/11/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 2/11/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 2/11/2021 | Not Ready for Inspection | DAVID FEILER |
| MERV13>=Rough | 2/11/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 2/11/2021 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 2/11/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 2/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/17/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/23/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/23/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 2/23/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 2/23/2021 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/23/2021 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 2/23/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 2/23/2021 | Conditional Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/23/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/1/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 3/1/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/1/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/1/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 3/9/2021 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 3/9/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 3/9/2021 | Approved | EUGENE CASSIDY |
| Insulation | 3/11/2021 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 3/11/2021 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 3/16/2021 | Not Ready for Inspection | SCOTT FINNILA |
| Insulation | 3/16/2021 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 3/23/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/2/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| MERV13>=Final | 11/2/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 11/2/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/5/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| MERV13>=Final | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 11/5/2021 | Approved | JOAQUIN GREENOUGH |