Pre-Inspection
|
3/18/2024
|
Approved
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
4/3/2024
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Other (see comments)
|
4/4/2024
|
Approved
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
4/4/2024
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Masonry
|
4/10/2024
|
Approved
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
4/10/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Reinf. Masonry
|
4/11/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Green Building Rough
|
4/12/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Reinforced Concrete Frame
|
4/12/2024
|
Partial Approval
|
GRANT WOODS
|
|
Verify Sprinkler Sign Off
|
4/12/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Deputy Reinf. Masonry
|
4/16/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Masonry
|
4/17/2024
|
Approved
|
GRANT WOODS
|
|
Green Building Rough
|
4/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Reinforced Masonry Frame
|
4/17/2024
|
Partial Approval
|
GRANT WOODS
|
|
Verify Sprinkler Sign Off
|
4/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Deputy Reinf. Masonry
|
4/18/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Masonry
|
4/19/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Green Building Rough
|
4/29/2024
|
Approved
|
ALAN NOVAK
|
|
Reinforced Concrete Frame
|
4/29/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Verify Sprinkler Sign Off
|
4/29/2024
|
Approved
|
ALAN NOVAK
|
|
Pre-Inspection
|
4/30/2024
|
Approved
|
ALAN NOVAK
|
|
Reinforced Concrete Frame
|
5/7/2024
|
Approved
|
MICHAEL PETRUSKO
|
|
Footing/Foundation/Slab
|
5/13/2024
|
Partial Approval
|
DERRICK SPENCER
|
|
Final
|
6/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
6/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Green Building Final
|
6/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Reinforced Masonry Frame
|
6/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
SGSOV-Seismic Gas S/O Valve
|
6/17/2024
|
SGSOV Not Ready
|
GRANT WOODS
|
|
Smoke Detectors
|
6/17/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
6/20/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
6/25/2024
|
Partial Approval
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Wood Construction
|
7/16/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
7/17/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Drilled-In Anchors
|
7/25/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/5/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/6/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/9/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/12/2024
|
Approved
|
GRANT WOODS
|
|
Deputy Wood Construction
|
8/12/2024
|
Approved
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/13/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/19/2024
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
8/28/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
8/29/2024
|
Conditional Approval
|
RICARDO ROBLES
|
|
Deputy Wood Construction
|
9/5/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
9/6/2024
|
Approved
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/6/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
9/10/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
9/11/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
9/18/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
9/20/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
9/23/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Wood Construction
|
9/30/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/1/2024
|
Corrections Issued
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/2/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/3/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/3/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/4/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/4/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/7/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/16/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/17/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/18/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/22/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/23/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/24/2024
|
Approved
|
GRANT WOODS
|
|
Deputy Wood Construction
|
10/24/2024
|
Approved
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Wood Frame
|
10/30/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/1/2024
|
Partial Approval
|
GRANT WOODS
|
|
Pre-Inspection
|
11/5/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Deputy Wood Construction
|
11/7/2024
|
Conditional Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2024
|
Partial Approval
|
GRANT WOODS
|
|
Pre-Inspection
|
11/8/2024
|
Partial Approval
|
GRANT WOODS
|
|
Wood Frame
|
11/15/2024
|
Partial Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2024
|
Partial Approval
|
GRANT WOODS
|
|
Insulation
|
12/4/2024
|
Partial Approval
|
GRANT WOODS
|
|
Insulation
|
12/19/2024
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
12/24/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Insulation
|
12/27/2024
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Wood Construction
|
1/6/2025
|
Conditional Approval
|
GRANT WOODS
|
|
Wood Frame
|
1/16/2025
|
Partial Approval
|
NICK LAROCCA
|
|
Insulation
|
1/22/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Special/Order Compliance
|
1/28/2025
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
2/3/2025
|
Conditional Approval
|
GRANT WOODS
|
|
Insulation
|
2/4/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Wood Frame
|
2/13/2025
|
Partial Approval
|
GRANT WOODS
|
|
Wood Frame
|
2/24/2025
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Insulation
|
3/4/2025
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Insulation
|
3/6/2025
|
Partial Approval
|
GRANT WOODS
|
|
Drywall Nailing
|
3/14/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
3/14/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Wood Frame
|
3/14/2025
|
Approved
|
DERRICK SPENCER
|
|
Insulation
|
3/26/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
4/3/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
4/22/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
4/29/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
4/29/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
5/5/2025
|
Approved
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
5/13/2025
|
Approved
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
5/16/2025
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
7/7/2025
|
Corrections Issued
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
7/9/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
7/21/2025
|
Partial Inspection
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
8/6/2025
|
Approved
|
DERRICK SPENCER
|
|
Final
|
8/20/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
8/20/2025
|
Approved
|
DERRICK SPENCER
|
|
Green Building Final
|
8/20/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Reinforced Masonry Frame
|
8/20/2025
|
Approved
|
DERRICK SPENCER
|
|
SGSOV-Seismic Gas S/O Valve
|
8/20/2025
|
SGSOV Approved
|
DERRICK SPENCER
|
|
Smoke Detectors
|
8/20/2025
|
Approved
|
DERRICK SPENCER
|
|
Final
|
8/27/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Green Building Final
|
8/27/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Drywall Nailing
|
9/2/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Masonry Wall/Backfill
|
9/5/2025
|
Approved
|
DERRICK SPENCER
|
|
Masonry Wall/Backfill
|
10/29/2025
|
Approved
|
DERRICK SPENCER
|
|
T-Bar Ceiling
|
11/13/2025
|
Approved
|
DERRICK SPENCER
|
|
Final
|
11/19/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Green Building Final
|
11/19/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Final
|
12/5/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Green Building Final
|
12/5/2025
|
Approved
|
DERRICK SPENCER
|
|
Final
|
12/10/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
5/19/2026
|
Approved
|
DERRICK SPENCER
|