421 E CARROLL CL 90291

Certificate Information: 421 E CARROLL CL 90291

Application / Permit
19010-10000-03819
Plan Check / Job No.
B19LA18113
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND UNCOVERED ROOF DECK
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
Issued on 9/23/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 FERNANDO FLORES
Corrections Issued 9/18/2019 FERNANDO FLORES
Quality Review Completed 10/1/2019 ARMEN JIVALAGIAN
Green Plans Picked Up 10/4/2019 APPLICANT
Applicant returned to address corrections 10/30/2019 FERNANDO FLORES
Applicant returned to address corrections 9/29/2020 FERNANDO FLORES
Applicant returned to address corrections 6/16/2021 FERNANDO FLORES
Plan Check Approved 8/6/2021 FERNANDO FLORES
Building Plans Picked Up 8/9/2021 APPLICANT
Issued 9/23/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/30/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/30/2019 JEANIE LAM
Hydrant and Access approval Cleared 10/30/2019 JEREMY CARTER
Permit Cleared 10/30/2019 JEANIE LAM
Sewer availability Cleared 10/30/2019 JEANIE LAM
Specific Plan Cleared 5/15/2020 COLLINS ALLAN
Construction near power lines Cleared 9/10/2020 WALTER RAMIREZ
Green Code Cleared 10/20/2020 FERNANDO FLORES
Low Impact Development Cleared 6/4/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/30/2021 JEANIE LAM
Coastal Zone Cleared 7/30/2021 KENTON TRINH
Miscellaneous Cleared 7/30/2021 KENTON TRINH
Specific Plan Cleared 7/30/2021 KENTON TRINH
ZI Cleared 7/30/2021 KENTON TRINH
City Hist. Cultural Monument Cleared 8/2/2021 LAMBERT GIESSINGER
Historic monument Cleared 8/2/2021 LAMBERT GIESSINGER

Contact Information

Architect Pini,, Paola; Lic. No.: C31886 1227 PALMS BLVD      VENICE, CA 90291
Contractor De Priest David; Lic. No.: 814310-B 3768 COUNTRY CLUB DRIVE      LONG BEACH, CA 90807
Engineer Jaramillo,, Mauricio Enrique; Lic. No.: C69957 578 WASHINGTON BLVD 743      MARINA DEL REY, CA 90292
Engineer Norton,, Steven A; Lic. No.: C90654 1417 ARMACOST AVENUE, #10      RIVERSIDE, CA 90025
Engineer Zangoli,, Fabio; Lic. No.: S6191 13245 FIJI WY UNIT J      MARINA DEL REY, CA 90292

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/1/2021 Corrections Issued JOHNNY MIRANDA
METHANE-Barrier 10/1/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Subgrade 10/1/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 11/15/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 11/17/2021 Partial Approval DAVID FEILER
METHANE-Subgrade 11/24/2021 Corrections Issued DAVID FEILER
METHANE-Subgrade 11/30/2021 Not Ready for Inspection DAVID FEILER
Deputy Methane Barrier 12/8/2021 No Access for Inspection DAVID FEILER
Deputy Methane Barrier 12/9/2021 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 1/21/2022 Not Ready for Inspection DAVID FEILER
METHANE-Barrier 1/21/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 1/27/2022 Partial Approval DAVID FEILER
METHANE-Barrier 1/27/2022 Not Ready for Inspection DAVID FEILER
Deputy Reinf. Concrete 2/3/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 3/2/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/7/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/14/2022 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 3/14/2022 Not Ready for Inspection DAVID FEILER
Deputy Steel/Welding 4/25/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Corrections Issued DAVID FEILER
Deputy Wood Construction 5/4/2022 No Access for Inspection DAVID FEILER
Deputy Wood Construction 5/31/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval JESUS RODRIGUEZ
Deputy Wood Construction 6/1/2022 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 10/4/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/18/2024 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 7/18/2024 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 7/22/2024 Conditional Approval HERBERT GIRON
Deputy Reinf. Concrete 7/26/2024 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 8/1/2024 Corrections Issued HERBERT GIRON
METHANE-Subgrade 8/1/2024 Partial Approval HERBERT GIRON
Deputy Methane Barrier 8/6/2024 Approved HERBERT GIRON
Deputy Reinf. Concrete 8/6/2024 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 8/6/2024 Partial Approval HERBERT GIRON
METHANE-Subgrade 8/6/2024 Approved HERBERT GIRON
PLUMBING-Rough 8/14/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 8/19/2024 Partial Approval TEMISTOCLES CAAL
Deputy Methane Barrier 8/28/2024 Conditional Approval HERBERT GIRON
METHANE-Barrier 8/29/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 9/12/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 9/16/2024 Approved HERBERT GIRON
Deputy Steel/Welding 9/25/2024 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 9/26/2024 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 10/15/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Corrections Issued HERBERT GIRON
Deputy Wood Construction 10/17/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval HERBERT GIRON
Deputy Wood Construction 11/4/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval HERBERT GIRON
Deputy Wood Construction 12/17/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 4/2/2025 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 4/9/2025 Approved JESUS RODRIGUEZ
Gas Test 4/9/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 4/9/2025 Approved JESUS RODRIGUEZ
METHANE-Rough 4/9/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/9/2025 Approved JESUS RODRIGUEZ
Deputy Wood Construction 5/2/2025 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 5/5/2025 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 5/9/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 5/13/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/20/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/23/2025 Approved JESUS RODRIGUEZ
Green Building Rough 6/23/2025 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/23/2025 Approved JESUS RODRIGUEZ
Insulation 7/8/2025 Corrections Issued JAYLIN GRAVITTE
Insulation 7/10/2025 Corrections Issued JESUS PINEDA
Insulation 7/14/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 7/29/2025 Approved JESUS RODRIGUEZ
Shower Pan 10/27/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/2/2025 Approved ANTHONY EGSON
Pre-Inspection 12/2/2025 Partial Inspection ANTHONY EGSON
Underground Mechanical 3/23/2026 Approved RUBEN RIVAS