246-248 E 23RD ST 90011

Certificate Information: 246-248 E 23RD ST 90011

Application / Permit
19010-10000-03910
Plan Check / Job No.
B19LA18472
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 92'-6"x25'-0", MAX HEIGHT 24'-2" 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE. SPRINKLER: NFPA-13D
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 JOHNNY WU
Green Plans Picked Up 10/8/2019 APPLICANT
Corrections Issued 10/16/2019 JOHNNY WU
Quality Review Completed 10/17/2019 JOSE RODRIGUEZ
Building Plans Picked Up 10/18/2019 APPLICANT
Plan Check Approved 12/24/2019 JOHNNY WU
Issued 1/23/2020 LADBS
CofO in Progress 8/21/2020 ROBERT MCDOWELL
Permit Finaled 9/3/2020 DEROLD HAUFF
CofO Issued 9/3/2020 DEROLD HAUFF
Permit Finaled 9/3/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/25/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 10/25/2019 JOHN CONNEALLY
Permit Cleared 10/25/2019 ERIK BEASLEY
Sewer availability Cleared 10/25/2019 ERIK BEASLEY
Address approval Cleared 10/29/2019 EMIL KYUPELYAN
Green Code Cleared 10/30/2019 KHEDER ALRAZAA
ZI Cleared 10/31/2019 SOPHIE GABEL-SCHEINBAU
Trees in Parkway Cleared 11/4/2019 JOHN KIM
Low Impact Development Cleared 11/6/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/6/2019 EMIL KYUPELYAN
Highway dedication Cleared 12/18/2019 ELENA LOPEZ

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2020 Conditional Approval JOAQUIN GREENOUGH
METHANE-Barrier 2/7/2020 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 2/7/2020 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 3/6/2020 Partial Approval JOAQUIN GREENOUGH
Wood Frame 3/6/2020 Approved JOAQUIN GREENOUGH
Insulation 3/20/2020 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/24/2020 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/21/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/1/2020 Conditional Approval FREDDIE RIVERA
Green Building Rough 5/1/2020 Approved FREDDIE RIVERA
HVAC-Rough 5/1/2020 Partial Approval FREDDIE RIVERA
METHANE-Rough 5/1/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 5/1/2020 Approved FREDDIE RIVERA
Sewer 5/1/2020 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 5/1/2020 Approved FREDDIE RIVERA
Insulation 5/5/2020 Approved SABAS ALONSO
Sewer 5/5/2020 Approved SABAS ALONSO
Drywall Nailing 5/11/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 5/11/2020 Approved SABAS ALONSO
Final 8/17/2020 Corrections Issued COREY HUPP
Gas Test 8/17/2020 Corrections Issued COREY HUPP
Green Building Final 8/17/2020 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Approved COREY HUPP
Smoke Detectors 8/17/2020 Approved COREY HUPP
BUILDING-Rough-Frame 8/21/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 8/21/2020 Approved ROBERT MCDOWELL
Final 8/21/2020 OK to Issue CofO ROBERT MCDOWELL
Footing/Foundation/Slab 8/21/2020 Approved ROBERT MCDOWELL
Gas Test 8/21/2020 Approved ROBERT MCDOWELL
HVAC-Final 8/21/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 8/21/2020 Approved ROBERT MCDOWELL
Service/Power Release 8/21/2020 Approved ROBERT MCDOWELL