119-121 W 52ND ST 90037

Certificate Information: 119-121 W 52ND ST 90037

Application / Permit
19010-10000-03912
Plan Check / Job No.
B19LA18478
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-story duplex with an attached 3-car garage.
Permit Issued
Issued on 1/31/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Green Plans Picked Up 9/11/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 HELEN NGUYEN
Corrections Issued 9/16/2019 HELEN NGUYEN
Quality Review Completed 9/29/2019 YOUNG KIM
Building Plans Picked Up 10/8/2019 APPLICANT
Plan Check Approved 1/14/2020 HELEN NGUYEN
Issued 1/31/2020 LADBS
CofO in Progress 11/1/2020 ROBERT MCDOWELL
Permit Finaled 11/4/2020 DEROLD HAUFF
CofO Issued 11/4/2020 DEROLD HAUFF
Permit Finaled 11/4/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/15/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/15/2019 ERIK BEASLEY
Sewer availability Cleared 10/15/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 10/18/2019 JEREMY CARTER
Green Code Cleared 12/6/2019 VIVIAN LAO
Low Impact Development Cleared 12/13/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/13/2019 JEANIE LAM
ZI Cleared 12/20/2019 RICHARD REASER

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2020 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/14/2020 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 4/15/2020 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 4/23/2020 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 4/23/2020 Partial Approval FREDDIE RIVERA
Pre-Inspection 4/23/2020 Not Ready for Inspection FREDDIE RIVERA
Insulation 4/24/2020 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Partial Approval FREDDIE RIVERA
Deputy Wood Construction 5/12/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 5/22/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 5/22/2020 Approved ENRIQUE MIRELES
Green Building Rough 5/22/2020 Approved ENRIQUE MIRELES
HVAC-Rough 5/22/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/22/2020 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 5/22/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 7/15/2020 Approved COREY HUPP
Verify Sprinkler Sign Off 7/15/2020 Approved COREY HUPP
Insulation 7/20/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/20/2020 Partial Approval SABAS ALONSO
Drywall Nailing 7/28/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/28/2020 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Not Ready DAVID FEILER
ELECTRICAL-Final 10/30/2020 Approved ROBERT MCDOWELL
Final 10/30/2020 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 10/30/2020 Approved ROBERT MCDOWELL
HVAC-Final 10/30/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 10/30/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 10/30/2020 Approved ROBERT MCDOWELL
Smoke Detectors 10/30/2020 Approved ROBERT MCDOWELL