130 S CROFT AVE 1-18 90048

Certificate Information: 130 S CROFT AVE 1-18 90048

Application / Permit
19010-10000-04237
Plan Check / Job No.
B19LA20192
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 120' X 80'-9" 4 STORY 18 UNIT APARTMENT BUILDING OVER A SUBTERRANEAN GARAGE
Permit Issued
Issued on 1/21/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 MICHAEL PEREZ
Disabled Access Plans Picked Up 10/7/2019 APPLICANT
Green Plans Picked Up 10/7/2019 APPLICANT
Corrections Issued 10/19/2019 MICHAEL PEREZ
Quality Review Completed 10/31/2019 QUAN NGHIEM
Building Plans Picked Up 11/4/2019 APPLICANT
Applicant returned to address corrections 3/10/2020 MICHAEL PEREZ
Plan Check Approved 3/16/2020 MICHAEL PEREZ
Issued 1/21/2021 APPLICANT
CofO in Progress 5/26/2023 EDWIN GREGORYONA
Permit Finaled 6/2/2023 TED RIES
CofO Issued 6/2/2023 TED RIES
Permit Finaled 6/2/2023 TED RIES

Permit Application Clearance Information

Address approval Cleared 11/12/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/12/2019 THOMAS LANG
Hydrant and Access approval Cleared 11/12/2019 JEREMY CARTER
Internal circulation Cleared 1/3/2020 EDUARDO HERMOSO
Sewer availability Cleared 1/8/2020 THOMAS LANG
Permit Cleared 2/3/2020 EMIL KYUPELYAN
Frnt yard landscape/Water mgmt Cleared 2/10/2020 DENZEL HENDERSON
Opn space landscape/Water mgmt Cleared 2/10/2020 DENZEL HENDERSON
Trees in Parkway Cleared 2/10/2020 JOHN KIM
Work Adjacent to Public Way Cleared 2/11/2020 ROSA SILVA
Fire Marshall Fire Life Safety Cleared 2/19/2020 WILLIAM JOHNS
Green Code Cleared 2/19/2020 KHEDER ALRAZAA
Methane Ordinance Cleared 2/19/2020 WILLIAM JOHNS
Building over 3-story or 36-ft Cleared 2/28/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 2/28/2020 CALOSHA APPROVED
DAS Clearance Cleared 3/2/2020 SHINE LIN
Construction near power lines Cleared 3/8/2020 RIDWAN HARDY
Construction within easement Cleared 3/8/2020 RIDWAN HARDY
Low Impact Development Cleared 3/13/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/16/2020 EMIL KYUPELYAN

Contact Information

Architect Taylor,, Robert James; Lic. No.: C24422 1416 STANFORD DRIVE      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 321 E FAIRVIEW AVE APT 307      GLENDALE, CA 91207

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/29/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/3/2021 Partial Approval JONATHAN QUACH
METHANE-Barrier 5/3/2021 Partial Inspection JONATHAN QUACH
METHANE-Subgrade 5/3/2021 Partial Inspection JONATHAN QUACH
Footing/Foundation/Slab 5/13/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 5/13/2021 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 5/13/2021 Partial Inspection EDWIN GREGORYONA
Deputy Methane Barrier 6/11/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/14/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/17/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 7/2/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 7/2/2021 Partial Approval JONATHAN QUACH
METHANE-Barrier 7/2/2021 Conditional Approval JONATHAN QUACH
METHANE-Subgrade 7/2/2021 Not Ready for Inspection JONATHAN QUACH
Special/Order Compliance 7/16/2021 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 7/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/20/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/21/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/27/2021 Conditional Approval TIMOTHY BUXTON
Masonry Wall/Backfill 8/9/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/29/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/29/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 9/29/2021 Approved EDWIN GREGORYONA
METHANE-Subgrade 9/29/2021 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 9/30/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/7/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/8/2021 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 10/8/2021 Approved EDWIN GREGORYONA
Masonry Wall/Backfill 10/8/2021 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 10/8/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/8/2021 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 11/2/2021 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/2/2021 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 11/2/2021 Partial Inspection EDWIN GREGORYONA
Deputy Shotcrete 11/10/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/15/2021 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/15/2021 Partial Inspection EDWIN GREGORYONA
Wood Frame 11/15/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 11/22/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/24/2021 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/24/2021 Partial Inspection EDWIN GREGORYONA
Wood Frame 11/24/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 12/13/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/13/2021 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 12/13/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 12/15/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Order to Comply Issued EDWIN GREGORYONA
Green Building Rough 1/11/2022 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/11/2022 Partial Inspection EDWIN GREGORYONA
Green Building Rough 2/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 2/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 2/3/2022 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/3/2022 Approved EDWIN GREGORYONA
Wood Frame 2/3/2022 Approved EDWIN GREGORYONA
Wood Frame 2/24/2022 Approved EDWIN GREGORYONA
Drywall Nailing 3/17/2022 Partial Approval EDWIN GREGORYONA
Insulation 3/25/2022 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 4/1/2022 Approved EDWIN GREGORYONA
Drywall Nailing 4/18/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/28/2022 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 6/27/2022 Approved EDWIN GREGORYONA
Pre-Inspection 1/12/2023 Approved EDWIN GREGORYONA
Final 3/8/2023 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/8/2023 Approved EDWIN GREGORYONA
Green Building Final 3/8/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 3/8/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 3/8/2023 Approved EDWIN GREGORYONA
Final 5/5/2023 Conditional Approval EDWIN GREGORYONA
Green Building Final 5/5/2023 Approved EDWIN GREGORYONA