635 1/2 W 32ND ST 90731

Certificate Information: 635 1/2 W 32ND ST 90731

Application / Permit
19010-10000-04159
Plan Check / Job No.
B19LA19858
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ADU PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 10/12/2022
Issuing Office
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 FERNANDO FLORES
Corrections Issued 10/3/2019 FERNANDO FLORES
Quality Review Completed 10/15/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 10/17/2019 APPLICANT
Plan Check Approved 10/12/2022 FERNANDO FLORES
Issued 10/12/2022 APPLICANT
CofO in Progress 4/12/2024 ANSON MAGLASANG
Permit Finaled 4/12/2024 ANSON MAGLASANG
CofO Issued 4/12/2024 ANSON MAGLASANG
Permit Finaled 4/12/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/1/2020 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 10/27/2020 CHINH DINH
Permit Cleared 10/27/2020 CHINH DINH
Roof/Waste drainage to street Cleared 10/27/2020 CHINH DINH
Sewer availability Cleared 10/27/2020 CHINH DINH
Hydrant and Access approval Cleared 11/16/2020 MATTHEW CRAIG
Low Impact Development Cleared 4/11/2022 KHAING AYE
Coastal Zone Cleared 7/7/2022 DANIEL CORONADO
Green Code Cleared 7/22/2022 COLIN LOREDO
Zoning Information File Cleared 7/22/2022 FERNANDO FLORES
Grading Pre-Inspection Cleared 9/28/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2022 Partial Inspection ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 11/14/2022 No Access for Inspection ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 11/28/2022 Corrections Issued ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 12/12/2022 Approved JOHN KLARIN
PLUMBING-Rough 1/23/2023 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 2/2/2023 Not Ready for Inspection JULIAN AMAYA
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Not Ready for Inspection JULIAN AMAYA
Green Building Rough 2/2/2023 Not Ready for Inspection JULIAN AMAYA
Verify Sprinkler Sign Off 2/2/2023 Not Ready for Inspection JULIAN AMAYA
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 3/23/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 3/23/2023 Approved JOHN KLARIN
Green Building Rough 3/23/2023 Approved JOHN KLARIN
HVAC-Rough 3/23/2023 Approved JOHN KLARIN
PLUMBING-Rough 3/23/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/23/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 3/30/2023 Partial Approval ANSON MAGLASANG
Insulation 4/6/2023 Approved JAMES CHAVEZ
Drywall Nailing 4/25/2023 Approved ANSON MAGLASANG
Shower Pan 4/25/2023 Approved ANSON MAGLASANG
Pre-Inspection 5/30/2023 Partial Inspection JAMES CHAVEZ
Underground Mechanical 5/30/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 7/19/2023 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 7/19/2023 Partial Approval JAMES CHAVEZ
Service/Power Release 9/1/2023 Not Ready for Inspection JAMES CHAVEZ
Final 12/11/2023 No Access for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 12/11/2023 No Access for Inspection JAMES CHAVEZ
Green Building Final 12/11/2023 No Access for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 12/11/2023 No Access for Inspection JAMES CHAVEZ
Smoke Detectors 12/11/2023 No Access for Inspection JAMES CHAVEZ
Final 12/19/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 12/19/2023 Approved JAMES CHAVEZ
Green Building Final 12/19/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 12/19/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 12/19/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready JAMES CHAVEZ
Final 3/7/2024 No Access for Inspection EUGENE CASSIDY
Green Building Final 3/7/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 3/7/2024 No Access for Inspection EUGENE CASSIDY
Smoke Detectors 3/7/2024 No Access for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 3/19/2024 No Access for Inspection JAMES CHAVEZ
Final 3/22/2024 Corrections Issued JAMES CHAVEZ
Final 4/2/2024 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 4/2/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Approved JAMES CHAVEZ
Service/Power Release 4/2/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 4/2/2024 Not Ready for Inspection JAMES CHAVEZ
Final 4/8/2024 Corrections Issued JAMES CHAVEZ
Service/Power Release 4/8/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 4/8/2024 No Access for Inspection JAMES CHAVEZ
Final 4/12/2024 OK to Issue CofO ANSON MAGLASANG
Service/Power Release 4/12/2024 Approved ANSON MAGLASANG
Smoke Detectors 4/12/2024 Approved ANSON MAGLASANG