164-166 W 80TH ST 90003
Certificate Information: 164-166 W 80TH ST 90003
- Application / Permit
- 19010-10000-03916
- Plan Check / Job No.
- B19LA18488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | RAHEL BEYENE |
| Corrections Issued | 9/25/2019 | RAHEL BEYENE |
| Green Plans Picked Up | 10/2/2019 | APPLICANT |
| Quality Review Completed | 10/8/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 10/16/2019 | APPLICANT |
| Plan Check Approved | 11/15/2019 | RAHEL BEYENE |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 8/4/2020 | FREDDIE RIVERA |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 10/18/2019 | ANNA VAN |
| Hydrant and Access approval | Cleared | 10/22/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 10/22/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/23/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | EMIL KYUPELYAN |
| Permit | Cleared | 10/29/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 10/29/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 10/30/2019 | VIVIAN LAO |
| Address approval | Cleared | 12/5/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/28/2020 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 1/31/2020 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/14/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 2/14/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 2/14/2020 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 2/14/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/14/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 2/18/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/7/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/7/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/7/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/7/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/7/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/11/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/11/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/11/2020 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/11/2020 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 5/11/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/19/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/19/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/4/2020 | Approved | FREDDIE RIVERA |
| Final | 8/4/2020 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 8/4/2020 | Approved | FREDDIE RIVERA |
| HVAC-Final | 8/4/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 8/4/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/4/2020 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 8/4/2020 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 8/4/2020 | Approved | FREDDIE RIVERA |