119-121 W 52ND ST 90037
Certificate Information: 119-121 W 52ND ST 90037
- Application / Permit
- 19010-10000-03912
- Plan Check / Job No.
- B19LA18478
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-story duplex with an attached 3-car garage.
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Green Plans Picked Up | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | HELEN NGUYEN |
| Corrections Issued | 9/16/2019 | HELEN NGUYEN |
| Quality Review Completed | 9/29/2019 | YOUNG KIM |
| Building Plans Picked Up | 10/8/2019 | APPLICANT |
| Plan Check Approved | 1/14/2020 | HELEN NGUYEN |
| Issued | 1/31/2020 | LADBS |
| CofO in Progress | 11/1/2020 | ROBERT MCDOWELL |
| Permit Finaled | 11/4/2020 | DEROLD HAUFF |
| CofO Issued | 11/4/2020 | DEROLD HAUFF |
| Permit Finaled | 11/4/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/15/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 10/18/2019 | JEREMY CARTER |
| Green Code | Cleared | 12/6/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 12/13/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | JEANIE LAM |
| ZI | Cleared | 12/20/2019 | RICHARD REASER |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/14/2020 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 4/15/2020 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/23/2020 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 4/23/2020 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 4/23/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 4/24/2020 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2020 | Partial Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 5/12/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/22/2020 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/22/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/22/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/22/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/22/2020 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/15/2020 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 7/15/2020 | Approved | COREY HUPP |
| Insulation | 7/20/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/20/2020 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 7/28/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/28/2020 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Not Ready | DAVID FEILER |
| ELECTRICAL-Final | 10/30/2020 | Approved | ROBERT MCDOWELL |
| Final | 10/30/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 10/30/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 10/30/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 10/30/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 10/30/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 10/30/2020 | Approved | ROBERT MCDOWELL |