118-120 W 90TH ST 90003

Certificate Information: 118-120 W 90TH ST 90003

Application / Permit
19010-10000-03914
Plan Check / Job No.
B19LA18482
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 1/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 RACHEL BEYENE
Corrections Issued 9/24/2019 RACHEL BEYENE
Green Plans Picked Up 10/2/2019 APPLICANT
Quality Review Completed 10/8/2019 QUAN NGHIEM
Building Plans Picked Up 10/16/2019 APPLICANT
Plan Check Approved 11/18/2019 RAHEL BEYENE
Issued 1/6/2020 LADBS
CofO in Progress 8/4/2020 ENRIQUE MIRELES
Permit Finaled 11/3/2020 DEROLD HAUFF
CofO Issued 11/3/2020 DEROLD HAUFF
Permit Finaled 11/3/2020 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 10/18/2019 ANNA VAN
Green Code Cleared 10/22/2019 VIVIAN LAO
Hydrant and Access approval Cleared 10/22/2019 GEORGE SUCHAND
Low Impact Development Cleared 10/22/2019 RYAN HUDSON
Permit Cleared 10/22/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 10/22/2019 CELINA MORENO
Address approval Cleared 10/28/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 10/29/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/29/2019 EMIL KYUPELYAN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 1/29/2020 Conditional Approval WILLIAM ROSE
BUILDING-Rough-Frame 2/20/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 2/20/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 2/20/2020 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 2/20/2020 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval EUGENE CASSIDY
Insulation 2/21/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 3/25/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/28/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/28/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 4/28/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 4/28/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/28/2020 Partial Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 4/28/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/29/2020 Approved EUGENE CASSIDY
Green Building Rough 4/29/2020 Approved EUGENE CASSIDY
HVAC-Rough 4/29/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 4/29/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/29/2020 Approved EUGENE CASSIDY
Insulation 5/1/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/15/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/15/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 8/3/2020 Approved ENRIQUE MIRELES
Final 8/3/2020 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/3/2020 Approved ENRIQUE MIRELES
HVAC-Final 8/3/2020 Approved ENRIQUE MIRELES
PLUMBING-Final 8/3/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 8/3/2020 Approved ENRIQUE MIRELES
Smoke Detectors 8/3/2020 Approved ENRIQUE MIRELES
Final 8/4/2020 OK to Issue CofO ENRIQUE MIRELES