1532 N MOHAWK ST 90026
Certificate Information: 1532 N MOHAWK ST 90026
- Application / Permit
- 19010-10000-04068
- Plan Check / Job No.
- B19LA19389
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | JESSE ARELLANO |
| Corrections Issued | 10/3/2019 | JESSE ARELLANO |
| Quality Review Completed | 10/17/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 10/18/2019 | APPLICANT |
| Green Plans Picked Up | 10/18/2019 | APPLICANT |
| Applicant returned to address corrections | 11/13/2019 | JESSE ARELLANO |
| Plan Check Approved | 12/10/2019 | JESSE ARELLANO |
| Issued | 1/10/2020 | LADBS |
| CofO in Progress | 8/25/2022 | THOMAS LOGRASSO |
| Permit Finaled | 10/11/2022 | DEROLD HAUFF |
| CofO Issued | 10/11/2022 | DEROLD HAUFF |
| Permit Finaled | 10/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 10/31/2019 | JEREMY CARTER |
| Sewer availability | Cleared | 10/31/2019 | THOMAS LANG |
| Green Code | Cleared | 11/12/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 12/9/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/9/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 2/3/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/4/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/11/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 2/18/2022 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 2/28/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 3/29/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/29/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/20/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 4/20/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 4/25/2022 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 4/26/2022 | Conditional Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 5/2/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/2/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 5/2/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 5/2/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/19/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 5/19/2022 | Approved | THOMAS LOGRASSO |
| Gas Test | 6/3/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 8/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 8/1/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/18/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/18/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 8/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 8/18/2022 | Approved | THOMAS LOGRASSO |
| Reinforced Masonry Frame | 8/18/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 8/18/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/24/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 8/24/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/24/2022 | Approved | THOMAS LOGRASSO |