327 1/4 N WELCOME ST 90026

Certificate Information: 327 1/4 N WELCOME ST 90026

Application / Permit
19010-10000-04018
Plan Check / Job No.
B19LA19108
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELL W/ATTACHED 6 CAR GARAGE 2ND STORY 1185 SF UNIT
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 JESSE VIDUYA
Corrections Issued 10/1/2019 JESSE VIDUYA
Quality Review Completed 10/25/2019 JOSE RODRIGUEZ
Building Plans Picked Up 10/30/2019 APPLICANT
Applicant returned to address corrections 1/8/2020 JESSE VIDUYA
Green Plans Picked Up 4/24/2020 APPLICANT
Applicant returned to address corrections 6/16/2020 JESSE VIDUYA
Plan Check Approved 8/10/2020 JESSE VIDUYA
Issued 9/10/2020 APPLICANT
CofO in Progress 12/16/2022 THOMAS LOGRASSO
Permit Finaled 12/24/2022 DEROLD HAUFF
Permit Finaled 12/24/2022 DEROLD HAUFF
CofO Issued 12/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/27/2019 THAN WIN
Eng Process Fee Ord 176,300 Cleared 11/27/2019 THAN WIN
Sewer availability Cleared 11/27/2019 THAN WIN
Hydrant and Access approval Cleared 12/4/2019 JEREMY CARTER
Green Code Cleared 12/27/2019 JESSE VIDUYA
Low Impact Development Cleared 12/30/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/30/2019 EMIL KYUPELYAN
GPI Written Notices Cleared 7/23/2020 JESSE VIDUYA
Grading Pre-Inspection Cleared 7/23/2020 JESSE VIDUYA

Contact Information

Architect Song,, Michael; Lic. No.: C32566 5608 E PEABODY STREET      LONG BEACH, CA 90808
Contractor Union Lee Construction Inc; Lic. No.: 795671-B 3731 WILSHIRE BLVD SUITE 860      LOS ANGELES, CA 90010
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2020 Partial Approval STUART CHAPMAN
METHANE-Barrier 10/19/2020 Approved STUART CHAPMAN
METHANE-Subgrade 10/19/2020 Approved STUART CHAPMAN
Reinforced Masonry Frame 10/29/2020 Partial Approval ROBERT VORHIS
Masonry Wall/Backfill 11/16/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/1/2020 Approved DAVID CHAN
Deputy Reinf. Concrete 12/22/2020 No Access for Inspection ELMER BLAND
Deputy Steel/Welding 1/6/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 1/7/2021 Partial Approval COREY HUPP
HVAC-Rough 2/12/2021 Approved COREY HUPP
PLUMBING-Rough 2/12/2021 Approved COREY HUPP
ELECTRICAL-Rough 3/11/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/27/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 4/27/2021 Approved KATHRYN BUTTERWORTH
Insulation 4/27/2021 Approved KATHRYN BUTTERWORTH
METHANE-Rough 4/27/2021 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 4/27/2021 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 5/5/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/5/2021 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 1/14/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 1/14/2022 Corrections Issued THOMAS LOGRASSO
Gas Test 1/14/2022 Approved THOMAS LOGRASSO
HVAC-Final 1/14/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 1/14/2022 Corrections Issued THOMAS LOGRASSO
Service/Power Release 1/14/2022 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 1/14/2022 Approved THOMAS LOGRASSO
Deputy Steel/Welding 9/29/2022 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Final 10/26/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 10/26/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 10/26/2022 Approved THOMAS LOGRASSO
HVAC-Final 10/26/2022 Approved THOMAS LOGRASSO
PLUMBING-Final 10/26/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 10/26/2022 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 10/26/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 11/22/2022 Conditional Approval DONALD CRICHLOW
ELECTRICAL-Final 12/15/2022 Approved THOMAS LOGRASSO
Final 12/15/2022 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 12/15/2022 Approved THOMAS LOGRASSO