1875-1875 1/2 W 20TH ST 90007

Certificate Information: 1875-1875 1/2 W 20TH ST 90007

Application / Permit
19010-10000-04056
Plan Check / Job No.
B19LA19323
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED DUPLEX AT FRONT
Permit Issued
Issued on 3/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 SINA KHOSRAVI
Green Plans Picked Up 9/26/2019 APPLICANT
Corrections Issued 10/9/2019 SINA KHOSRAVI
Quality Review Completed 10/19/2019 YOUNG KIM
Building Plans Picked Up 10/22/2019 APPLICANT
Applicant returned to address corrections 11/22/2019 SINA KHOSRAVI
Applicant returned to address corrections 12/6/2019 SINA KHOSRAVI
Plan Check Approved 1/3/2020 SINA KHOSRAVI
Issued 3/2/2020 LADBS
CofO in Progress 5/13/2022 KATHRYN BUTTERWORTH
Permit Finaled 6/30/2022 DEROLD HAUFF
CofO Issued 6/30/2022 DEROLD HAUFF
Permit Finaled 6/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/29/2019 THOMAS LANG
ZI Cleared 10/29/2019 HELEN JADALI
Green Code Cleared 12/17/2019 DONALD CRICHLOW
Low Impact Development Cleared 12/17/2019 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 12/18/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 12/18/2019 ERIK BEASLEY
Sewer availability Cleared 12/18/2019 ERIK BEASLEY

Contact Information

Contractor J T K Construction Inc; Lic. No.: 1056422-B 4055 WILSHIRE BLVD #260      LOS ANGELES, CA 90010
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/1/2020 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/1/2020 Partial Approval KATHRYN BUTTERWORTH
Grounding or Bonding 5/1/2020 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 5/1/2020 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 5/7/2020 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/7/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 7/2/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 7/13/2020 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/17/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 8/17/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 8/17/2020 Approved KATHRYN BUTTERWORTH
Special/Order Compliance 8/17/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 8/21/2020 Approved KATHRYN BUTTERWORTH
Wood Frame 9/25/2020 Not Ready for Inspection DONALD CRICHLOW
Wood Frame 10/13/2020 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/22/2020 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/27/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 10/27/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/27/2020 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 10/27/2020 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 10/27/2020 Approved KATHRYN BUTTERWORTH
Insulation 10/30/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 11/6/2020 Approved KATHRYN BUTTERWORTH
Insulation 12/3/2020 Approved KATHRYN BUTTERWORTH
Sewer 3/31/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 4/9/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 7/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 7/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 7/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 7/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 7/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 12/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 12/29/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 12/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 12/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Final 12/29/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 12/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 12/29/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 12/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 12/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 1/10/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Final 1/10/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/14/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 2/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 2/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 2/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 3/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 3/2/2022 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 3/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 3/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 3/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 3/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 3/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 3/4/2022 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Final 3/4/2022 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Final 3/4/2022 Corrections Issued KATHRYN BUTTERWORTH
Service/Power Release 3/4/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 3/11/2022 Not Ready for Inspection STUART CHAPMAN
Final 3/11/2022 Corrections Issued STUART CHAPMAN
Gas Test 3/11/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 3/11/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 3/11/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 3/11/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 5/5/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Final 5/5/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/5/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 5/5/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 5/5/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 5/12/2022 Approved KATHRYN BUTTERWORTH
Final 5/12/2022 OK to Issue CofO KATHRYN BUTTERWORTH
HVAC-Final 5/12/2022 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 5/12/2022 Approved KATHRYN BUTTERWORTH
Service/Power Release 5/12/2022 Approved KATHRYN BUTTERWORTH