130 S CROFT AVE 1-18 90048
Certificate Information: 130 S CROFT AVE 1-18 90048
- Application / Permit
- 19010-10000-04237
- Plan Check / Job No.
- B19LA20192
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 120' X 80'-9" 4 STORY 18 UNIT APARTMENT BUILDING OVER A SUBTERRANEAN GARAGE
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | MICHAEL PEREZ |
| Disabled Access Plans Picked Up | 10/7/2019 | APPLICANT |
| Green Plans Picked Up | 10/7/2019 | APPLICANT |
| Corrections Issued | 10/19/2019 | MICHAEL PEREZ |
| Quality Review Completed | 10/31/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Applicant returned to address corrections | 3/10/2020 | MICHAEL PEREZ |
| Plan Check Approved | 3/16/2020 | MICHAEL PEREZ |
| Issued | 1/21/2021 | APPLICANT |
| CofO in Progress | 5/26/2023 | EDWIN GREGORYONA |
| Permit Finaled | 6/2/2023 | TED RIES |
| CofO Issued | 6/2/2023 | TED RIES |
| Permit Finaled | 6/2/2023 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 11/12/2019 | JEREMY CARTER |
| Internal circulation | Cleared | 1/3/2020 | EDUARDO HERMOSO |
| Sewer availability | Cleared | 1/8/2020 | THOMAS LANG |
| Permit | Cleared | 2/3/2020 | EMIL KYUPELYAN |
| Frnt yard landscape/Water mgmt | Cleared | 2/10/2020 | DENZEL HENDERSON |
| Opn space landscape/Water mgmt | Cleared | 2/10/2020 | DENZEL HENDERSON |
| Trees in Parkway | Cleared | 2/10/2020 | JOHN KIM |
| Work Adjacent to Public Way | Cleared | 2/11/2020 | ROSA SILVA |
| Fire Marshall Fire Life Safety | Cleared | 2/19/2020 | WILLIAM JOHNS |
| Green Code | Cleared | 2/19/2020 | KHEDER ALRAZAA |
| Methane Ordinance | Cleared | 2/19/2020 | WILLIAM JOHNS |
| Building over 3-story or 36-ft | Cleared | 2/28/2020 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 2/28/2020 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 3/2/2020 | SHINE LIN |
| Construction near power lines | Cleared | 3/8/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/8/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/13/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/16/2020 | EMIL KYUPELYAN |
Contact Information
| Architect | Taylor,, Robert James; Lic. No.: C24422 | 1416 STANFORD DRIVE GLENDALE, CA 91205 |
| Contractor | Owner-Builder | , |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 321 E FAIRVIEW AVE APT 307 GLENDALE, CA 91207 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/29/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 5/3/2021 | Partial Approval | JONATHAN QUACH |
| METHANE-Barrier | 5/3/2021 | Partial Inspection | JONATHAN QUACH |
| METHANE-Subgrade | 5/3/2021 | Partial Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 5/13/2021 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 5/13/2021 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Subgrade | 5/13/2021 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Methane Barrier | 6/11/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Methane Barrier | 6/14/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Methane Barrier | 6/17/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 7/2/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 7/2/2021 | Partial Approval | JONATHAN QUACH |
| METHANE-Barrier | 7/2/2021 | Conditional Approval | JONATHAN QUACH |
| METHANE-Subgrade | 7/2/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Special/Order Compliance | 7/16/2021 | Approved | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 7/20/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 7/20/2021 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 7/21/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 7/27/2021 | Conditional Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 8/9/2021 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/29/2021 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 9/29/2021 | Approved | EDWIN GREGORYONA |
| METHANE-Subgrade | 9/29/2021 | Approved | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/30/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 10/8/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Rough | 10/8/2021 | Approved | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 10/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 10/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 10/8/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Rough | 11/2/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 11/2/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 11/2/2021 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Shotcrete | 11/10/2021 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 11/15/2021 | Partial Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 11/15/2021 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 11/15/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 11/22/2021 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 11/24/2021 | Partial Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 11/24/2021 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 11/24/2021 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 12/13/2021 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 12/13/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 12/13/2021 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Wood Construction | 12/15/2021 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Order to Comply Issued | EDWIN GREGORYONA |
| Green Building Rough | 1/11/2022 | Partial Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 1/11/2022 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 2/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 2/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Rough | 2/3/2022 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 2/3/2022 | Approved | EDWIN GREGORYONA |
| Wood Frame | 2/3/2022 | Approved | EDWIN GREGORYONA |
| Wood Frame | 2/24/2022 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 3/17/2022 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 3/25/2022 | Approved | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 4/1/2022 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 4/18/2022 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 4/28/2022 | Approved | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 6/27/2022 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 1/12/2023 | Approved | EDWIN GREGORYONA |
| Final | 3/8/2023 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/8/2023 | Approved | EDWIN GREGORYONA |
| Green Building Final | 3/8/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 3/8/2023 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 3/8/2023 | Approved | EDWIN GREGORYONA |
| Final | 5/5/2023 | Conditional Approval | EDWIN GREGORYONA |
| Green Building Final | 5/5/2023 | Approved | EDWIN GREGORYONA |