15650 W SHERMAN WAY 91406

Certificate Information: 15650 W SHERMAN WAY 91406

Application / Permit
19010-10000-04191
Plan Check / Job No.
B19LA20057
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Car Wash
Work Description
CONSTRUCT NEW ONE STORY TUNNEL CAR WASH BUILDING W/ EQUIPMENT ROOM PER ZA-2017-4824-ZV-CU-CUB
Permit Issued
Issued on 12/4/2020
Issuing Office
Current Status
CofO in Progress on 3/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 SAM CHANG
Corrections Issued 10/11/2019 SAM CHANG
Quality Review Completed 10/19/2019 STANLEY RAAP
Building Plans Picked Up 12/4/2019 APPLICANT
Disabled Access Plans Picked Up 12/4/2019 APPLICANT
Green Plans Picked Up 7/13/2020 APPLICANT
Applicant returned to address corrections 7/14/2020 SAM CHANG
Applicant returned to address corrections 9/30/2020 SAM CHANG
Plan Check Approved 12/4/2020 SAM CHANG
Issued 12/4/2020 APPLICANT
CofO in Progress 3/12/2024 CAMERON CHABAN
CofO in Progress 3/14/2024 CAMERON CHABAN

Permit Application Clearance Information

Green Code Cleared 7/13/2020 SAM CHANG
Eng Process Fee Ord 176,300 Cleared 7/22/2020 GUILLERMO PETRA
Sewer availability Cleared 8/26/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 8/31/2020 MATTHEW CRAIG
DAS Clearance Cleared 9/3/2020 SAM CHANG
Low Impact Development Cleared 9/15/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/17/2020 GUILLERMO PETRA
CPC Cleared 9/25/2020 ANACANY HURTADO
ZA Case Cleared 9/25/2020 ANACANY HURTADO
Trees in Parkway Cleared 11/18/2020 JOHN KIM

Contact Information

Contractor Channel Development Inc; Lic. No.: 652823-B 4332 LOUISE AVENUE      ENCINO, CA 91316
Engineer Ghaderi,, Nader; Lic. No.: C36475 28405 SAND CANYON ROAD STE B      CANYON COUNTRY, CA 91387
Engineer Pbi, Perry Builder, Inc.; Lic. No.: C91400       ,
Landscape Architect Eichelberger,, Derrik Tate; Lic. No.: LA3513 202 E COTA      SANTA BARBARA, CA 93101

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/15/2021 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 5/4/2021 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 5/6/2021 Partial Inspection JEFFREY FULTON
Green Building Rough 5/7/2021 Not Ready for Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 5/7/2021 Not Ready for Inspection CAMERON CHABAN
Wood Frame 5/7/2021 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/14/2021 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/24/2021 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/25/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 6/14/2021 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 6/16/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 6/21/2021 Not Ready for Inspection HAMID PISHEHVAR
Verify Sprinkler Sign Off 6/21/2021 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 6/21/2021 Not Ready for Inspection HAMID PISHEHVAR
Footing/Foundation/Slab 6/28/2021 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 7/2/2021 Approved JEFFREY DURAN
Green Building Rough 7/7/2021 Partial Inspection CAMERON CHABAN
Light Gage Steel Frame 7/7/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 7/7/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 7/15/2021 Approved KENNETH ROBERTS
Verify Sprinkler Sign Off 7/15/2021 Not Ready for Inspection KENNETH ROBERTS
Wood Frame 7/15/2021 Partial Approval KENNETH ROBERTS
Insulation 7/19/2021 Approved CAMERON CHABAN
Drywall Nailing 7/22/2021 Partial Approval CAMERON CHABAN
Interior/Exterior Lathing 7/30/2021 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 8/11/2021 Partial Approval CAMERON CHABAN
Reinforced Masonry Frame 8/17/2021 Partial Approval JONATHAN QUACH
Verify Sprinkler Sign Off 8/24/2021 Partial Inspection CAMERON CHABAN
Wood Frame 8/24/2021 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 8/30/2021 Approved DANIEL VARNUM
Interior/Exterior Lathing 10/26/2021 Partial Approval DANNY RODRIGUEZ
Final 11/16/2021 Partial Inspection CAMERON CHABAN
Green Building Final 11/16/2021 Not Ready for Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 11/16/2021 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 11/16/2021 Approved CAMERON CHABAN
Wood Frame 11/16/2021 Approved CAMERON CHABAN
Final 1/27/2022 Partial Inspection CAMERON CHABAN
Green Building Final 1/27/2022 Not Ready for Inspection CAMERON CHABAN
Final 5/10/2022 Partial Inspection CAMERON CHABAN
Green Building Final 5/10/2022 Approved CAMERON CHABAN
Final 5/16/2022 Not Ready for Inspection JEFFREY FULTON
Final 5/18/2022 Conditional Approval CAMERON CHABAN
Final 3/12/2024 OK to Issue CofO CAMERON CHABAN