1513 N ISLAND AVE 90744
Certificate Information: 1513 N ISLAND AVE 90744
- Application / Permit
- 19010-10000-04125
- Plan Check / Job No.
- B19LA19729
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | ERIC WONG |
| Corrections Issued | 10/1/2019 | ERIC WONG |
| Quality Review Completed | 10/4/2019 | PETER KIM |
| Building Plans Picked Up | 10/21/2019 | APPLICANT |
| Plan Check Approved | 2/14/2020 | ERIC WONG |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 1/26/2021 | JOHN KLARIN |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
| CofO Issued | 2/6/2021 | DEROLD HAUFF |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 11/7/2019 | VIVIAN LAO |
| Address approval | Cleared | 1/10/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/10/2020 | JEREMY CARTER |
| Sewer availability | Cleared | 1/10/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 2/3/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/3/2020 | THOMAS LANG |
Contact Information
| Contractor | J M E Construction; Lic. No.: 921816-B | 1450 RONAN AVENUE WILMINGTON, CA 90744 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 3/27/2020 | Approved | JOHN KLARIN |
| METHANE-Barrier | 3/27/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 3/27/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/27/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 5/5/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/14/2020 | Approved | JOHN KLARIN |
| Gas Test | 7/14/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/14/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/14/2020 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/30/2020 | Conditional Approval | JOHN KLARIN |
| Green Building Rough | 7/30/2020 | Approved | JOHN KLARIN |
| MERV13>=Rough | 7/30/2020 | Approved | JOHN KLARIN |
| Underground Mechanical | 7/30/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/30/2020 | Approved | JOHN KLARIN |
| Insulation | 7/31/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/11/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/11/2020 | Approved | JOHN KLARIN |
| Shower Pan | 8/11/2020 | Approved | JOHN KLARIN |
| Service/Power Release | 10/1/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/23/2020 | Approved | JOHN KLARIN |
| Final | 12/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 12/23/2020 | Approved | JOHN KLARIN |
| METHANE-Final | 12/23/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 12/23/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 12/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 12/23/2020 | Approved | JOHN KLARIN |
| Service/Power Release | 1/12/2021 | Approved | JOHN KLARIN |
| Final | 1/26/2021 | OK to Issue CofO | JOHN KLARIN |