2450 N GLENDOWER AVE 90027

Certificate Information: 2450 N GLENDOWER AVE 90027

Application / Permit
19010-10000-04245
Plan Check / Job No.
B19LA20231
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 ZAW HAN
Corrections Issued 10/16/2019 ZAW HAN
Quality Review Completed 10/17/2019 HERNAN ARREOLA
Building Plans Picked Up 10/18/2019 APPLICANT
Green Plans Picked Up 4/3/2020 APPLICANT
Applicant returned to address corrections 4/14/2020 ZAW HAN
Applicant returned to address corrections 7/22/2021 ZAW HAN
Plan Check Approved 7/28/2021 ZAW HAN
Issued 8/10/2021 APPLICANT
CofO in Progress 4/25/2024 JOSEPH MCGARRY
CofO Issued 5/16/2024 DEROLD HAUFF
Permit Finaled 5/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/5/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 11/5/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 11/5/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 11/5/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/5/2019 ADRIAN CASTRO
Sewer availability Cleared 11/5/2019 ADRIAN CASTRO
Green Code Cleared 4/2/2020 ZAW HAN
Trees in Parkway Cleared 7/30/2020 STEPHEN DUPREY
Construction near power lines Cleared 9/1/2020 RIDWAN HARDY
Construction within easement Cleared 9/1/2020 RIDWAN HARDY
Disturb/Remove Protected Trees Cleared 9/11/2020 STEPHEN DUPREY
Permit Cleared 1/26/2021 RENZ SORIANO
Low Impact Development Cleared 4/1/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/1/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/8/2021 MATTHEW CRAIG
Miscellaneous Cleared 7/22/2021 DENZEL HENDERSON
Miscellaneous Cleared 7/22/2021 DENZEL HENDERSON
Frnt yard landscape/Water mgmt Cleared 7/27/2021 NOAH MCCOY
Excavation more than 5-ft deep Cleared 7/28/2021 CALOSHA APPROVED
GPI Written Notices Cleared 7/28/2021 ROBERT HUGHES
Grading Pre-Inspection Cleared 7/28/2021 ROBERT HUGHES

Contact Information

Architect Bertram,, John; Lic. No.: C29063 673 N BERENDO STREET      LOS ANGELES, CA 90004
Contractor Golden Touch Construction Inc; Lic. No.: 892123-B 461 JESSIE STREET      SAN FERNANDO, CA 91340
Engineer Robert, Alan Hollingsworth; Lic. No.: GE2022       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 9/29/2021 Partial Inspection JOSEPH MCGARRY
Pre-Inspection 9/29/2021 Approved JOSEPH MCGARRY
Special/Order Compliance 11/19/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 11/29/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 1/31/2022 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 1/31/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/4/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 2/4/2022 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 5/3/2022 Approved JOSEPH MCGARRY
Deputy Steel/Welding 5/9/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval JOSEPH MCGARRY
Gas Test 6/9/2022 Partial Approval JOSEPH MCGARRY
HVAC-Rough 6/9/2022 Conditional Approval JOSEPH MCGARRY
PLUMBING-Rough 6/9/2022 Approved JOSEPH MCGARRY
Sewer 6/9/2022 Partial Approval JOSEPH MCGARRY
Underground Mechanical 6/9/2022 Partial Approval JOSEPH MCGARRY
Deputy Steel/Welding 7/21/2022 Conditional Approval ADAM ESCOTO
Gas Test 8/29/2022 Approved JEFFREY MEAD
HVAC-Rough 8/29/2022 Approved JEFFREY MEAD
Underground Mechanical 8/29/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 1/25/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 1/25/2023 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved JOSEPH MCGARRY
Green Building Rough 1/25/2023 Approved JOSEPH MCGARRY
Shower Pan 1/25/2023 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 1/25/2023 Approved JOSEPH MCGARRY
Insulation 2/27/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/27/2023 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 3/21/2023 Approved JOSEPH MCGARRY
Drywall Nailing 3/23/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Final 9/28/2023 Approved JOSEPH MCGARRY
Service/Power Release 9/28/2023 Approved JOSEPH MCGARRY
Gas Test 1/30/2024 Partial Approval RICHARD DOCKUS
Sewer 1/30/2024 Approved RICHARD DOCKUS
Underground Mechanical 1/30/2024 Approved RICHARD DOCKUS
Final 3/14/2024 Corrections Issued JOSEPH MCGARRY
Gas Test 3/14/2024 Approved JOSEPH MCGARRY
Green Building Final 3/14/2024 Approved JOSEPH MCGARRY
HVAC-Final 3/14/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 3/14/2024 Approved JOSEPH MCGARRY
Reinforced Concrete Frame 3/14/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 3/14/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Final 4/18/2024 Approved JOSEPH MCGARRY
Final 4/18/2024 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 4/18/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 4/18/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved JOSEPH MCGARRY
Final 4/22/2024 OK to Issue CofO JOSEPH MCGARRY