3145-3147 N BUDAU AVE 90032

Certificate Information: 3145-3147 N BUDAU AVE 90032

Application / Permit
19010-10000-03959
Plan Check / Job No.
B19LA18790
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SFD WITH 2-CAR GARAGE AND ADU ON BASEMENT PER SB229AND AB494. FULLY SPRINKLERED.
Permit Issued
Issued on 1/30/2023
Issuing Office
Metro
Current Status
Issued on 1/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/5/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 SAMUEL GONZALEZ
Corrections Issued 9/24/2019 SAMUEL GONZALEZ
Green Plans Picked Up 9/30/2019 APPLICANT
Quality Review Completed 10/15/2019 QUAN NGHIEM
Applicant returned to address corrections 3/2/2022 SAMUEL GONZALEZ
Building Plans Picked Up 3/7/2022 APPLICANT
Plan Check Approved 6/21/2022 SAMUEL GONZALEZ
Issued 1/30/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/14/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 11/14/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 11/14/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 11/14/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 7/29/2020 KURT CORRAL
Low Impact Development Cleared 1/11/2022 LONDY ALVARADO
"D" conditions Cleared 3/4/2022 MAXFIELD VERMY
"Q" conditions Cleared 3/4/2022 MAXFIELD VERMY
ZI Cleared 3/4/2022 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 4/19/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/25/2022 TREVOR QUAN
Sewer availability Cleared 4/25/2022 TREVOR QUAN
GPI Written Notices Cleared 6/6/2022 SAMUEL GONZALEZ
Grading Pre-Inspection Cleared 6/6/2022 SAMUEL GONZALEZ
Green Code Cleared 6/6/2022 VIVIAN LAO

Contact Information

Architect Van, Grunsven, Gregory D; Lic. No.: C36145 4819 ALGOMA AVENUE      LOS ANGELES, CA 90041
Contractor Owner-Builder       ,
Engineer Alina,, Alhakem A; Lic. No.: C53044 1061 YARDLEY WAY      CORONA, CA 92881

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/22/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 5/22/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 5/25/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 6/12/2023 Partial Inspection RUBEN SALAS
Footing/Foundation/Slab 7/5/2023 Corrections Issued RUBEN SALAS
Reinforced Concrete Frame 7/5/2023 Partial Inspection RUBEN SALAS
Structural Steel Frame 7/5/2023 Partial Inspection RUBEN SALAS
Deputy Reinf. Concrete 7/6/2023 Conditional Approval AMY COLIN
Reinforced Concrete Frame 7/7/2023 Not Ready for Inspection AMY COLIN
Structural Steel Frame 7/7/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 7/18/2023 Partial Approval AMY COLIN
Reinforced Concrete Frame 7/18/2023 Partial Approval AMY COLIN
Structural Steel Frame 7/18/2023 Not Ready for Inspection AMY COLIN
Deputy Reinf. Concrete 7/19/2023 Conditional Approval AMY COLIN
Deputy Steel/Welding 7/19/2023 Conditional Approval AMY COLIN
Deputy Reinf. Concrete 7/24/2023 Conditional Approval AMY COLIN
Masonry Wall/Backfill 7/25/2023 Corrections Issued AMY COLIN
Deputy Reinf. Masonry 7/27/2023 Conditional Approval AMY COLIN
Masonry Wall/Backfill 7/28/2023 Partial Approval AMY COLIN
Deputy Reinf. Masonry 8/1/2023 Partial Approval AMY COLIN
Deputy Reinf. Masonry 8/3/2023 Conditional Approval AMY COLIN
Masonry Wall/Backfill 8/4/2023 Not Ready for Inspection AMY COLIN
Deputy Reinf. Masonry 8/7/2023 Conditional Approval AMY COLIN
Masonry Wall/Backfill 8/8/2023 Approved AMY COLIN
Deputy Reinf. Masonry 8/9/2023 Conditional Approval AMY COLIN
Deputy Reinf. Masonry 8/10/2023 Conditional Approval AMY COLIN
PLUMBING-Rough 9/5/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 9/11/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 10/12/2023 Corrections Issued AMY COLIN
Green Building Rough 10/12/2023 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 10/12/2023 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 No Access for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Not Ready for Inspection AMY COLIN
Rough-Elec/Plmb/HVAC 12/19/2023 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 12/22/2023 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 12/22/2023 Not Ready for Inspection AMY COLIN
Green Building Rough 12/22/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 12/22/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 12/22/2023 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 12/22/2023 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 12/27/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 12/27/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Corrections Issued AMY COLIN
HVAC-Rough 12/27/2023 Approved AMY COLIN
PLUMBING-Rough 12/27/2023 Approved AMY COLIN
Deputy Wood Construction 1/24/2024 No Access for Inspection AMY COLIN
BUILDING-Rough-Frame 1/26/2024 Partial Approval AMY COLIN
Interior/Exterior Lathing 2/13/2024 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 2/21/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/21/2024 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 2/21/2024 Approved LILIANA PORTILLO
Insulation 2/26/2024 Corrections Issued JOSH MEISTER
Green Building Rough 3/8/2024 Approved LILIANA PORTILLO
Insulation 3/8/2024 Corrections Issued LILIANA PORTILLO
Insulation 3/15/2024 Approved LILIANA PORTILLO
Drywall Nailing 4/1/2024 Partial Approval JOSEPH MCGARRY
Drywall Nailing 9/26/2024 Approved BRENDAN MORELLI
Gas Test 9/26/2024 Not Ready for Inspection BRENDAN MORELLI
Gas Test 9/30/2024 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 9/30/2024 Not Ready for Inspection LILIANA PORTILLO
Gas Test 11/18/2024 Approved LILIANA PORTILLO
Service/Power Release 2/5/2025 Not Ready for Inspection LILIANA PORTILLO
Final 5/15/2025 Corrections Issued LILIANA PORTILLO
Gas Test 5/15/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/10/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 6/10/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 9/24/2025 No Access for Inspection LILIANA PORTILLO
HVAC-Final 9/24/2025 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/3/2026 Partial Approval ALIZAH MAYAGOITIA
Final 3/3/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 3/3/2026 Approved ALIZAH MAYAGOITIA
HVAC-Final 3/3/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 3/3/2026 Approved ALIZAH MAYAGOITIA
Service/Power Release 3/3/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 3/3/2026 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/7/2026 Corrections Issued LILIANA PORTILLO
Service/Power Release 7/7/2026 Not Ready for Inspection LILIANA PORTILLO