3525 W CRESTMONT AVE 90026

Certificate Information: 3525 W CRESTMONT AVE 90026

Application / Permit
19010-10000-03949
Plan Check / Job No.
B19LA18673
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ACCESSORY DWELLING UNIT W/ADJACENT COVERED PATIO/TRELLIS, NEW GRADING 125 CY CUT
Permit Issued
Issued on 5/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2019 APPLICANT
Assigned to Plan Check Engineer 9/20/2019 JESSE ARELLANO
Corrections Issued 9/24/2019 JESSE ARELLANO
Quality Review Completed 10/1/2019 BILL STUTSMAN
Building Plans Picked Up 10/8/2019 APPLICANT
Green Plans Picked Up 10/8/2019 APPLICANT
Applicant returned to address corrections 12/11/2019 JESSE ARELLANO
Applicant returned to address corrections 2/6/2020 JESSE ARELLANO
Plan Check Approved 3/6/2020 JESSE ARELLANO
Issued 5/13/2020 LADBS
CofO in Progress 12/21/2021 THOMAS LOGRASSO
Permit Finaled 1/14/2022 DEROLD HAUFF
CofO Issued 1/14/2022 DEROLD HAUFF
Permit Finaled 1/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/25/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 11/25/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 11/25/2019 THOMAS LANG
BHO/Hillside ordinance Cleared 11/25/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/25/2019 THOMAS LANG
Hydrant and Access approval Cleared 11/25/2019 JOHN CONNEALLY
Sewer availability Cleared 11/25/2019 THOMAS LANG
Green Code Cleared 1/30/2020 JESSE ARELLANO
Low Impact Development Cleared 2/5/2020 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/3/2020 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 9/16/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 10/19/2020 Corrections Issued HAMIK HARTOUNIAN
Masonry Wall/Backfill 11/9/2020 Corrections Issued COREY HUPP
Masonry Wall/Backfill 11/18/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/19/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 1/19/2021 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 1/19/2021 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 1/21/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/25/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Masonry Wall/Backfill 1/25/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 1/25/2021 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 1/25/2021 Approved HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 2/2/2021 Approved SCOTT FINNILA
Wood Frame 2/2/2021 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 2/22/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 2/22/2021 Approved HAMIK HARTOUNIAN
Masonry Wall/Backfill 2/22/2021 Approved HAMIK HARTOUNIAN
Insulation 3/4/2021 Partial Approval RUBEN SALAS
Drywall Nailing 3/11/2021 Corrections Issued RUBEN SALAS
Insulation 3/17/2021 Corrections Issued HAMIK HARTOUNIAN
Insulation 4/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Drywall Nailing 4/15/2021 Approved ROBERT MCDOWELL
Insulation 4/15/2021 Approved ROBERT MCDOWELL
Service/Power Release 4/15/2021 Approved ROBERT MCDOWELL
Masonry Wall/Backfill 5/10/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 8/4/2021 Partial Inspection THOMAS LOGRASSO
Final 11/3/2021 Corrections Issued STUART CHAPMAN
Green Building Final 11/3/2021 Corrections Issued STUART CHAPMAN
Reinforced Masonry Frame 11/3/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 11/3/2021 Approved STUART CHAPMAN
Structural Steel Frame 11/3/2021 Approved STUART CHAPMAN
Final 11/10/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 11/10/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 12/20/2021 Approved THOMAS LOGRASSO
Final 12/20/2021 OK to Issue CofO THOMAS LOGRASSO
HVAC-Final 12/20/2021 Approved THOMAS LOGRASSO
PLUMBING-Final 12/20/2021 Approved THOMAS LOGRASSO