1545 W 36TH PL 90018
Certificate Information: 1545 W 36TH PL 90018
- Application / Permit
- 19010-10000-04137
- Plan Check / Job No.
- B19LA19797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH 2-CAR ATTACHED GARAGE (Each of the Duplex unit is to be occupied by a family. Not to be used as guest rooms or other type of flexible use).
- Permit Issued
- Issued on 5/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | ERIC WONG |
| Corrections Issued | 10/1/2019 | ERIC WONG |
| Green Plans Picked Up | 10/1/2019 | APPLICANT |
| Quality Review Completed | 10/4/2019 | PETER KIM |
| Building Plans Picked Up | 12/13/2019 | APPLICANT |
| Applicant returned to address corrections | 4/6/2020 | ERIC WONG |
| Plan Check Approved | 4/8/2020 | ERIC WONG |
| Plan Check Approved | 4/8/2020 | MARVINA ANDERSON |
| Plan Check Approved | 4/15/2020 | ERIC WONG |
| Issued | 5/5/2020 | LADBS |
| CofO in Progress | 12/17/2020 | ROBERT MCDOWELL |
| Permit Finaled | 3/29/2021 | DEROLD HAUFF |
| CofO Issued | 3/29/2021 | DEROLD HAUFF |
| Permit Finaled | 3/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2020 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2020 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 1/7/2020 | GILBERT URREA |
| Sewer availability | Cleared | 1/7/2020 | JAMES MORALEZ |
| Low Impact Development | Cleared | 2/4/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/4/2020 | JEANETTE VONG |
| Green Code | Cleared | 2/25/2020 | ERIC WONG |
| Permit | Cleared | 4/9/2020 | JEANIE LAM |
Contact Information
| Contractor | Luban Z Construction Corp; Lic. No.: 1033129-B | 5695 SORREL HILLS AVE CHINO HILLS, CA 91709 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/6/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 5/6/2020 | Approved | ROBERT MCDOWELL |
| Deputy Reinf. Concrete | 5/15/2020 | Conditional Approval | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 5/15/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 5/15/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 5/15/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 5/15/2020 | Approved | ROBERT MCDOWELL |
| Deputy Reinf. Concrete | 5/18/2020 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/19/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/19/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 6/19/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 6/19/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 6/19/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/14/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Rough | 7/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 7/14/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 7/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 7/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/21/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Final | 7/21/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 7/21/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 7/21/2020 | Corrections Issued | ROBERT MCDOWELL |
| Insulation | 7/21/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/21/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 7/21/2020 | Approved | ROBERT MCDOWELL |
| Wood Frame | 7/21/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/24/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 7/24/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 7/24/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 7/24/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 7/24/2020 | Conditional Approval | ROBERT MCDOWELL |
| Insulation | 7/24/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 7/24/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/24/2020 | Approved | ROBERT MCDOWELL |
| Gas Test | 8/7/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 8/7/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 8/7/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 8/18/2020 | Approved | ROBERT MCDOWELL |
| Final | 8/18/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 8/18/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 8/18/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 8/18/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 8/18/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 8/18/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 8/18/2020 | Approved | ROBERT MCDOWELL |
| Gas Test | 9/2/2020 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 9/2/2020 | Approved | ROBERT MCDOWELL |
| Final | 11/25/2020 | Conditional Approval | ROBERT MCDOWELL |
| Final | 12/17/2020 | OK to Issue CofO | ROBERT MCDOWELL |