6000 W 6TH ST 1-3 90036
Certificate Information: 6000 W 6TH ST 1-3 90036
- Application / Permit
- 19010-10000-03913
- Plan Check / Job No.
- B19LA18479
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (26) Temporary Structure
- Work Description
- Installation of (3) state approved pre-fabricated modular trailers, sloped path, stairs and deck. (N) concrete pad. Temporary trailers. Permit to expire 6 months after issuance.
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Metro
- Current Status
- Issued on 10/29/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | HELEN NGUYEN |
| Corrections Issued | 12/12/2019 | HELEN NGUYEN |
| Plan Check Approved | 1/15/2020 | ADAM HEGAZI |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 5/4/2020 | JAMES POWERS |
| TCO Issued (Expire Date: 11-18-2020) | 5/22/2020 | DAVID TSAU |
| No Progress | 10/29/2020 | JAMES POWERS |
| TCO Issued (Expire Date: 04-27-2021) | 10/29/2020 | DAVID TSAU |
| TCO Issued (Expire Date: 09-28-2021) | 4/1/2021 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2019 | ELAINE LEI |
| City Hist. Cultural Monument | Cleared | 9/3/2019 | LAMBERT GIESSINGER |
| Highway dedication | Cleared | 9/3/2019 | ELAINE LEI |
| Historic monument | Cleared | 9/3/2019 | LAMBERT GIESSINGER |
| Metro Rail approval | Cleared | 9/24/2019 | CHIHARU SUZUKI |
| Hydrant and Access approval | Cleared | 10/1/2019 | JEREMY CARTER |
| DAS Clearance | Cleared | 12/12/2019 | CHIHARU SUZUKI |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 12/19/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/19/2019 | THOMAS LANG |
| ZI | Cleared | 12/19/2019 | ANNA VAN |
| "Q" conditions | Cleared | 12/20/2019 | ANNA VAN |
| Supp. Use District POD/CDO/TDO | Cleared | 12/20/2019 | IRIS WAN |
| ZA Case | Cleared | 12/20/2019 | ANNA VAN |
| ZI | Cleared | 12/20/2019 | ANNA VAN |
| Green Code | Cleared | 12/23/2019 | CHIHARU SUZUKI |
Contact Information
| Architect | Simeo,, James W; Lic. No.: C26166 | 1525 N HAYWORTH AVENUE UNIT 108 LOS ANGELES, CA 90046 |
| Contractor | G C X Llc; Lic. No.: 1045286-B | 29209 LARO DRIVE AGOURA HILLS, CA 91301 |
| Engineer | Powers,, Brian Frederick; Lic. No.: C75902 | 2090 WEST 31ST STREET LOS ANGELES, CA 90018 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 2/19/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 2/19/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Barrier | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Final | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Subgrade | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 2/19/2020 | SGSOV No Gas | RAFAEL ESPINOZA |
| Smoke Detectors | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 2/19/2020 | Approved | RAFAEL ESPINOZA |
| Final | 2/21/2020 | OK for TCO | JAMES POWERS |
| Final | 2/21/2020 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/21/2020 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 2/21/2020 | Off-Hour Fees Due | |
| Final | 5/4/2020 | OK to Issue CofO | JAMES POWERS |
| Special/Order Compliance | 10/26/2020 | Approved | JAMES POWERS |
| Special/Order Compliance | 3/31/2021 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 9/1/2021 | Approved | EDWIN GREGORYONA |