1497 W SEPULVEDA ST 90732
Certificate Information: 1497 W SEPULVEDA ST 90732
- Application / Permit
- 19010-10000-04070
- Plan Check / Job No.
- B19LA19425
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 3-CAR GARAGE WITH A SECOND STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | JESSE ARELLANO |
| Green Plans Picked Up | 9/27/2019 | APPLICANT |
| Corrections Issued | 10/4/2019 | JESSE ARELLANO |
| Quality Review Completed | 10/10/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 11/5/2019 | APPLICANT |
| Plan Check Approved | 2/25/2020 | JESSE ARELLANO |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 4/8/2021 | JOHN KLARIN |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 12/12/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 12/12/2019 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 1/3/2020 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 1/16/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/11/2020 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 3/16/2020 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/16/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 3/16/2020 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 4/20/2020 | Approved | JOHN KLARIN |
| PLUMBING-Final | 4/20/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 4/20/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/23/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 4/23/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 4/23/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/23/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 4/23/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 4/28/2020 | Approved | JOHN KLARIN |
| Insulation | 5/27/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/10/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/15/2020 | Corrections Issued | JOHN KLARIN |
| Shower Pan | 6/15/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/17/2020 | Approved | BRIAN CHRISTIAN |
| PLUMBING-Rough | 10/19/2020 | Approved | JOHN KLARIN |
| Underground Mechanical | 10/26/2020 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 10/30/2020 | Partial Inspection | JOHN KLARIN |
| Pool Piping | 10/30/2020 | Partial Inspection | JOHN KLARIN |
| Special/Order Compliance | 10/30/2020 | Partial Inspection | JOHN KLARIN |
| Underground Mechanical | 10/30/2020 | Partial Approval | JOHN KLARIN |
| Enclosure/Fence | 1/4/2021 | Conditional Approval | JOHN KLARIN |
| Final | 1/19/2021 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 1/19/2021 | Approved | JOHN KLARIN |
| Green Building Final | 1/19/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 1/19/2021 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 1/19/2021 | Corrections Issued | JOHN KLARIN |
| Final | 2/8/2021 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 2/8/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 2/8/2021 | Approved | JOHN KLARIN |
| Final | 2/10/2021 | Corrections Issued | JOHN KLARIN |
| Final | 2/19/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/18/2021 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 3/30/2021 | Approved | JOHN KLARIN |
| Final | 4/7/2021 | OK to Issue CofO | JOHN KLARIN |