12062 W NEENACH ST 91352

Certificate Information: 12062 W NEENACH ST 91352

Application / Permit
19010-10000-04166
Plan Check / Job No.
B19LA19880
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-story Accessory Dwelling Unit per AB 494 and SB 229.
Permit Issued
Issued on 2/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 HELEN NGUYEN
Corrections Issued 10/15/2019 HELEN NGUYEN
Green Plans Picked Up 10/18/2019 APPLICANT
Quality Review Completed 10/27/2019 YOUNG KIM
Building Plans Picked Up 12/6/2019 APPLICANT
Plan Check Approved 2/4/2020 HELEN NGUYEN
Issued 2/24/2020 LADBS
CofO in Progress 8/17/2021 JOHN HAYES
CofO Issued 9/18/2021 MICHAEL SMITH
Permit Finaled 9/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/20/2019 ERIK BEASLEY
Clean Up Green Up Cleared 12/20/2019 SOPHIE GABEL-SCHEINBAU
Construction near power lines Cleared 12/21/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/2/2020 THAN WIN
Green Code Cleared 1/2/2020 VIVIAN LAO
Low Impact Development Cleared 1/2/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/2/2020 THAN WIN
Sewer availability Cleared 1/2/2020 THAN WIN
Hydrant and Access approval Cleared 1/3/2020 JEREMY CARTER

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/3/2020 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/5/2020 Approved JOHN HAYES
Green Building Rough 3/5/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 3/5/2020 Approved JOHN HAYES
Verify Sprinkler Sign Off 3/5/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/17/2020 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 3/17/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/29/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/29/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/29/2020 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 4/29/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/27/2020 Partial Approval JOHN HAYES
Green Building Rough 5/27/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 5/27/2020 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Approval JOHN HAYES
Wood Frame 6/5/2020 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 7/6/2020 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Partial Approval JOHN HAYES
Green Building Rough 7/6/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/6/2020 Approved JOHN HAYES
Sewer 7/6/2020 Approved JOHN HAYES
Verify Sprinkler Sign Off 7/6/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Partial Approval PIERRE VEGA
Deputy Wood Construction 8/17/2020 Partial Approval MATTHEW NELSON
Deputy Wood Construction 8/18/2020 Partial Approval PIERRE VEGA
BUILDING-Rough-Frame 10/9/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 10/9/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/9/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 10/9/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/9/2020 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 10/9/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/16/2020 Approved JOHN HAYES
Green Building Rough 10/16/2020 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 10/16/2020 Approved JOHN HAYES
Verify Sprinkler Sign Off 10/16/2020 Approved JOHN HAYES
Interior/Exterior Lathing 11/25/2020 Partial Approval JOHN HAYES
Drywall Nailing 12/15/2020 Approved MICHEL ABAJAN
Shower Pan 1/13/2021 Approved JOHN HAYES
Interior/Exterior Lathing 1/28/2021 Approved JOHN HAYES
ELECTRICAL-Final 8/5/2021 Not Ready for Inspection JOHN HAYES
Final 8/5/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 8/5/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 8/5/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 8/5/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 8/5/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/5/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 8/5/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 8/5/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 8/10/2021 Not Ready for Inspection JOHN HAYES
Final 8/10/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 8/10/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 8/10/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 8/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 8/10/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 8/10/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 8/10/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 8/17/2021 Approved JOHN HAYES
Final 8/17/2021 OK to Issue CofO JOHN HAYES
Footing/Foundation/Slab 8/17/2021 Approved JOHN HAYES
Green Building Final 8/17/2021 Approved JOHN HAYES
HVAC-Final 8/17/2021 Approved JOHN HAYES
PLUMBING-Final 8/17/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/17/2021 SGSOV Approved JOHN HAYES
Service/Power Release 8/17/2021 Approved JOHN HAYES
Smoke Detectors 8/17/2021 Approved JOHN HAYES